Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Chandpur-s
1 RTIP-II/CHA/RPM-180 b) Kallayanpur UP (Baburhat G.C)-Upazila H/Q (Bishnadi) Road via Kasim Bazar. 5.6750 134.779   134.779 06/05/2015 30/05/2017 100 23/12/2018  
2 RTIP-II/CHA/GCM-2 a) Improvement of Mohamaya GCM 2.0000 85.816 Joint Venture of M/S. Aziz Brothers & Md. Mizanur Rahman Liton (JV of AB-MRL) 85.816 26/01/2015 28/12/2016 100 23/12/2018 Final
3 RTIP-II/CHA/RPM-43.1 Chandpur (Bagadi R&H)-Chandra GC 8.2500 162.804 Mizanur Rahman Liton 162.804 20/02/2013 11/02/2014 100 23/12/2018 Final
2 Faridganj
1 CHA/RPM-179 Rehabilitation and periodic Maintenance of Faridgonj R&H-Rampur GC-Sollakhali R&H Road (Ch-0+000 15+475km) 15.4750 43500000.000 Appolo Engineering Constraction Ltd 43500000.000 11/06/2015 30/04/2017 75 08/04/2019 Cancel
2 CHA/UNR-4 (A) Improvement of Latifgonj Bazar-Paschim Subidpur UP (Uttali) Road via Guher Bazar (Faridgonj Upazila). (B) Improvement of Khila Bazar (Khila Eidgah)-Shahrasti Bazar Road via Gabtoli (Shahrasti Upazila). (C) Improvement of Matlab-Master Bazar Ghosherhat Road (Matlab South Upazila) 13.4000 82130047.000 Mohammed Eunus & Brothers (Pvt.) Ltd 82130047.000 20/10/2014 30/06/2017 100 08/04/2019
3 RTIP-II/CHA/RPM-339 Faridganj GC-Chandra GC Road. 9.3500 661.475 Mohammed Eunus & Brothers (Pvt.) Ltd 661.475 19/02/2017 30/06/2018 94 23/12/2018  
4 RTIP-II/CHA/RPM-179 Faridgonj R&H-Rampur GC-Sollakhali R&H Road 15.4750 419.763 Appollo Engineering & Construction Ltd. 419.763 11/06/2015 30/04/2017 75 23/12/2018  
5 RTIP-II/CHA/RPM-43.2 Faridganj GC-Rupsha GC 5.4000 89.758 M/S. Aziz & Brothers 89.758 24/02/2013 05/05/2014 100 23/12/2018 Final
6 RTIP-II/CHA/UNR-4 a) Latifgonj Bazar-Paschim Subidpur UP (Uttali) Road via Guher Bazar 4.7000 274.180 M/S. Mohammad Eunus & Brothers (Pvt), Ltd 274.180 26/10/2014 30/06/2017 100 23/12/2018 Final
7 CHA/RPM-339 Rehabilitation and periodic Maintenance of Faridganj GC-Chandra GC Road at (Ch.0+000 - 9+350km) 9.3500 66147557.000 0 66147557.000 0 01/02/2017 NOA Issued
3 Haimchar
1 CHA/UZR-96.2 Improvement of Chandpur puran bazar (Nayani bazar)-Haimchar-Charbhairabi Road (ch. 6+953-12+083km) 5.1300 89452696.000 Mashiure Rahman Chowdhury 89452696.000 07/02/2017 14/03/2018 52 08/04/2019 WMM is on going
2 CHA/UZR-96.1 Improvement of Chandpur puran bazar (Nayani bazar)-Haimchar-Charbhairabi Road (ch. 0+ 000-6+953km) 6.9530 106702459.000 M/S Paradise Tra. & Mashiure Rahman JV 106702459.000 07/02/2017 14/03/2018 85 08/04/2019 WMM complete
3 RTIP-II/CHA/RPM-340 Haimchar Upazila H/Q-Madina market R&H via Ananda bazar Road. 5.1150 358.857 RAB-RC (PVT) Limited-M/S. Patwary Construction (JV) 358.857 06/02/2017 11/12/2017 100 23/12/2018 Final
4 RTIP-II/CHA/RPM-138 b) Charbharabi U.P Office-Shahorali Mour road 3.0500 72.510   72.510 25/05/2014 19/07/2015 100 23/12/2018  
