SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
1
|
Austagram
|
1
|
HILIP/17/WD4/VR-KIS/Aus -02
|
Improvement of Dalarkandi road (Ch.5500 - 5850m);
|
0.3500
|
17.349
|
LCS; 1 no group
|
17.349
|
|
24/04/2019
|
10
|
19/01/2019
|
Community Road
|
2
|
HILIP/16/WD4/VR-KIS/Aus -28
|
Improvement of Adampur - Shibpur Ferryghat road (Ch.2000 - 3000m);
|
1.0000
|
49.570
|
LCS; 3 nos groups
|
49.570
|
|
30/11/2018
|
10
|
19/01/2019
|
Community Road
|
3
|
HILIP/16/WD4/VR-KIS/Aus -27
|
Improvement of Adampur - Shibpur Ferryghat road (Ch.1000 - 2000m);
|
1.0000
|
49.570
|
LCS; 3 nos groups
|
49.570
|
|
30/11/2018
|
10
|
19/01/2019
|
Community Road
|
4
|
HILIP/16/WD4/VR-KIS/Aus-25
|
Part-A) Improvement of Adampur - Shibpur Ferryghat road (Ch.5000 - 6000m);
Part-B) Improvement of Adampur - Shibpur Ferryghat road (Ch.6000 - 7015m);
|
1.0000
|
49.570
|
LCS; 3 nos groups
|
49.570
|
|
30/11/2018
|
10
|
19/01/2019
|
Community Road
|
5
|
HILIP/16/WD4/VR-KIS/Aus-24
|
Part-A) Improvement of Adampur - Shibpur Ferryghat road (Ch.3000 - 4000m);
Part-B) Improvement of Adampur - Shibpur Ferryghat road (Ch.4000 - 5000m);
|
1.0000
|
49.570
|
LCS; 3 nos groups
|
49.570
|
|
30/11/2018
|
45
|
19/01/2019
|
Community Road
|
6
|
HILIP/14/WD15/ VR-KIS/Aus-81
|
Improvement of Dalarkandi Road (Ch 3000-5500m) with 6 nos U-Drain size 0.625mx0.60m at ch. 3060m, 6260m, 4260m, 4560m, 4965m & 5200m;
|
2.5000
|
123.925
|
LCS; 6 nos groups
|
123.925
|
|
30/04/2017
|
100
|
19/01/2019
|
Community Road
|
7
|
HILIP/14/WD15/ VR-KIS/Aus-80
|
Improvement of Kariral Ferryghat-Shibpur Ferryghat Road (Ch.3100-4250m);
|
1.1500
|
57.005
|
LCS; 3 nos groups
|
57.005
|
|
30/04/2017
|
100
|
19/01/2019
|
Community Road
|
8
|
HILIP/14/WD15/ VR-KIS/Aus-79
|
Improvement of Batinagar - Paon Road (Ch 2000-3850m) with 5 nos RCC U-Drain size 0.625mx0.60m at ch. 2120m, 2445m,2740m,3360m & 5570m:
|
1.8500
|
91.704
|
LCS; 5 nos groups
|
91.704
|
|
30/04/2017
|
100
|
19/01/2019
|
Community Road
|
9
|
HILIP/14/WD15/ VR-KIS/Aus-75
|
Improvement of Batinagar - Paon Road (Ch 3850-5700m) with 5 nos RCC U-Drain at ch.4650m, 5050m, 5235m,5540m & 5570m;
|
1.8500
|
91.704
|
LCS; 5 nos groups
|
91.704
|
|
30/04/2017
|
100
|
19/01/2019
|
Community Road
|
10
|
HILIP/14/WD15/ VR-KIS/Aus-52
|
Improvement of Kariral Ferryghat-Shibpur Ferryghat Road (Ch.1350-3100m);
|
1.7500
|
86.747
|
LCS; 6 nos groups
|
86.747
|
|
09/03/2016
|
100
|
19/01/2019
|
Community Road
|
11
|
HILIP/14/WD15/ VR-KIS/Aus-51
|
Improvement of Kariral Ferryghat-Shibpur Ferryghat Road (Ch 00-1350m);
|
1.3500
|
66.919
|
LCS; 4 nos groups
|
66.919
|
|
30/04/2017
|
100
|
19/01/2019
|
Community Road
|
12
|
HILIP/14/WD15/ VR-KIS/Aus-33
|
Improvement of Dalarkandi Road (Ch 1000-3000m);
|
2.0000
|
99.140
|
LCS; 6 nos groups
|
99.140
|
|
02/11/2015
|
100
|
19/01/2019
