Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Balaganj
1 RTIP-II/SYL/RPM-270 Osmanpur UP-Khalermukh Bazar-Madrasha Bazar-Khondokar Bazar-Nazir Bazar Road 14.5800 312.860 M/S. M.A. Engineering & M/S. Khan & Sons JV (M/S. MA- Khan JV) 312.860 28/05/2015 27/12/2016 100 23/12/2018 Final
2 RTIP-II/SYL/PBMC-9.3 c) Balaganj bazar GC-Fenchuganj GC road (Balagonj part) 15.5510 311.329   311.329 07/06/2016 06/06/2021 100 23/12/2018  
3 RTIP-II/SYL/RPM-158 Doyameer GC-Dewanbazar GC road 7.0000 218.709 M/S. Puspa Construction & M/S. J.R. Enterprise JV 218.709 10/02/2014 19/03/2017 100 23/12/2018 Final. Cancelled by XEN on 07/03/17, Memo. GjwRBwW/wbtcÖt/wm‡jU/AviwUAvBwc-2/10-14/2013/856
4 RTIP-II/SYL/UZR-34.2 Kasrupur bazar GC-Pailanpur-Balaganj GC Road. 6.5200 786.653 Meghna Structural Engineering Ltd. 786.653 27/01/2016 13/06/2017 26 23/12/2018  
5 RTIP-II/SYL/UZR-34.1 Kasrupur bazar GC-Pailanpur-Balaganj GC Road. 6.0000 838.871 Meghna Structural Engineering Ltd. 838.871 08/11/2015 29/07/2017 43 23/12/2018  
2 Beanibazar
1 RTIP-II/SYL/RPM-324A Golapgonj-Amura-Mathiura-Beanibazar Road (Beanibazar Portion) (Remaining work) 5.0100 314.808 M/S. Suhag Enterprise & Md. Zafar Ahmed Gilman JVCA 314.808 07/02/2018 31/12/2018 45 23/12/2018  
2 RTIP-II/SYL/RPM-324 Golapgonj-Amura-Mathiura-Beanibazar Rd. (Beanibazar Portion) 317.587 A.K.M. Delwar Hossain & Md. Nayeb Ali Khan JV [(Delwar Hossain-NK (JV)] 317.587 24/05/2016 23/05/2017 15 23/12/2018 Cancelled ??
3 RTIP-II/SYL/UZR-33 Beanibazar-Sarupar GC- Sylhetypara RHD-Gojukata Road. 6.4640 1153.023 Rana Builders (Pvt) Ltd, & Md. Jahangir Alam JV, (RBL_MJAJV) 1153.023 17/12/2015 31/12/2018 94 23/12/2018 Work cannot completed by Apr, 2019 - XEN, Syleht informed vide memo 3755, Dt: 14/11/18
3 Biswanath
1 RTIP-II/SYL/RPM-386 RHD Sylhet-Kamal bazer-Ponaulla bazer-Nowagow-Biswanath GC Road. 10.4070 424.514 Zafar Ahemd Gilman & M/S. Suhag Enterprise JVCA 424.514 12/02/2017 25/04/2018 100 23/12/2018  
2 RTIP-II/SYL/RPM-159 Biswanath GC-Perer bazar GC-Jagannathpur HQ road (Biswanath Part) 15.9070 484.440 M/S. Md. Taibur Rahman & M/S. M.A. Engineering JV 484.440 29/04/2014 25/02/2016 100 23/12/2018 Final
3 RTIP-II/SYL/UZR-36 RHD Rampasa-Lamachalk-Bairagir bazar GC Road. 3.0850 706.502 M/S. Ataur Rahman Khan 706.502 24/12/2015 28/02/2018 45 23/12/2018  
4 Dakshin surma
1 RTIP-II/SYL/RPM-268 a) Jalalpur GC-Mogla bazar RHD Road. 6.3400 187.293 M/S. M.A. Engineering & M/S. Khan & Sons JV (M/S. MA- Khan JV) 187.293 28/05/2015 31/12/2016 100 23/12/2018 Final
2 RTIP-II/SYL/RPM-71 Sylhet-Kamalbazar-Ponaullahbazar-Biswanath GC Road (Sadar portion) 7.7000 175.252 A. K. M. Delewar Hossain 175.252 13/03/2013 24/05/2014 100 23/12/2018 Final
5 Fenchuganj
1 RTIP-II/SYL/RPM-268 b) Fenchugonj GC-Gillachara GC road. 5.5040 107.064   107.064 28/05/2015 31/12/2016 100 23/12/2018  
2 RTIP-II/SYL/PBMC-9.3 d) Balaganj-Fenchuganj GC road (Fenchuganj portion) 2.0500 14.351   14.351 07/06/2016 06/06/2021 100 23/12/2018  
6 Golapganj
1 RTIP-II/SYL/PBMC-9.1 b) Sylhet-Gasbari GC-Kanaighat Rd (Golapgonj Portion) 11.7600 204.867   204.867 01/07/2015 30/06/2020 100 23/12/2018  
2 RTIP-II/SYL/RPM-160 b) Lakhanabondh UP-Fulshaind-Porokayestha bazar road 7.2010 202.909   202.909 17/02/2014 31/12/2015 100 23/12/2018  
3 RTIP-II/SYL/RPM-72.2 Sylhet-Gasbari GC-Kanaighat Rd (Golapgonj Portion) 6.7000 151.265 Shibabrata Bhowmick, M/S. Puspa Construction & Mahmudul Hossain Tufa Joint Venture 151.265 13/03/2013 12/03/2014 100 23/12/2018 Final
