MGSP/CHM/W-01
|
(a) Road Work : Improvement of East Bypass Road Start from Birchandranagar Highway Road to South Side Girls School Road Under Chouddagram Pourashava, Comilla (Ch.0.00-4718.00m) (Total Length= 4710m)
(b) Drain Work : Improvement of East Bypass Road Start from Birchandranagar Highway Road to South Side Girls School Road Chouddagram Pourashava, Comilla (Ch.0.00-4718.00m) Drain-1=250m, D-2=420m= (Total Length =670m)
(c) Culvert Work : Improvement of East Bypass Road Start from Birchandranagar Highway Road to South Side Girls School Road Chouddagram Pourashava, Comilla (Ch.0.00-4718.00m) (Ch. 750m, 3620m, 4020m, 4040m)= (Total Length =7.50m)
(d) Retaining Wall : Improvement of East Bypass Road Start from Birchandranagar Highway Road to South Side Girls School Road Under Chouddagram Pourashava, Comilla (Ch.0.00-4718.00m) (Total Length= 149.00m)
|
5.5365
|
41315076.000
|
M/S. R-TA Enterprise
|
41315076.000
|
15/12/2015
|
22/05/2017
|
81
|
27/09/2017
|
Further extension in process
|