MGSP/MAD/2015-16/W-03
|
(a) Improvement of (BISIC road) Bachchu Sarak to main road (Ch.0+00 to 0+862m) by BC Pavement.
(b) Improvement of (BISIC road) Bachchu Sarak to main road by RCC Pavement (Ch.0+00 to 0+208m) by BC (bypus road)
(c ) Construction of RCC Drain start from Shahid Bachchu Sarak (BISIC road side drain) (R/S) with foothpath Ch. 0+000 to 0+867m under Madaripur Pourashava.
(d) Environmental work on road and drain at Bisic road starting from Bachchu Sarak to main road (Ch. 0+000m to 0+862m) under Madaripur Pourashava, Madaripur. Fixed cost-01
(e) Environmental work on road and drain at Bisic road starting from Bachchu Sarak to main road (Ch. 0+000m to 0+862m) under Madaripur Pourashava, Madaripur. Fixed cost-02
|
1.9370
|
35397555.710
|
M.A.H. Construction Ltd.
|
35397555.710
|
06/11/2016
|
05/11/2017
|
41
|
27/09/2017
|
|
2
|
MGSP/MAD/W-02
|
a) Construction of RCC Road at Shahid Harun Sarak Starting from Madaripur Main Road to Dorgha Sharif Road. (Ch. 0.00-365.00m) (Total Length: 365m)
b) Construction of RCC Road at Pakdi Peshker Bari road starting from Charmuguria Puraton road to Beri badh (Ch0.00m to 280.00m) (Total Length: 280m)
c) Construction of RCC Road at Bankers Colony starting from Madaripur Shariatpur road to Posu Hospital (Ch. 0.00-465.00m) (Total Length: 465m)
d) Construction of Drain at Bankers Colony starting from Madaripur Shariatpur road to Posu Hospital (Ch. 4.00-465.00m) (Total Length: 461m)
e) Construction of RCC Road at L. Faruk Sarak starting from RHD Road to End of Poura Area. (Ch. 0.00-270.00m) (Total Length: 270m)
f) Construction of RCC Road starting from Badamtola Hamid Akind Srak to U.I School (Ch. 0.00-270.00m) (Total Length: 270m)
g) Construction of Drain starting from Badamtola Hamid Akind Srak to U.I School (Ch. 0.00-270.00m) (Total Length: 270m)
h) Construction of RCC Road at the Nasim Nagar Charity Hospital road starting from Charmuguria Main road to Grave Yard road (Ch. 0.00-290.00m) (Total Length: 290m)
i) Construction of drain at the Nasim Nagar Charity Hospital road starting from Charmuguria Main road to Grave Yard road (Ch. 0.00-290.00m) (Total Length: 290m)
|
2.9610
|
26222469.000
|
M/S Atahar EnterPrise
|
26222469.000
|
05/02/2015
|
17/04/2016
|
100
|
27/09/2017
|
Completed
|
3
|
MGSP/MAD/W-01
|
a) Construction of RCC Road at Shahid Bachu Sarak Starting from Kazir More to Howlader Godi. (Ch. 1230.00-1572.00m) (Total Length: 342m)
b) Construction of Drain (Both side) at Shahid Bachu Sarak Starting from Kazir More to Howlader Godi. (Ch. 1230.00-1572.00m) (Total Length: 684m)
c) Construction of RCC Road at Uttoron Club Road (Ch.000-90.00m) (Total Length: 90m)
d) Construction of Drain at Uttoron Club Road (Both side) (Ch.000-90.00m) (Total Length: 180m)
e) Construction of RCC road at Amin Uddin Howlader Sarak. (Ch. 0.00-430.00) (Total Length: 430m)
f) Construction of Drain at Amin Uddin Howlader Sarak. (Ch. 0.00-430.00) (Total Length: 430m)
g) Construction of RCC Road at Sardar Colony Hamid Sikder Sarak Starting from Hamid Akond Sarak. to RHD main Road (Ch. 0.00-420.00m) (Total Length: 420m)
h) Construction of of Drain at Sardar Colony Hamid Sikder Sarak Starting from Hamid Akond Sarak. to RHD main Road (Ch. 0.00-420.00m) (Total Length: 253m)
|
2.9960
|
28598735.000
|
Md. Kabir Hossain
|
28598735.000
|
05/02/2015
|
30/07/2016
|
100
|
27/09/2017
|
Completed
|