|
Community Road
|
13
|
HILIP/14/WD15/ VR-KIS/Aus-32
|
Improvement of Austagram - Hablibari Road (Ch.1300-2633m);
|
1.3330
|
66.076
|
LCS; 4 nos groups
|
66.076
|
|
01/12/2015
|
100
|
19/01/2019
|
Community Road
|
14
|
HILIP/14/WD15/ VR-KIS/Aus-31
|
Improvement of Batinagar - Paon Road (Ch 00-2000m);
|
2.0000
|
99.140
|
LCS; 7 nos groups
|
99.140
|
|
22/11/2015
|
100
|
19/01/2019
|
Community Road
|
15
|
HILIP/13/WD5/KIS-29
|
Improvement of Dalarkandi Road (Ch. 00-1000 m):
|
1.0000
|
49.570
|
LCS; 7 nos groups
|
49.570
|
|
07/05/2015
|
100
|
19/01/2019
|
Community Road
|
16
|
HILIP/KIS/COM-002
|
Improvement of Purba Austagram UP Office -Pukurpar Mor Road (Ch. 00-780m);
|
0.7800
|
38.664
|
LCS; 8 nos groups
|
38.664
|
|
25/05/2014
|
100
|
19/01/2019
|
Community Road
|
17
|
HILIP/KIS/COM-001
|
Improvement of Austagram - Hablibari Road (Ch. 546-1300m);
|
0.7540
|
37.375
|
LCS; 8 nos groups
|
37.375
|
|
25/05/2014
|
100
|
19/01/2019
|
Community Road
|
18
|
HILIP/15/WD5/UNR-KIS/Aus-02
|
Part-A)Improvement of Bangalpara-Humayunpur UP Office Road (ch.7100-8200m) with 5 nos U-drain at ch.7130m,7545m,7880m, 8110m & 8150m;
Part-B)Improvement of Bangalpara-Humayunpur UP Office Road (ch.8200-9150m) with 3 nos U-drain at ch.8308m,8385m & 8650m;
|
1.1000
|
143.500
|
M/S Zillur Enterprise, 45/1/A purana Pultan,Dhaka
|
143.500
|
|
26/05/2017
|
100
|
19/01/2019
|
Union Road
|
19
|
HILIP/15/WD5/UNR-KIS/Aus-01
|
Part-A) Improvement of Abdullahpur-Adampur UP Office via Meghna Ferryghat Road (ch.4175-5675m) with 8 nos U-drain at ch. 4395m, 4490m, 4625m, 4810m, 5045m, 5285m & 5435m;
Part-B) Improvement of Abdullahpur-Adampur UP Office via Meghna Ferryghat Road (ch. 5675-7240m) with 2 nos U-drain at ch. 5975m & 6090m;
Part-C) Improvement of Abdullahpur-Adampur UP office via Meghna Ferryghat Road (ch. 7240-8940m) with 2 nos U-drain at ch.7590m & 7840m;
|
1.5000
|
333.900
|
M/S Mominul Haque, Bhairab, Kishoreganj
|
333.900
|
|
19/03/2017
|
75
|
19/01/2019
|
Union Road
|
20
|
HILIP/14/WD5/UNR-KIS/Aus-11
|
Improvement of Bangalpara-Humayunpur UP Office Road (ch. 5100-7100m) with 375m Slop Protection work & 5 nos U-drain at ch. 5340m, 5560m, 5707m, 6900m, 7100m;
|
2.0000
|
140.000
|
M/S Shamim Construction, Pakundia, Kishoreganj
|
140.000
|
|
04/04/2016
|
100
|
19/01/2019
|
Union Road
|
21
|
HILIP/14/WD5/UNR-KIS/Aus-10
|
Improvement of Abdullahpur-Adampur UP Office via Meghna Ferryghat Road (ch.1175-4175m) with 8 nos U-drain ch.1275m,1965m, 2080m, 2575m, 3000m, 3500m, 3700m & 3950m;
|
3.0000
|
210.000
|
M/S Mominul Haque, Bhairab, Kishoreganj
|
210.000
|
|
30/06/2018
|
100
|
19/01/2019
|
Union Road
|
22
|
HILIP/13/WD5/KIS-17
|
Improvement of Bangalpara-Humayunpur Road (Ch. 3065-3648 & 3689-4100m);
|
0.9940
|
69.580
|
M/S Challenger, Batrish, Kishoreganj
|
69.580
|
|
29/12/2014
