Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Chandanish
1 PD/CLBUURP/W-363 Const. of Bridge on Dohazari G.C-Lalutia Vhomang hat G.C road at Ch.3550m. 0.000   0.000 0 23/02/2021 Switched to FS for IBRR ( 2nd Phase)
2 PD CLBUURP, W-201 Const. of RCC Bridge on Dewanhat-Bailtali-Barma-Patiya road at Ch. 2760m. 225.740 M/S M.A. Zaher 225.740 24/08/2018 100 18/02/2020
2 Lohagara
1 PD CLBUURP, W-362 Const. of PSC Girder Bridge on Dorbeshat Miesbila roads over Tonkaboti Khal. 485.740 M/S Chowdhury Enterprise & Consonance Engineers (JV) 485.740 19/04/2020 95 23/02/2021
3 Mirsharai
1 PD/CLBUURP/W-202 Bridge at Hossain Hazi road. 0.000 0.000 100 23/02/2021 Done by PIO
2 PD CLBUURP, W-202 Const. of RCC Bridge on Karer Hat UP-Santir Hat GC road (Hinguli Khal) at Ch. 4480m. 243.720 PPL-ALML-JV 243.720 15/11/2016 22/11/2017 100 18/02/2020
4 Patiya
1 PD CLBUURP, W-203A Remaining Work for Const. of PC Girder Bridge on Uzirpur road at Ch. 10580m over Sikalbaha Khal (ID No.: 415532013). 3500.000 3500.000 0 23/02/2021 Financial Evaluation under process
2 PD CLBUURP, W-203 Const. of PC Girder Bridge on Uzirpur road at Ch. 10580m over Sikalbaha Khal 231.3000 1678.240 Al-amin & Taher Br.(JV) 1678.240 29/06/2017 15/11/2019 100 23/02/2021
5 Rangunia
1 PD CLBUURP, W-204 Const. of RCC Bridge on Hazee Sayed Ali road (From RHD #98) at Ch. 11150m. 0.000 0.000 100 23/02/2021 Done by RHD
6 Raojan
1 PD CLBUURP, W-205 Const. of RCC Bridge on Haladia village road at Ch. 1700m(Ali Hosen mazer road). 353.860 MD.Yunusf & Brothers 353.860 16/05/2013 25/06/2016 100 18/02/2020
Total : 231.3000 (Km) 6487.30 (Lac) 6487.30 (Lac)