5 RTIP-II/CHA/UZR-96.2 Chandpur Puran bazar-Haimchar-Charbhairabi Road (Haimchar Part) 5.1300 894.526 Moshiur Rahman Chowdhury 894.526 07/02/2017 30/06/2018 49 23/12/2018  
6 RTIP-II/CHA/UZR-96.1 Chandpur Puran bazar-Haimchar-Charbhairabi Road (Haimchar Part) 6.9530 1067.024 M/S. Paradise Traders & Moshiur Rahman Chowdhury JV 1067.024 07/02/2017 30/06/2018 81 23/12/2018  
4 Haziganj
1 RTIP-II/CHA/RPM-45.2 Balakhal-Rampur-Narayanpur 5.3500 157.455 M/S. Amena International 157.455 18/02/2013 08/12/2013 100 23/12/2018 Final
2 RTIP-II/CHA/UZR-45 Belchow-Ramchandrapur-Sameshpur-Nadighat road. 7.7500 1076.324 RBL-HB-ZT JV 1076.324 15/03/2015 16/12/2015 100 23/12/2018 Final
3 CHA/UZR-45 Improvement of Belchow-Ramchandrapur-Sameshpur-Nadighat road (Ch. 00-7+785km) 7.7480 107632405.000 RBL-HBZT JV 107632405.000 15/03/2015 05/09/2016 100 01/02/2017
5 Kachua
1 RTIP-II/CHA/RPM-337 Pathair-Mazigacha-Nandanpur bazar road. 4.9580 265.705 Pioneer Construction 265.705 06/02/2017 30/06/2018 59 23/12/2018  
2 RTIP-II/CHA/RPM-334 Sachar-Bardail-Nayergoan road (Kachua portion) 5.8300 307.208 A.A Trading Construction 307.208 30/06/2016 12/08/2017 41 23/12/2018  
3 RTIP-II/CHA/RPM-181 b) Asrafpur (Kathal bagan)-Jagatpur bazar road. Via Asrafpur UP 3.8250 117.843   117.843 14/06/2015 10/02/2019 0 23/12/2018  
4 RTIP-II/CHA/RPM-139 a) Kachua-Raghunathpur G.C road 6.5000 112.710 JV of Tania & Shahid 112.710 01/04/2014 11/06/2015 100 23/12/2018 Final
5 CHA/RPM-334 Rehabilitation and periodic Maintenance of Sachar-Bardali-Nayergoan Road (Kachua Portion) at (Ch.0+000 - 5+830km) 5.8300 30720866.000 A A Trading Corporation 30720866.000 30/06/2016 30/06/2017 20 31/01/2017 On going
6 Matlab (dakshin)
1 Cha/RPM-181 Rehabilitation and Periodic Maintenance of (a) Nayergaon-Bordol Shachar via Pitambordi Road (Matlab South part) (Ch. 0+700 to 6+065km) Upazila: Matlab Dakshin, Chandpur. (b) Asrafpur (Kathal bagan)-Jagatpur bazar road via Asrafpur UP road (Ch. 0+000 to 3+825km) Upazila: Kachua, Chandpur 9.1900 33171838.000 M/S. R-TA Enterprise 33171838.000 14/06/2015 30/04/2019 69 08/04/2019 Work on going
2 RTIP-II/CHA/RPM-341 Bahari Arong-Munshirhat Road 4.7000 280.067 M/S. Sarkar Construction-M/S. Zakir Enterprise (JV) 280.067 06/02/2017 30/12/2017 100 23/12/2018  
3 RTIP-II/CHA/RPM-181 a) Nayergaon-Bordol Shachar via pitambordi Road (Matlab South part) 5.3650 213.875 M/S. R-TA Enterprise 213.875 14/06/2015 10/02/2019 0 23/12/2018  
4 RTIP-II/CHA/GCM-2 b) Improvement of Chengarchar GCM 2.0000 79.636   79.636 26/01/2015 28/12/2016 100 23/12/2018  
5 RTIP-II/CHA/RPM-140 Machuakhal-Narayanpur-Balakhal road 8.8100 158.365 Mohammed Eunus & Brothers (Pvt.) Ltd. 158.365 01/04/2014 01/04/2015 100 23/12/2018  