|
100
|
19/01/2019
|
Union Road
|
23
|
HILIP/13/WD5/KIS-16
|
Improvement of Bangalpara-Humayunpur Road (Ch. 2195-3065m);
|
0.8700
|
60.900
|
M/S Challenger, Batrish, Kishoreganj
|
60.900
|
|
29/12/2014
|
100
|
19/01/2019
|
Union Road
|
24
|
HILIP/13/WD5/KIS-15
|
Improvement of Bangalpara-Humayunpur Road (Ch.1400-1635 & 1695-2195m);
|
0.7350
|
51.450
|
M/S Mominul Haque, Bhairab, Kishoreganj
|
51.450
|
|
09/03/2015
|
100
|
19/01/2019
|
Union Road
|
25
|
HILIP/13/WD5/KIS-14
|
Improvement of Bangalpara-Humayunpur Road (Ch. 565-1400m);
|
0.8350
|
58.450
|
M/S Mithamoin Builders, Mithamoin, Kishoreganj
|
58.450
|
|
25/02/2015
|
100
|
19/01/2019
|
Union Road
|
26
|
HILIP/KIS/UNR-003
|
Improvement of Abdullahpur-Adampur UP office via Meghna Ferryghat Road (Ch.00-1000m);
|
1.0000
|
70.000
|
M/S Shahidul Islam James, Austagram, Kishoreganj.
|
70.000
|
|
26/03/2014
|
100
|
19/01/2019
|
Union Road
|
27
|
HILIP/15/WD3/UZR-KIS/Aus-09
|
Part-A)Improvement of Austagram-Mohishertillia-Gagra GC -Mithamoin road (Ch. 3570m-11490m);
Part-B)Const. of 1x2.00mx2.00m RCC Box Culvert Ch. 3620m on the same alignment;
Part-C) Const. of 28 nos U-drain size .625mx0..06m in Diff. Chainage on the same alignment;
Part-D)Const. of 20 nos Pipe Culvert in Diff. Chainage on the same alignment;
|
7.9200
|
1108.403
|
Shamim Enterprise (Pvt.) Ltd, Mymensingh
|
1108.403
|
|
30/12/2017
|
39
|
19/01/2019
|
Ongoing (Upazila Road)
|
28
|
HILIP/15/WD4/UZR-KIS /Aus-03
|
Improvement of Austagram – Adampur GC Road (ch. 7430m-8110m);
|
0.6800
|
54.400
|
Escon Trading and Construction, 57/14,Tejturi Bazar, Chalk Lane, East Raza Bazar, Dhaka
|
54.400
|
|
30/05/2017
|
100
|
19/01/2019
|
Upazila Road
|
29
|
HILIP/14/WD4/UZR-Kis /Aus-09
|
Part-A: Improvement of Austagram-Adampur GC Road (Ch. 11750m-13500m);
Part-B: Const. of 1x2.00mx2.00m & 3x4.00mx3.30m RCC Box Culvert at ch.10910m,12650m at same road;
|
1.7500
|
140.000
|
M/S Challenger, Batrish, Kishoreganj
|
140.000
|
|
31/12/2016
|
100
|
19/01/2019
|
Upazila Road
|
30
|
HILIP/14/WD4/UZR-Kis /Aus-08
|
Improvement of Austagram-Adampur GC Road (Ch. 9550m-11750m);
|
2.2000
|
176.000
|
M/S Challenger, Batrish, Kishoreganj
|
176.000
|
|
22/03/2016
|
100
|
19/01/2019
|
Upazila Road
|
31
|
HILIP/13/WD-4/KIS-7
|
Improvement of Austagram-Adampur GC Road (Ch.14500-15500m);
|
1.0000
|
80.000
|
M/S Shamim Construction, Pakundia,Kishoreganj
|
80.000
|
|
10/03/2015
|
100
|
19/01/2019
|
Upazila Road
|
32
|
HILIP/13/WD-4/KIS-6
|
Improvement of Austagram-Adampur GC Road (Ch. 13500-14500m);
|
1.0000
|
80.000
|
M/S Shamim Construction, Pakundia, Kishoreganj
|
80.000
|
|
04/02/2015
|
100
|
19/01/2019
|
Upazila Road
|
33
|
HILIP/KIS/UZR-001
|
Improvement of Austagram-Adampur GC Road (Ch. 8200-9200m);
|
1.0000
|
80.000
|
M/S Shahidul Islam James, Austagram, Kishoregonj.
