Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Belabo
1 RTIP-II/NAR/RPM-369 Baznabo UP office-Gangajali Hat Road. 3.5460 93.165 M/S. Bangladesh Development Corporation 93.165 18/02/2017 31/01/2018 100 23/12/2018  
2 RTIP-II/NAR/RPM-241 a) Belabo-Hatirdia Road 7.0000 194.317 M/S. Bishwa Bandhu International & Belabo Traders JV 194.317 07/05/2015 03/05/2016 100 23/12/2018 Final
3 RTIP-II/NAR/RPM-111 b) Patuli UP office-Harishangoan bazar road 7.2200 147.406   147.406 09/03/2014 07/03/2015 100 23/12/2018  
4 RTIP-II/NAR/RPM-28.1 Jangli Shibpur bazar-Dhukandi-Baznabo UP office 10.1250 176.649 M/S. Mithamon Builders 176.649 26/03/2013 10/02/2014 100 23/12/2018 Final
2 Monohardi
1 RTIP-II/NAR/RPM-394 Barachapa-Patoli R&H Road. 5.4000 198.568 JV of M/S. Faruk Traders & M/S. Suchi Enterprise 198.568 25/04/2017 11/01/2018 100 23/12/2018 Final
2 RTIP-II/NAR/RPM-241 b) Chalakchar bazar-Kotiadi GC 8.5600 497.224   497.224 07/05/2015 03/05/2016 100 23/12/2018  
3 RTIP-II/NAR/GCM-34 Improvement of Hatirdia GCM 1.0000 116.473 M/S. Haque Enterprise 116.473 11/04/2016 13/06/2017 100 23/12/2018 Final
4 RTIP-II/NAR/RPM-114 Chalakchar bazar-Belabo Border road 9.7400 233.067 M/S. Faruk Traders 233.067 26/02/2014 25/09/2015 100 23/12/2018 Final
5 RTIP-II/NAR/RPM-29.2 Monohordi H/Q-Drinerghat R&H 6.5720 120.752 M/S. Tapash Traders, M/S. Parvez Enterprise & M/S. Faruk Traders Joint Venture 120.752 26/03/2013 28/11/2013 100 23/12/2018 Final
6 RTIP-II/NAR/RPM-29.1 Monohordi H/Q-Drinerghat R&H 6.0000 157.704 M/S. Mahbub Alam 157.704 27/03/2013 15/06/2014 100 23/12/2018 Final
3 Narshingdi-s
1 RTIP-II/NAR/RPM-309 Mohisasura UP Office-Madhabdi GC Rd. 2.9000 112.972 M/S N.H.B. Traders 112.972 24/07/2016 03/05/2017 100 23/12/2018 Final
2 RTIP-II/NAR/RPM-242 a) Madhabdi GC-Gopaldi GC Road Via Balapur GC. 8.6700 205.364 M/S. Faruk Traders & M/S. Amirgonj Builders JV 205.364 02/05/2015 31/12/2016 100 23/12/2018  
3 RTIP-II/NAR/PBMC-7.1 a) Narsingdi-Amirgonj GC Rd. 4.5000 617.731 JV of M/S. Alam Construction & M/S. N. H. B. Traders (AC-NT JV) 617.731 10/06/2015 13/05/2020 100 23/12/2018  
4 RTIP-II/NAR/RPM-111 a) Kathalia UP Office-Rangpur Bazar via Fozurkandi Bazar Road 4.5000 60.965 M/S. Udayan Enterprise 60.965 09/03/2014 07/03/2015 100 23/12/2018 Final
5 RTIP-II/NAR/UNR-26 a) Shilmandi U.P Office (South Shilmandi)-Shilmandi Natun Bazar Road. 1.8250 135.029 M/S. Mominul Hoque 135.029 24/04/2014 09/03/2016 100 23/12/2018 Final
4 Palash
1 RTIP-II/NAR/RPM-370 Charnagardi GC-Purandia RHD Via Sukundirghat 8.3660 285.593 Marco International & M/S. Nazmul Haque Enterprise JV (Marco nd Nazmul Haque JV) 285.593 01/02/2017 30/11/2017 100 23/12/2018  
2 RTIP-II/NAR/RPM-242 b) Khanepur bazar-Charsindur UP Via Fouji Jute Mill. 4.3000 98.497   98.497 02/05/2015 31/12/2016 100 23/12/2018  
5 Raipura
1 RTIP-II/NAR/UNR-26-STR-5 Construction of 69m long RCC girder bridge at Ch. 7+485km on Mirzapur UP Office-Chanderkandi UP Office road 69.0000 308.904 M/S. Islam Traders 308.904 08/03/2015 30/06/2018 100 23/12/2018  
2 RTIP-II/NAR/PBMC-7.2 b) Radhagonj GC to Hasnabad GC via Adiabad Collage Road 8.1620 0.000   0.000 10/06/2015 13/05/2020 100 23/12/2018  
3 RTIP-II/NAR/PBMC-7.1 b) Gopinathpur-Hasnabad upto Thana Border Rd. 14.9200 0.000   0.000 10/06/2015 13/05/2020 100 23/12/2018  
4 RTIP-II/NAR/RPM-112 Sreerampur G.C-Nilkuti R&H road 12.6780 326.361 M/S. Udayan Enterprise 326.361 26/02/2014 20/04/2015 100 23/12/2018 Final
5 RTIP-II/NAR/RPM-30.2 Sreerampur Rail gate R&H-Monipura GC 7.4610 291.241 M/S. Ataur Rahman Khan 291.241 26/03/2013 18/03/2014 100 23/12/2018 Final
6 RTIP-II/NAR/RPM-30.1 Sreerampur Rail gate R&H-Monipura GC 9.0000 266.682 M/S. Udayan Enterprise 266.682 26/03/2013 28/11/2013 100 23/12/2018 Final
7 RTIP-II/NAR/UNR-53 Mahamudabad R&H-Dulatkandi-Algi Bazar 8.6710 1151.212 M/S. M.A. Engineering & Dhaly Construction Ltd, [(MAE & DCL(JV)] 1151.212 02/01/2016 18/01/2019 100 23/12/2018  
8 RTIP-II/NAR/UNR-26 b) Mirzapur U.P. Office-Chanderkandi U.P. Office Road. 3.3750 261.336   261.336 24/04/2014 09/03/2016 100 23/12/2018  
6 Shibpur
1 RTIP-II/NAR/RPM-310 Sristigar R&H-Radhagonj bazar via Kutir bazar. 3.8500 113.336 M/S. Parvaz Enterprise & Amirgonj Builders JV, (Amirgonj & Parvaz JV) 113.336 03/10/2016 01/06/2017 100 23/12/2018 Final
2 RTIP-II/NAR/RPM-243 Ayubpur UP - Putia UP Via Jangalia Bazar, Bhurbhuria. 10.0000 310.500 M/S. Faruk Traders 310.500 02/05/2015 13/12/2016 100 23/12/2018 Final
3 RTIP-II/NAR/RPM-113 Shibpur - Charsindur road 9.1000 144.464 M/S. Faruk Traders 144.464 27/01/2014 12/09/2014 100 23/12/2018 Final
4 RTIP-II/NAR/RPM-28.2 Gazaria UP - Jangalia bazar Via Bariatola 4.7000 100.500 M/S. Mominul Haque 100.500 26/03/2013 10/11/2013 100 23/12/2018 Final
Total : 261.1410 (Km) 6726.01 (Lac) 6726.01 (Lac)