6 RTIP-II/CHA/UNR-4 c) Matlab-Master Bazar Ghosherhat Road 4.5280 321.890   321.890 26/10/2014 30/06/2017 100 23/12/2018  
7 CHA/RPM-140 Rehabilitation and periodic Maintenance of Machuakhal-Narayanpur-Balakhal road (Ch. 1+425 to 11+880km) 8.8100 15836569.000 Mohammed Eunus & Brothers (Pvt.) Ltd. 15836569.000 01/04/2014 30/06/2015 100 01/02/2017
7 Matlab (uttar)
1 CHA/RPM-182 Rehabilitation and periodic Maintenance of Matlab Bazar-Sengarchar Road (Ch-0+000 to 12+335km) 12.3350 71500000.000 M/S Shahid & Brothers 71500000.000 06/07/2015 18/01/2017 100 08/04/2019
2 RTIP-II/CHA/RPM-338 Gazra bazar-Pachani Chowrasta bazar-Eklashpur UP Office road. 2.7500 195.842 M/S. Confidence International & M/S. M.H Bablu (JV) 195.842 01/02/2017 30/06/2018 100 23/12/2018  
3 RTIP-II/CHA/RPM-335 Sujatpur bazar-Pathanbazar-Shatnal UP Office road. 12.4500 437.599 M/S. Asif Traders 437.599 08/07/2016 20/09/2017 100 23/12/2018 Final
4 RTIP-II/CHA/RPM-182 Matlab Bazar-Sengarchar Road. 12.3350 715.417 M/S. Shahid Brothers 715.417 06/07/2015 28/01/2017 100 23/12/2018 Final
5 RTIP-II/CHA/RPM-138 a) Senganchar-Eklaspur road 8.1000 142.974 M/S. Rathindra Chandra Roy & Md. Mizanur Rahman Liton Joint Venture (JV of RCR-MRL) 142.974 25/05/2014 19/07/2015 100 23/12/2018 Final
6 RTIP-II/CHA/RPM-44.2 Senganchar-Kalirbazar 7.5000 127.353 Mohammad Ali Zinnah 127.353 17/02/2013 16/02/2014 100 23/12/2018 Final
7 RTIP-II/CHA/RPM-44.1 Senganchar-Kalirbazar 6.0000 149.399 M/S. Akkas Construction 149.399 18/02/2013 15/02/2014 100 23/12/2018 Final
8 CHA/RPM-335 Rehabilitation and periodic Maintenance of Sujatpur bazar-Pathan bazar-Shatnal UP office Road at (Ch.0+000 - 12+450km) 12.4500 43759913.000 M/S Asif Trading 43759913.000 08/07/2016 08/07/2017 30 31/01/2017 On going
8 Shahrasti
1 CHA/UZR-49 Improvement of Thakur Bazar (U.H.C) GC-Jadabpur R&H Net work (ch. 5+ 375-7+125km) 1.7500 20969834.000 Appolo Engineering Constraction Ltd 20969834.000 12/11/2015 07/08/2017 61 08/04/2019 Cancel
2 RTIP-II/CHA/RPM-336 Chitoshi (w) U.P office-Shampur bazar road via Ugharia bazar 3.9370 255.641 Ahsan Habib Arun 255.641 21/03/2017 30/11/2018 100 23/12/2018  
3 RTIP-II/CHA/RPM-180 a) Shahid Anwar Hossain Road (Mehar North Up office-Debkara Bazar Via Bholdighi bazar) 5.3200 142.188 AB-MRL 142.188 06/05/2015 30/05/2017 100 23/12/2018 Final
4 RTIP-II/CHA/RPM-45.1 Tamta U.P H/Q-Khorda Fery Ghat 3.5200 60.655 M/S. Zia Enterprise 60.655 24/02/2013 17/02/2014 100 23/12/2018 Final
5 RTIP-II/CHA/UNR-4 b) Khila Bazar (Khila Eidgah)-Shahrasti Bazar Road via Gabtoli 3.6680 225.229   225.229 26/10/2014 30/06/2017 100 23/12/2018  
6 RTIP-II/CHA/UZR-49 Thakur bazar (U.H.C) GC-Jadabpur R& H Net work. 1.7500 209.698 Appollo Engineering and Construction Ltd. 209.698 12/11/2015 22/04/2017 61 23/12/2018  
Total : 306.4650 (Km) 711534158.57 (Lac) 711534158.57 (Lac)