|
80.000
|
|
30/03/2014
|
100
|
19/01/2019
|
Upazila Road
|
|
2
|
Itna
|
1
|
HILIP/14/WD15/ VR-KIS/Itn-70
|
Improvement of Dram Ferryghat -Arailia Ferryghat Road (ch 4412m -5712) with 4 nos RCC U-Drain 1X0.625mX0.550m at ch.4602m,4782m,4932m & 5022m;
|
1.3000
|
64.441
|
LCS; 4 nos groups
|
64.441
|
|
31/05/2017
|
100
|
19/01/2019
|
Community Road
|
2
|
HILIP/14/WD15/ VR-KIS/Itn-69
|
Improvement of Dram Ferryghat -Arailia Ferryghat Road(ch 3000 - 4412m) with 5 nos RCC U-Drain 1X0.625mX0.550m at ch.3090m,3981m,4062m,4182m & 4332m;
|
1.4120
|
69.992
|
LCS; 4 nos groups
|
69.992
|
|
31/05/2017
|
100
|
19/01/2019
|
Community Road
|
3
|
HILIP/14/WD15/ VR-KIS/Itn-68
|
Improvement of Dram Ferryghat -Arailia Ferryghat Road (ch. 2000- 3000m) with 4 nos RCC U-Drain 1X0.625mX0.550m at ch. 20602m,2390m, 2765m & 2880;
|
1.0000
|
49.570
|
LCS; 3 nos groups
|
49.570
|
|
31/05/2017
|
100
|
19/01/2019
|
Community Road
|
4
|
HILIP/14/WD15 /VR-KIS/Itna-46
|
Improvement of Dram Ferryghat -Arailia Ferryghat Road (ch.00 -2000m);
|
2.0000
|
99.140
|
LCS; 5 nos groups
|
99.140
|
|
31/12/2016
|
100
|
19/01/2019
|
Community Road
|
5
|
HILIP/14/WD15 /VR-KIS/Itna-45
|
Improvement of Baribari-Shaila Road(ch.00- 2000m);
|
2.0000
|
99.140
|
LCS; 6 nos groups
|
99.140
|
|
28/02/2017
|
100
|
19/01/2019
|
Community Road
|
6
|
HILIP/14/WD15 /VR-KIS/Itna-37
|
Improvement of Dailong -Kathair Road (Ch.00-3500m);
|
3.5000
|
173.495
|
LCS; 10 nos groups
|
173.495
|
|
28/02/2017
|
100
|
19/01/2019
|
Community Road
|
7
|
HILIP/13/WD15/
KIS-12
|
Improvement of Haripur-Pongdulan – Uttar Razi Hat Road (Ch. 00-2500m);
|
2.5000
|
123.925
|
LCS; 18 nos groups
|
123.925
|
|
31/05/2015
|
84
|
19/01/2019
|
Community Road
|
8
|
HILIP/17/WD3/UNR-KIS/Itn - 02
|
Part-A) Improvement of Raytuti UP-Uttar Razi - Kalna Hat Road (ch. 00 – 1125m);
Part-B) Const. of 4 nos U-Drain (Size 0.60mx0.60m) at ch. 30m, 360m, 730m & 860m on the same road;
|
1.1250
|
78.750
|
Md.Sarwar Jahan, Jahangirpur, Madan, Netrakona
|
78.750
|
|
05/06/2019
|
50
|
19/01/2019
|
Union Road
|
9
|
HILIP/16/WD3/UNR-KIS/Itn-03
|
Improvement of Itna - Silni-Elongjuri Road (ch.00 - 1000m & 6500 - 6990m) with 5 Nos U-drain (Size: 0.60mx0.625m) at ch.150m, 875m, 930m, 6700m & 6850m;
|
1.4900
|
104.300
|
bbejvroy, Ukilpara, Kishoreganj
|
104.300
|
|
05/11/2018
|
0
|
19/01/2019
|
Union Road
|
10
|
HILIP/14/WD5/UNR-KIS/Itn-18
|
Improvement of Raytuti UP-Uttar Razi- Kalan Hat Road at Ch.3870-4870m with 3 nos U-drain at ch. 4086m, 4127m & 4434m;
|
1.0000
|
70.000
|
M/S Shameem Construction Pakundia,Kishoreganj
|
70.000
|
|
23/02/2016
|
100
|
19/01/2019
|
Union Road
|
11
|
HILIP/14/WD5/UNR-KIS/Itn-17
|
Improvement of Chowganga UP- Chandpur Hat road at (Ch.00-1165m);
|
1.1650
|
81.550
|
M/S Challenger, Batrish, Kishoreganj.