4 RTIP-II/SYL/RPM-72.1 Sylhet-Gasbari GC-Kanaighat Rd (Golapgonj Portion) 5.0000 108.522 Shibabrata Bhowmick, M/S. Puspa Construction & Mahmudul Hossain Tufa Joint Venture 108.522 13/03/2013 12/03/2014 100 23/12/2018 Final
7 Gowainghat
1 RTIP-II/SYL/RPM-269 Salutikar Bazar-Gowainghat G. C. Road. 23.8900 1727.836 RAB-RC (PVT) LIMITED & Md. Jahangir Alam JV, (RABRC-M.JAJV). 1727.836 18/02/2016 10/02/2019 100 23/12/2018  
8 Kanaighat
1 RTIP-II/SYL/PBMC-9.2 Sylhet-Gachbari GC-Kanighat Upazila H/Q Road (Kanaighat part) 34.9980 1283.051 JV of M/S Mahbub Enterprise & M/S Priti Enterprise 1283.051 01/07/2016 30/06/2021 100 23/12/2018  
2 RTIP-II/SYL/UZR-35.2 Haripur GC-Gachbari GC Road. (Kanaighat part) 4.4490 991.174 JV of Mr. Sujib Ranjan Das & M/S. Belal Enterprise (Shojib Belal_JV) 991.174 01/11/2015 23/07/2017 55 23/12/2018  
3 RTIP-II/SYL/UZR-35.1 Haripur GC-Gachbari GC Road. (Kanaighat part) 2.6310 799.208 JV of M/S. Mahbub Enterprise & M/S. Priti Enterprise (JV of ME-PE) 799.208 28/01/2016 30/06/2018 85 23/12/2018  
9 Sylhet-s
1 RTIP-II/SYL/RPM-325 RHD (Salutikar)-Shaheber bazar-Horipur Rd.(Sadar portion) 6.7800 487.363 M/S. Ishaque & Sons Construction, M/S. Meghna Enterprise & M/S. F. Islam Construction [(IC-ME-FIC (JV)] 487.363 24/05/2016 28/02/2018 100 23/12/2018  
2 RTIP-II/SYL/PBMC-9.1 a) Sylhet-Gachbari-Kanaighat Rd (Sadar portion). 6.8480 119.296 M/S. Shahan Enterprise 119.296 01/07/2015 30/06/2020 100 23/12/2018  
3 RTIP-II/SYL/RPM-160 a) Sylhet-Gachbari-Kanaighat road (Sadar portion) 6.8480 101.335 M/S. Zafar Ahmed Gilman & M/S. MLR Trading JV 101.335 17/02/2014 31/12/2015 100 23/12/2018 Final
4 RTIP-II/SYL/RPM-73 Shiber bazar GC-Companigonj RHD Road (Sadar Portion). 6.5000 186.303 M/S. Ishaque & Sons Construction, M/S. Meghna Enterprise and M/S. F. Islam Construction Joint Venture 186.303 13/03/2013 25/06/2014 100 23/12/2018 Final
10 Zakiganj
1 RTIP-II/SYL/UNR-57-STR-31 Construction of 60 m RCC girder bridge on Mayakhali Bazar-R&H (Barohal UP Office) Via Hatubill Madrasha Road at Ch. 1+474 km 60.0000 423.503 Consonance Engineers & Builders 423.503 27/01/2016 28/02/2018 100 23/12/2018  
2 RTIP-II/SYL/GCM-28 Improvement of Laxmibazar GCM 1.0000 76.880 M/S. Progoti Traders 76.880 01/11/2015 10/05/2017 100 23/12/2018 Final
3 RTIP-II/SYL/RPM-161 Zakigonj (GC)-Laxmibazar (GC)-Dubagbazar (GC) road 21.9900 750.425 Md. Shamsur Rahman & M/S. Mahbub Enterprise JV [SR-ME (JV)] 750.425 18/06/2014 22/04/2017 100 23/12/2018 Final
4 RTIP-II/SYL/RPM-70.2 Atgram (R&H)-Zakigonj (G.C) 6.9950 234.973 Md. Shamsur Rahman & M/S. A. K. M. Shahabuddin Sk. Joint Venture 234.973 13/03/2013 12/03/2014 100 23/12/2018 Final
5 RTIP-II/SYL/RPM-70.1 Atgram (R&H)-Zakigonj (G.C) 5.0000 168.534 Project Builders Limited 168.534 09/07/2013 05/09/2014 100 23/12/2018 Final
6 RTIP-II/SYL/UNR-70.2 Manikpur UP Office (Noor Pur)-Babur Bazar via Mirzarchak-Tirashi-Gachua-Maizbondh Road 5.4250 711.529 M/S. Hasan Enterprise 711.529 12/02/2017 25/04/2018 56 23/12/2018  
7 RTIP-II/SYL/UNR-70.1 Manikpur UP Office (Noor Pur)-Babur Bazar via Mirzarchak-Tirashi-Gachua-Maizbondh Road 5.4000 625.868 M/S. Belal Enterprise & Md. Atiqur Rahman JV, (BE&AT_JV) 625.868 15/01/2017 14/01/2018 20 23/12/2018  
8 RTIP-II/SYL/UNR-57 Mayakhali Bazar-R&H(Barohal UP Office) Via Hatubill Madrasha Road. 4.2280 411.132 Md. Shamsur Rahman & Md. Helal Uddin [(SR-HU (JV)] 411.132 15/12/2015 31/12/2018 57 23/12/2018  
Total : 345.7610 (Km) 16119.23 (Lac) 16119.23 (Lac)