SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Magura-s
1 PD CLBUURP, W-270 Const. of RCC Bridge on Moghi UP office-Dhonepara Bazar via Andalbaria road at Ch. 8800m. 538.400 M/S.Shohor Enterprise & IT (JV) 538.400 11/02/2015 19/06/2017 100 14/07/2019
2 Mohammadpur
1 PD/CLBUURP/W- b)Remaining work for Const. of PC Girder Bridge over Madhumati river at Alangkhali Ghat 179.730 Nishit Bosu, Kanchannagar.Jhinaidah. 179.730 03/05/2018 75 20/02/2020
2 PD CLBUURP, W-269A Const. of RCC Bridge on Polita-Noliaghat road over Nobogonga river. 355.020 Brozen Kumar shaha 355.020 22/06/2009 14/06/2010 100 21/05/2019
3 PD CLBUURP, W-269 a) Const. of PC Girder Bridge over Madhumati river at Alangkhali Ghat. 4943.700 Max-Ranken (JV) 4943.700 11/11/2014 05/11/2017 100 21/05/2019
Total : 0.0000 (Km) 6016.85 (Lac) 6016.85 (Lac)