|
81.550
|
|
23/02/2016
|
100
|
19/01/2019
|
Union Road
|
12
|
HILIP/14/WD5/UNR-KIS/Itn-09
|
Improvement of Itna-Silni-Elongjuri road (Ch.3000-4900m) with 6 nos U-drain at ch.3085m, 3500m,3950m, 4375m, 4650m, & 4800m;
|
1.9000
|
133.000
|
M/S Bhati Bangla Enterprise
Ukilpara, Kishoreganj.
|
133.000
|
|
21/02/2016
|
100
|
19/01/2019
|
Union Road
|
13
|
HILIP/13/WD5/KIS-19
|
Improvement of Chowganga UP-Chandrapur hat Road (Ch.1500-3000m);
|
1.5000
|
105.000
|
M/S Osman Gani, Tarapasha, Kishoreganj
|
105.000
|
|
25/12/2014
|
100
|
19/01/2019
|
Union Road
|
14
|
HILIP/13/WD5/KIS-18
|
Improvement of Itna-Silni-Elongjuri Road (Ch.4900-6500m);
|
1.6000
|
112.000
|
M/S Shahil Enterprise, Station Road, Kishoreganj
|
112.000
|
|
29/12/2014
|
100
|
19/01/2019
|
Union Road
|
15
|
HILIP/KIS/UNR-002
|
Improvement of Itna -Silni-Elongjuri Road (Ch.2000-3000m);
|
1.0000
|
70.000
|
M/S Bhati Bangla Enterprise,
Ukilpara, Kishoreganj
|
70.000
|
|
01/04/2014
|
100
|
19/01/2019
|
Union Road
|
16
|
HILIP/KIS/UNR-001
|
Improvement of Itna -Silni-Elongjuri Road (Ch.1000-2000m);
|
1.0000
|
70.000
|
M/S J. A Traders, Harua, Kishoreganj
|
70.000
|
|
30/03/2014
|
100
|
19/01/2019
|
Union Road
|
17
|
HILIP/16/WD2/UZR-KIS/Itn-01
|
Part-A)Improvement of Itna – Jawar hat via Raituty Hizaljani Road (ch.10745- 14200m);
Part-B) Const. of 1 no RCC Box Culvert Size: 1.00m x 1.00m & 2 vent 3.00mx3.00m RCC Box Culvert at ch. 11115m & 13681 on same road;
Part-C) Const. of 9 nos U-Drain Size : 1.00m x 1.00m at ch.11295m, 11395m, 11810m, 12205m,12550m, 12580m, 12832m, 12900m & 14030m on the same road;
|
3.4550
|
276.400
|
maw.mc.jv@gmail.com,Pakundia,Kishoreganj
|
276.400
|
|
17/02/2018
|
42
|
19/01/2019
|
Upazila Road
|
18
|
HILIP/15/WD4/UZR-KIS/Itn-05
|
Improvement of Jawar hat via Raituty Hazaijani Road (Ch. 7685-10695m) with 7 nos (size .075mx0.75m) U-drain at ch. 8400m,8777m,9296m,9634m,9907m & 10011m;
|
3.0100
|
240.800
|
M/S Mominul Haque, Bhairab, Kishoreganj
|
240.800
|
|
10/05/2017
|
95
|
19/01/2019
|
Upazila Road
|
19
|
HILIP/14/WD4/UZR-Kis/Itna-15
|
Improvement of Itna -Jawar hat via Raituti Hazaljani Road (ch.6685 -7685m) with 2 nos 1X0.625mX0.550m U-drain at ch-6775m & 7321m ;
|
1.0000
|
80.000
|
M/S Challenger, Batrish, Kishoreganj.
