1 Fulchari
1 PD CLBUURP, W-339 Const. of RCC Bridge on Fulchari Upazila H/Q -Gunvary GC road at Ch. 1141m. 190.960 Basundhara-Rashed Khan 190.960 03/04/2018 29/04/2020 100 23/02/2021
2 PD CLBUURP, W-341 Const.of RCC Bridge on Udakhali UP-Singria Bazar road at Ch. 3610m. 140.290 Rafiq Construction Co. (Pvt.) Ltd. 140.290 03/04/2018 29/04/2019 95 25/08/2020
3 PD CLBUURP, W-340 Const. of RCC Bridge on Gunvary GC- Badiakhali R&H road Kutighat Bridge at Ch. 200m. 160.650 Rafiq Construction Co. (Pvt.) Ltd. 160.650 03/04/2018 29/04/2019 95 25/08/2020
2 Gaibandha-s
1 PD CLBUURP, W-223 Const. of RCC Bridge on Badia khali UP office-Chak Barul Bazar road at Ch. 3000m 0.000 0.000 100 23/02/2021 Done by Zila Parishad
3 Gobindaganj
1 PD CLBUURP, W-222 Const.of RCC Bridge on Katabari UP-Boglagari hat roadOver the Katakhali River at Ch.1700m 1119.810 Mir Akter-AR JV 1119.810 15/09/2014 20/03/2017 100 02/04/2019
4 Palashbari
1 PD CLBUURP, W-338 Construction of on Doblagari National Highway-Dolbhanga GC Via Amlagachi GC road Kutighat Bridge at Ch. 8050m. 395.220 Md. Abdul Latif Hakkani 395.220 29/03/2020 100 23/02/2021
5 Saghata
1 PD/CLBUURP/W-224 Const.of PC Girder Bridge on Bonarpara UP H/Q Ramnagar Bazar Road on the Katakhali River at ch: 4025m. 2412.460 M/S Surma 2412.460 28/05/2016 100 02/04/2019
6 Sundarganj
1 PD CLBUURP, W-337 Construction of Bridge on Sundarganj gaibandha road to Bhorarghat (mirganj) at ch.1000m 318.510 RSL Enterprise 318.510 27/11/2019 100 23/02/2021
2 PD CLBUURP, W-336 Const.of Bridge on Ram Dakua (Mohila bazar) via ponchanon Madrasa at ch.320m. 588.000 Projukti Prokoushal Ltd. 588.000 03/03/2020 95 23/02/2021
Total : 0.0000 (Km) 5325.90 (Lac) 5325.90 (Lac)