SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Fatikchari
1 IRIDP-2/CTG/DW-8 a) Improvement of Shahnagar Ambita to Uttar Gapalgatta Road lelang UP from Ch. 690-1500m.b) Construction of 02 nos 0.900mx0.900m culvert at ch. 790 & 1225m on the same road. 0.8100 25.100 M/S. Alif Enterprise 25.100 02/02/2016 01/06/2016 100 23/12/2018  
2 IRIDP-2/CTG/DW-7 a) Improvement of Islampur-Kesia road by from Ch. 00-685km.b) Construction of 1 No 4-vent 4.00x4.50m RCC box Culvert at ch. 450m on the same road. 0.6850 49.800 M/S. JS Traders, Prop: Syed Mohammed Zia Uddin Haider 49.800 04/03/2016 28/02/2017 100 23/12/2018  
3 IRIDP-2/CTG/DW-6 a) Improvement of Paindong UP H/Q(Brindabonhat) to Kanchannagar UP H/Q road via Kanchurhat from Ch: 6300-6650m & 6829-6965m.b) Construction of 02 nos 0.600mx0.600m culvert at ch. 6450 & 6510m on the same road. 0.3500 23.910 M/s. Anma Traders 23.910 06/06/2016 05/10/2016 100 23/12/2018  
4 IRIDP-2/CTG/DW-5 Improvement of Shompara-East Fatickchari Dawpara via Khamaripara road from Ch. 00-1593m. 1.5000 43.810 M/S. S Hoque & Sons Enterprise, Prop: Md. Jahangir Alam 43.810 19/03/2016 17/07/2016 100 23/12/2018  
5 IRIDP-2/CTG/DW-4 a) Improvement of Kanchannagar Tag Baria Tea Eastate road from Ch. 00-1190m.b) Construction of 1 No 4-vent 4.50x5.00m RCC Box culvert at Ch. 880m on the same road. 1.1900 78.500 M/S. Alif Enterprise 78.500 31/01/2016 30/12/2016 100 23/12/2018  
6 IRIDP-2/CTG/DW-3 a) Improvement of Gopalgatta Adarshgram to Gamaritola Kachua road (Ananda Bazar-Khiram Dowlat Munshirhat) from Ch: 00-1400mb) Construction of 01 no 0.900mx0.900m culvert at ch.550m on the same road. 1.4000 40.000 M/s. S Hoque & Sons Enterprise, Prop: Md. Jahangir Alam 40.000 22/03/2016 22/07/2016 100 23/12/2018  
7 IRIDP-2/CTG/DW-2 a) Improvement of Shaheed Ahammed Safa Road from Ch: 00-2000m.b) Construction of 1 No 4-vent 4.50x5.00m RCC Box culvert at Ch. 750m on the same road. 2.0000 90.550 M/s. Elias Brothers, Prop: Mohammad Elias Chowdhury 90.550 04/02/2016 30/04/2017 100 23/12/2018  
8 IRIDP-2/CTG/DW-1 a) Improvement of Nanupur UPC Doulat Munshirhat Bazar (Nanupur-Khiram) Road from Ch. 3900-6262m.b) Construction of 1X2.00mx2.00m culvert at ch.6210m on the same road. 2.3600 185.210 M/s R.N Enterprise. 185.210 0 23/12/2018  
2 Sandwip
1 IRIDP-2/CTG/DW-15 Improvement of Mandir road from Ch. 150-370m. 0.2200 20.290 M/S. H K Traders 20.290 08/02/2016 30/10/2016 100 23/12/2018  
2 IRIDP-2/CTG/DW-14 Improvement of Bosidia Road from Ch. 150-1025m. 0.8700 47.990 M/S. Alin Enterprise, Prop: Md. Altaf Hossain 47.990 31/01/2016 31/05/2016 100 23/12/2018  
3 IRIDP-2/CTG/DW-13 Improvement of Badalia road from Ch. 500-1860m. 1.3600 74.590 M/S. Peoples Corporation, Prop: Md. Jahangir Hossain 74.590 31/01/2016 15/05/2017 100 23/12/2018  
4 IRIDP-2/CTG/DW-12 Improvement of Darul Ulum Madrasha road from Ch. 900-1600m. 0.7000 38.390 M/S. Zakir Hossain 38.390 07/03/2016 07/07/2016 100 23/12/2018  
5 IRIDP-2/CTG/DW-11 Improvement of Hatem Mozi Road from Ch. 325-1200m. 0.8750 74.590 M/s. Sandwip Traders, Prop: Md. Siddiqur Rahman 74.590 07/03/2016 04/06/2016 100 23/12/2018  
6 IRIDP-2/CTG/DW-10 Improvement of Gasua Bauris boarder (RHD to Sowdargo) road from Ch. 325-1200m. 0.8750 47.990 M/S. Lucky Enterprise, Prop: Md. Nasir Uddin 47.990 31/01/2016 31/05/2016 100 23/12/2018  
7 IRIDP-2/CTG/DW-9 Improvement of Modhya Bauria Road (Horispur UP H/Q to Embankment) from Ch. 3340-4700m. 1.3600 74.590 M/S. Kamal Uddin Enterprise 74.590 31/01/2016 31/03/2017 100 23/12/2018  
Total : 16.5550 (Km) 915.31 (Lac) 915.31 (Lac)