|
80.000
|
|
31/03/2017
|
100
|
19/01/2019
|
Upazila Road
|
20
|
HILIP/14/WD4/UZR-Kis/Itna-14
|
Improvement of Itna -Jawar hat via Raituti Hazaljani Road (ch.5685 -6685m) with 5 nos 1X0.625mX0.550m U-drain at ch-5835m,5885m,5995m,6215m,6580m;
|
1.0000
|
80.000
|
M/S Challenger, Batrish, Kishoreganj.
|
80.000
|
|
31/03/2017
|
100
|
19/01/2019
|
Upazila Road
|
21
|
HILIP/14/WD4/UZR-Kis/Itna-11
|
Improvement of Itna -Azmiriganj GC Road (ch.12000 -14250m);
|
2.2500
|
180.000
|
MAW-RJ (JV), Madan, Netrakona
|
180.000
|
|
25/07/2016
|
100
|
19/01/2019
|
Upazila Road
|
|
3
|
Mithamoin
|
1
|
HILIP/15/WD4/VR-KIS/Mit-30
|
Improvement of Kewarjure UP Office to Kazirkhala Ferry Ghat Road (ch.2000 - 4075m) with 3 nos RCC U-Drain (Size:0.60mx0.625m) at ch. 3885m, 3825m, & 4070m;
|
2.0750
|
102.857
|
LCS; 7 nos groups
|
102.857
|
|
02/09/2017
|
77
|
19/01/2019
|
Community Road
|
2
|
HILIP/14/WD15/ VR-KIS/Mit-84
|
Improvement of Mithamoin Bazar - Sadar Road (Ch.2000-4000m);
|
2.0000
|
99.140
|
LCS; 14 nos groups
|
99.140
|
|
31/05/2018
|
99
|
19/01/2019
|
Community Road
|
3
|
HILIP/15/WD15 /VR-KIS/Mit-11
|
Improvement of Kulkulir Khal to Noabad Road (Ch 2760--3760m) with 2 nos RCC U-Drain at ch. 3050m & 3300m;
|
1.0000
|
49.570
|
LCS; 3 nos groups
|
49.570
|
|
19/09/2016
|
100
|
19/01/2019
|
Community Road
|
4
|
HILIP/14/WD15/ VR-KIS/Mit-81
|
Improvement of Kewarjure UP Office to Kazir khala Feri ghat Road (ch.00 -2000m) with 6 nos U-Drain (size: 0.625m x 0.60m) at ch.235m,375m,575m,1200m,1452m & 1680m;
|
2.0000
|
99.140
|
LCS; 6 nos groups
|
99.140
|
|
28/02/2017
|
100
|
19/01/2019
|
Community Road
|
5
|
HILIP/14/WD15/ VR-KIS/Mit-76
|
Improvement of Kulkulir Khal to Noabad Road (Ch. 3760-5134m) with 1 nos RCC U-Drain at ch. 4920m;
|
1.3740
|
68.109
|
LCS; 4 nos groups
|
68.109
|
|
20/06/2016
|
100
|
19/01/2019
|
Community Road
|
6
|
HILIP/14/WD15 /VR-KIS/Mit-47
|
Improvement of Kewarjure UP Office to Kazir khala Feri ghat Road (ch.3490-4240m);
|
0.7500
|
37.177
|
LCS; 2 nos groups
|
37.177
|
|
02/02/2016
|
100
|
19/01/2019
|
Community Road
|
7
|
HILIP/14/WD15 /VR-KIS/Mit-30
|
Improvement of Kulkulir Khal to Noabad Road (Ch.1760-2760m);
|
1.0000
|
49.570
|
LCS; 3 nos groups
|
49.570
|
|
16/11/2015
|
100
|
19/01/2019
|
Community Road
|
8
|
HILIP/15/WD3/UNR-KIS /Mit-17
|
Part-A) Improvement of Dhaki UP Office - Katkhal UP Office Road (ch. 4000 – 7860m);
|
3.8600
|
270.200
|
M/S Nishat Trading Company, Kishoreganj
|
270.200
|
|
05/11/2017
|
50
|
19/01/2019
|
Union Road
|
9
|
HILIP/15/WD5/UNR-KIS /Mit-15
|
Improvement of Dhaki UP Office - Katkhal UP Office Road (ch. 2000 – 4000m) with 4 nos U-Drain (size: 0.625m x 0.60m ) at ch. 2580m, 3050m, 3550m & 3860m;
|
2.0000
|
140.000
|
M/S. Bhati Bangla Enterprise, Ukilpara, Kishorgonj.
