Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Kotwalipara
1 BAPARD/GOPA/BLDG/W-08 Installation of 2nos Production Tube well (PWT)& Installation of 2nos Submersible water Pump at BAPARD Complex, Kotalipara Dist: Gopalganj. 72.080 M/S Monir Traders 72.080 10/12/2017 30/03/2020 100 08/09/2020 Works is Completed
2 BAPARD/GOPA/BLDG/W-07 Part A:Construction of 3- storied Agriculture shed Part B:02-STORIED OFFICE & HATCHARY BUILDING Part C: Construction of Hatchery pond at BAPARD Complex Upazila: Kotwalipara Dist: Gopalgonj. 450.060 Wahid Construction 450.060 03/12/2017 30/12/2020 50 07/09/2020 Works is onegoing
3 BAPARD/GOPA/BLDG/W-06 Construction of Boundary wall at BAPARD Complex Upazila: Kotwalipara Dist: Gopalgonj. 677.690 Wahid Construction 677.690 03/12/2017 30/12/2020 70 07/09/2020 Works is ongoing
4 BAPARD/GOPA/BLDG/GD-01 SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF 2000KVA, 11/0.415KV INDOOR TYPE SUBSTATION & EXTERNAL ELECTRIFICATION WORKS FOR BAPARD NEW CAMPUS AT KOTWALIPARA, GOPALGANJ. 251.350 Sayed Electric 251.350 30/06/2017 24/11/2019 100 07/09/2020 works is completed
5 BAPARD/GOPA/BLDG/W-03 Construction of 10 Storied Hostel Building-02 at BAPARD Campus under Kotwalipara Upazila, Dist. Gopalgonj. 8480.000 Navana Construction Limited 8480.000 30/04/2015 30/12/2020 99 12/08/2020 works is on going
6 BAPARD/GOPA/BLDG/W-02 Construction of 10 Storied Academic BUILDING-01at BAPARD Campus under Kotwalipara Upazila, Dist. Gopalgonj. 8591.300 Mir Akther Hossain Limited 8591.300 14/12/2014 30/12/2018 100 12/08/2020 works is Completed
7 BAPARD/GOPA/BLDG/W-01 Construction of BAPARD Boundary Wall 51.100 Architecture & Structure Consultant Ltd 51.100 27/04/2014 06/03/2015 100 10/08/2020 Work has been Completed
8 BAPARD/GOPA/BLDG/W-05 Construction of 6 Storied Staff Quater at BAPARD Campus under Kotwalipara Upazila, Dist. Gopalgonj. 436.280 dhaly Construction LTD 436.280 11/12/2016 30/12/2020 75 03/08/2020 works is ongoing
9 BAPARD/GOPA/BLDG/W-04 Construction of 6 Storied officers Quater at BAPARD Campus under Kotwalipara Upazila, Dist. Gopalgonj. 1360.280 dhaly Construction LTD 1360.280 11/12/2016 11/12/2020 75 03/08/2020 works is ongoing
Total : 0.0000 (Km) 20370.14 (Lac) 20370.14 (Lac)