Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Barlekha
1 RTIP-II/MOU/GCM-9 Improvement of Chandgram GCM 1.0000 101.648 Zafar Ahmed Gilman 101.648 14/12/2014 29/05/2016 100 23/12/2018 Final
2 RTIP-II/MOU/RPM-165 Dasherbazar-Basirpur RHD via Kanongobazar Azimganj road 16.1500 335.622 Md. Habibur Rahman & M/S. Haque Construction (M.H. JV) 335.622 28/04/2014 30/04/2016 100 23/12/2018 Final
3 RTIP-II/MOU/UNR-71.1 Dakshinshahbazpur UP Office - Bobarthal bazar Via Gandai bazar road. 5.0000 542.526 Md. Muhibur Rahman 542.526 17/04/2017 30/11/2018 78 23/12/2018  
4 RTIP-II/MOU/UNR-37 Kathaltali-Madhabkunda Road 7.0000 710.885 Joint Venture of M/S. Ruhul Amin Bhuiyan & M/S. Muhibur Rahman 710.885 26/01/2014 29/03/2016 100 23/12/2018 Final
2 Juri
1 RTIP-II/MOU/RPM-227 b) Dasherbazar-Basirpur RHD via Kanongobazar Azimganj Rd 5.4000 167.010 Md. Nurul Alam Numan & Suheb Ahmed JVCA 167.010 26/04/2015 01/01/2017 100 23/12/2018  
3 Kamalganj
1 RTIP-II/MOU/RPM-398 Adampur G.C.-Bhanugach G.C. Road via Islampur-Madhabpur . 7.0450 565.115 Dolly Construction Ltd-Infratech (JV) 565.115 09/08/2017 30/06/2018 100 23/12/2018  
2 RTIP-II/MOU/RPM-304 Kamalgonj-Adampur Road . 8.5000 405.192 M/S. Haque Construction 405.192 14/05/2016 30/09/2017 100 23/12/2018 Final
3 RTIP-II/MOU/RPM-226 Adampur GC-Bhanugach GC Road via Islampur-Madhabpur 12.1000 285.765 Md. Nurul Alam Numan & Suheb Ahmed JVCA 285.765 26/04/2015 18/06/2017 100 23/12/2018 Final
4 RTIP-II/MOU/RPM-163 a) Chaytraghat-Nayabazar via Shahidnagar road 8.5000 333.005 Ohiduzzaman Chowdhury 333.005 04/04/2014 15/03/2015 100 23/12/2018 Final
5 RTIP-II/MOU/RPM-66.1 Kamolgonj HQ.-Munshibazar G.C 7.0000 273.484 Tufaiel Ahmed 273.484 14/03/2013 28/05/2014 100 23/12/2018 Final
6 RTIP-II/MOU/UNR-22A Adampur UP Office-Alinagarbazar Road via Changaon Jangalia 0.7420 148.242 Mohammad Ali & Bakshi Jubaer Ahmed JV [(M.J. (JV)] 148.242 26/02/2017 14/01/2018 100 23/12/2018  
7 RTIP-II/MOU/UNR-22 Adampur UP Office-Alinagarbazar Road via Changaon Jangalia 11.2600 773.636 M/S. Md. Jamil Iqbal & M/S. Haque Construction JV [HC-JI (JV)] 773.636 08/06/2014 15/03/2016 100 23/12/2018 Final
4 Kulaura
1 RTIP-II/MOU/RPM-408 Kulaura-Janata bazar-Rangicharra (Laskarpur-Lakshmipur) 7.0500 487.996 M/S. Haque Construction 487.996 29/11/2017 15/12/2018 98 23/12/2018  
2 RTIP-II/MOU/RPM-406 Kulaura UZHQ - Fulartol GC via Bhukshimoil UP office. 8.4800 549.820 Md. Muhibur Rahman 549.820 05/09/2017 30/11/2018 95 23/12/2018  
3 RTIP-II/MOU/RPM-225 Brahman Bazar-Fenchugonj 15.0000 402.107 Khandaker Lutfur Rahman Zafar Ahmed Gilman and Suhag Enterprise JVCA 402.107 03/05/2015 13/03/2016 100 23/12/2018 Final
4 RTIP-II/MOU/RPM-163 b) Rabirbazar-Karmadah U.P road 5.0150 130.706   130.706 04/04/2014 15/03/2015 100 23/12/2018  
5 Moulvibazar-s
1 RTIP-II/MOU/PBMC-3.2 Saifur Rahman Circular Road (Sadarpart) 17.3000 484.654 Zafar Ahmed Gilman & Khaled Ahmed (JV) 484.654 10/09/2015 10/09/2020 100 23/12/2018  
2 RTIP-II/MOU/RPM-164 Begum Durreh Samad Rahman road 16.9600 310.300 M/S. Tanvir Traders 310.300 23/03/2014 04/05/2015 100 23/12/2018 Final
3 Mou/PBMC-3.2 Performance Based Maintenance Contract of Saifur Rahman Circular Road (Sadar Part) (Ch. 0+000km to 17+300km) 17.3000 552.000 Zafar Ahmed Gilamn & Khaled Ahmed (JV) Uttar Bazar, Kulaura, Moulvibazar. 552.000 07/09/2015 07/09/2020 3 02/11/2015 Works Start.
6 Rajnagar
1 RTIP-II/MOU/RPM-227 a) Kamarchak UP-Manu Rly. station Rd via Bhuter Bazar. 6.1600 132.071 Md. Nurul Alam Numan & Suheb Ahmed JVCA 132.071 26/04/2015 01/01/2017 100 23/12/2018 Final
2 RTIP-II/MOU/PBMC-3.3 R&H (Haldigul)-KalarBazar-Balagonj-Chadnighat road.(Saifur Rahman Circular road) 27.0900 629.501 Khandakar Lutfur Rahman & M/S Suhag Enterprise (JV) 629.501 10/09/2015 10/09/2020 100 23/12/2018  
3 RTIP-II/MOU/RPM-67.2 Rajnagor-Fatepur (Balagonj) 8.8050 182.942 RC MR JV 182.942 14/03/2013 15/05/2014 100 23/12/2018 Final
4 RTIP-II/MOU/RPM-67.1 Rajnagor-Fatepur (Balagonj) 8.0000 290.833 NI-MA JV 290.833 14/03/2013 25/11/2014 100 23/12/2018 Final
5 Mou/PBMC-3.3 Performance Based Maintenance Contract of R&H (Haldigul)-Kalar Bazar-Chadnighat Road (Ch. 0+000km to 27+009km). 27.0090 718.040 Khandakar Lutfur Rahman & M/S Suhag Enterprise (JV) Monihar Mansion, Kulaura, Moulvibazar 718.040 08/09/2015 08/09/2020 2 02/11/2015 Work Start
7 Sreemangal
1 RTIP-II/MOU/RPM-162 Sreemangal-Sindurkhan Bazar road 10.1500 89.016 Md. Saiful Islam 89.016 09/03/2014 02/03/2015 100 23/12/2018 Final
Total : 264.0160 (Km) 9602.12 (Lac) 9602.12 (Lac)