Loading...

Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Sherpur
1 MGSP/SHE/2015-16/W-03 (a)Construction of RCC Drain starting from Ulipur to National highway ( Sherpur Hospital Road) via Darkipara Ch.0+000-2+715 under Sherpur Pourashava, Bogra (b) Supplying, fitting and fixing of street light in road side from Ulipur to National highway ( Sherpur Hospital Road) via Darkipara Ch.0+000-2+715 under Sherpur Pourashava, Bogra 5.4300 114268901.080 MS Appollo Engineering & Construction Ltd. 114268901.080 29/09/2016 29/09/2017 5 27/09/2017  
2 MGSP/SHE/W-02 a) Construction of BC Road at Dhunat road Doctor Clinic to Hazipur Highway road vai Sherpur Thana (Ch. 0.00-2600m) under Sherpur Pourashava. Total length = 2600m b) Construction of BC Road start from College road to near house of Hamed via near house of Razu Profficer (Ch. 0.00-370m & Link 130.0) In Ward no. 06 under Sherpur Pourashava. Total length = 500m c) Construction of RCC drain start from National Highway (Alamgir shop) to near Sarkar shop via Poura shishu park under Sherpur Pourashava (ch.0.00-760m) Total length=760m d) Construction of BC Road start from National Highway (Alamgir shop) to near house of Dinu Babu in Ward no-05 under Sherpur Pourashava (ch.0.00-90.0m) Total length=90m e) Construction of BC Road start from (National Highway Dhaka-Bogra) to Near Dalal office in Ward no-07 (ch.0.00-320.0m) under Sherpur Pourashava Total length=320m 4.2700 32597048.000 M/S. Ataur Rahman Khan 32597048.000 20/08/2015 15/08/2016 100 27/09/2017 Completed
3 MGSP/SHE/W-01 a) Construction of BC Road start from National Highway (Pals Clinic) to near house of Nowsher via Mottri NGO office (ch.0.00-370m & Link 130.0) in Word no-09, under Sherpur Pourashava,. Total length=500m b) Construction of RCC drain start from National Highway (Pals Clinic) road to Baroduary poura mosque via Katcha Bazar under Sherpur Pourashava (ch.0.00-520m), Total length=520m. c) Construction of RCC Drain start from near Uttara Plaza to Korotoa river via AC-Land Office under Sherpur Pourashava (Ch. 0.00-630m). Total length = 630m d) Construction of BC Road at Darkipara Existing BC road to Hazipur (Highway road) via Nayapara (ch.0.00-1600m), under Sherpur Pourashava. Total length =1600m. 3.2500 31526275.000 M/S MTE & MMRM JOINT VENTURE 31526275.000 20/08/2015 15/08/2016 100 27/09/2017 Completed
Total : 12.9500 (Km) 178392224.08 (Lac) 178392224.08 (Lac)