|
140.000
|
|
09/03/2017
|
100
|
19/01/2019
|
Union Road
|
10
|
HILIP/14/WD5/UNR-KIS/Mit-16
|
Improvement of Dhaki UP Office - Katkhal UP Office Road (ch. 00-2000m) with 8 nos U-drain at ch.110m, 440m, 580m, 970m,1230m,1430m,1690m & 1880m;
|
2.0000
|
140.000
|
M/S Nishat Trading Company, 9 New Eskaton, Dhaka-1000
|
140.000
|
|
28/07/2016
|
100
|
19/01/2019
|
Union Road
|
11
|
HILIP/13/WD5/KIS-6
|
Improvement of Gopedighi UP Office - Baghadia bazar Road (Ch. 4000-5174m);
|
1.1740
|
82.180
|
M/S Shahil Enterprise, Station Road, Kishoreganj
|
82.180
|
|
30/12/2014
|
100
|
19/01/2019
|
Union Road
|
12
|
HILIP/KIS/UNR-006
|
Improvement of Gopedighi UP Office - Baghadia Bazar Road (Ch.2774-4000m);
|
1.2260
|
85.820
|
M/S Al-Gilani Construction,
Motijheel, Dhaka.
|
85.820
|
|
20/03/2014
|
100
|
19/01/2019
|
Union Road
|
13
|
HILIP/KIS/UNR-005
|
Improvement of Gopedighi UP Office - Baghadia bazar Road (Ch.1774-2774m);
|
1.0000
|
70.000
|
M/S Bhati Bangla Enterprise,
Ukilpara, Kishoreganj.
|
70.000
|
|
01/04/2014
|
100
|
19/01/2019
|
Union Road
|
14
|
HILIP/KIS/UNR-004
|
Improvement of Gopedighi UP Office - Baghadia Bazar Road (Ch.774-1774m);
|
1.0000
|
70.000
|
M/S Shiplo Traders, Rathkola, Kishoreganj
|
70.000
|
|
03/04/2014
|
100
|
19/01/2019
|
Union Road
|
|
4
|
Nikli
|
1
|
HILIP/16/WD4/VR-KIS/Nik-23
|
Improvement of Dampara Bazar - Aliapara Road (ch. 3050 -5850m) with 3 Nos U-Drain (Size: 0.60mx.0.625m) at ch. 5240m, 4530m & 5760m;
|
2.8000
|
138.796
|
LCS; 10 nos groups
|
138.796
|
|
30/11/2018
|
70
|
19/01/2019
|
Community Road
|
2
|
HILIP/16/WD4/VR-KIS/Nik-22
|
Part-A) Improvement of Singpur to Vtivoratiya Road (Ch.3100 - 5100m) with 6 Nos U-drain (Size:0.60mx0.625m) at ch. 3250m, 3720m, 4330m, 4650m, 4760m, & 5040m;
Part-B) Improvement of Singpur to Vtivoratiya Road (Ch.5100 -7150m) with 3 Nos U-drain (Size:0.60mx0.625m) at ch. 5330m, 5850m, 6580m & 6900m;
|
2.0000
|
99.140
|
LCS; 7 nos groups
|
99.140
|
|
27/04/2018
|
100
|
19/01/2019
|
Community Road
|
3
|
HILIP/15/WD15 /VR-KIS/Nikli-13
|
Improvement of H/O Iman Ad - Nikli Bazar Road (Ch. 510-810m). Effective Length = 300 m ;
|
0.3000
|
14.871
|
LCS; 1 no group
|
14.871
|
|
23/08/2016
|
100
|
19/01/2019
|
Community Road
|
4
|
HILIP/15/WD15 /VR-KIS/Nikli-10
|
Improvement of Sajanpur FWC to Boiddarkanda Road (Ch 2000-4150m);
|
2.1500
|
106.575
|
LCS; 7 nos groups
|
106.575
|
|
23/05/2017
|
100
|
19/01/2019
|
Community Road
|
5
|
HILIP/15/WD15 /VR-KIS/Nikli-09
|
Improvement of Singpur -Vatioratia Pajghat Road (Ch 00-3100m);
|
3.1000
|
153.667
|
LCS; 9 nos groups
|
153.667
|
|
15/04/2017
|
100
|
19/01/2019
|
Community Road
|
6
|
HILIP/15/WD15 /VR-KIS/Nikli-08
|
Improvement of Karpasa UP- Jalalpur Bazar Road (Ch 2000-2500m);
|
0.5000
|
24.785
|
LCS; 2 nos groups
|
24.785
|
|
03/02/2017
|
100
|
19/01/2019
|
Community Road
|
7
|
HILIP/15/WD15 /VR-KIS/Nikli-07
|
Improvement of Dampara Bazar Ali para Road (Ch 2000-3050m);
|
1.0500
|
52.048
|
LCS; 3 nos groups
|
52.048
|
|
04/02/2017
|
100
|
19/01/2019
|
Community Road
|
8
|
HILIP/14/WD15 /VR-KIS/Nikli-43
|
Improvement of Karpasa UP -Jalalpur Bazar Road(Ch.0-2000m);
|
2.0000
|
99.140
|
LCS; 6 nos groups
|
99.140
|
|
28/02/2017
|
100
|
19/01/2019
|
Community Road
|
9
|
HILIP/14/WD15 /VR-KIS/Nikli-42
|
Improvement of Sajanpur FWC to Boiddarkanda Road (Ch. 0-2000m);
|
1.9590
|
97.107
|
LCS; 7 nos groups
|
97.107
|
|
15/01/2017
|
100
|
19/01/2019
|
Community Road
|
10
|
HILIP/14/WD15 /VR-KIS/Nikli-39
|
Improvement of Doulatpur - parabazitpur Road (Ch. 0-2500m);
|
2.5000
|
123.925
|
LCS; 8 nos groups
|
123.925
|
|
30/11/2015
|
100
|
19/01/2019
|
Community Road
|
11
|
HILIP/14/WD15 /VR-KIS/Nikli-38
|
Improvement of Dampara Bazar Ali para Road (Ch 0-2000m);
|
1.9400
|
96.165
|
LCS; 7 nos groups
|
96.165
|
|
15/01/2017
|
100
|
19/01/2019
|
Community Road
|
12
|
HILIP/13/WD15/
KIS-14
|
Improvement of Chatir Char-Sapmari Road (Ch. 108-2608m);
|
2.5000
|
123.925
|
LCS; 16 nos groups
|
123.925
|
|
15/03/2015
|
100
|
19/01/2019
|
Community Road
|
13
|
HILIP/KIS/COM-003
|
Improvement of H/O Iman Ad - Nikli Bazar Road (Ch. 00-845m). Effective Length = 510.00m;
|
0.5100
|
25.280
|
LCS; 6 nos groups
|
25.280
|
|
30/09/2014
|
100
|
19/01/2019
|
Community Road
|
14
|
HILIP/14/WD4/UZR-Kis/Nikli-10
|
Improvement of Nikli Bazar - Singpur Bazar Road (ch.2635-2775m, 2900-3765m & 6465-7575m);
|
2.1150
|
169.200
|
M/S Shahil Enterprise, Station Road, Kishoreganj
|
169.200
|
|
15/07/2016
|
100
|
19/01/2019
|
Upazila Road
|
|
Total :
|
134.3410 (Km)
|
9030.07 (Lac)
|
9030.07 (Lac)
|
|
|
|
|
|
|