SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
1
|
Barhatta
|
1
|
IRIDP-2/NTK/DW-4
|
a) Improvement of Alokdia Ferry ghat (Mohongonj GC)- Dharmapasha GC via Shingda Bazar Road (Barhatta Portion) ( Ch.00-1009m ) b) Construction of 1 no 0.600x0.600m Culvert on Same Road ( Ch.29m)
|
1.0090
|
67.260
|
M/S Anwara Enterprise
|
67.260
|
22/03/2016
|
30/11/2017
|
100
|
28/03/2019
|
|
2
|
IRIDP-2/NTK/DW-3
|
a) Improvement of Fakierar Bazar via Challishkahunia Baparipara to Barawari Ferryghat Road (Ch.00-1000.00m) b) Construction of 2nos 0.600x0.600m Culvert on Same Road (Ch. 260m, 475m)
|
1.0000
|
59.950
|
S. M. Angur
|
59.950
|
18/02/2016
|
20/09/2016
|
100
|
28/03/2019
|
|
3
|
IRIDP-2/NTK/DW-2
|
a) Improvement of Kandapara UZR-Pochim Shalipura Ferry Ghat Road (Ch. 00-500.00m.) b) Construction of 1no 0.600x0.600m Culvert on Same Road (Ch59m)
|
0.5000
|
30.530
|
M/S Anwara Enterprise
|
30.530
|
21/03/2016
|
18/12/2016
|
100
|
28/03/2019
|
|
4
|
IRIDP-2/NTK/DW-1
|
a) Improvement of Dattragram(LSD Godown)-Shahata Road(Ch.500-1000m.) b) Construction of 4 nos 0.600x0.600m Culvert on Same Road (Ch637m,703m,880m,940m)
|
0.5000
|
32.750
|
M/S Ammajan Enterprise
|
32.750
|
03/03/2016
|
03/10/2016
|
100
|
28/03/2019
|
|
|
2
|
Durgapur
|
1
|
IRIDP-2/NTK/DW-15
|
a) Improvement of Keronkhola-Mou madrasha Road (Ch. 00-500m) b) Construction of 1 nos 0.625x0.600m Culvert on Same Road (Ch. 300m)
|
0.5000
|
22.850
|
Amina Enterprise
|
22.850
|
03/03/2016
|
31/07/2016
|
100
|
23/12/2018
|
|
2
|
IRIDP-2/NTK/DW-14
|
a) Improvement of Kumudgonj GC-Sidly GC road via Abbas Nagar bazar road (Ch.4450-6200m) b) Construction of 2 nos 0.625x0.600m Culvert on Same Road (Ch. 5200m, 5800m)
|
1.7500
|
99.680
|
M/S Hawlader Builders
|
99.680
|
03/03/2016
|
27/12/2016
|
15
|
23/12/2018
|
|
3
|
IRIDP-2/NTK/DW-13
|
a)Improvement of Durgapur GC-Kumudgonj GC Road (Ch.2422-3422m) b) Construction of 2 nos 0.625x0.600m Culvert on Same Road (Ch. 3112m, 3232m)
|
1.0000
|
71.660
|
M/S Rocky Enterprise
|
71.660
|
07/03/2016
|
01/12/2016
|
100
|
23/12/2018
|
|
|
3
|
Kendua
|
1
|
IRIDP-2/NTK/DW-12
|
a)Improvement of Asujia UP Office - Gopalpur Bazar via Amlitola and Sarapara Bazar road (Ch.00-3020m) b) Construction of 8 nos 0.625x0.600m Culvert on Same Road (Ch. 213m, 771m, 835m, 1063m, 1524m, 1851m, 2231m, 2654m)
|
3.0200
|
178.710
|
M/S Kamrul Islam
|
178.710
|
18/02/2016
|
15/02/2017
|
100
|
23/12/2018
|
|
2
|
IRIDP-2/NTK/DW-11
|
a) Improvement of Raintreetola-Kachandara road ( Ch.00-1060m & Ch.1650-2000) b) Construction of 6 nos 0.625x0.600m Culvert on Same Road (Ch422m,461m,550m,600m,664m,1843m) c) Construction of 6nos 0.375x0.450m Culvert on Same Road (Ch300m,540m,605m,1860m,18
|
1.0000
|
100.340
|
M/S Kamrul Islam
|
100.340
|
18/02/2016
|
15/02/2017
|
100
|
23/12/2018
|
|
3
|
IRIDP-2/NTK/DW-10
|
a)Improvement of Noadia-Hasuary ferry ghat via Asujia UP Office ( Ch. 00-3825m) b) Construction of 13nos 0.625x0.600m Culvert on Same Road (Ch. 64m, 110m, 142m, 274m, 360m, 500m, 980m, 1180m, 1395m, 2310m, 2740m, 2942m, 3438m)
|
3.8250
|
222.710
|
M/S Kamrul Islam
|
222.710
|
20/04/2016
|
19/04/2017
|
100
|
23/12/2018
|
|
|
4
|
Purbadhala
|
1
|
IRIDP-2/NTK/DW-5
|
a) Improvement of Vikunia - Megshimul Bazar road ( Ch. 00-1000m) b) Construction of 5 no 0.600x0.600m Culvert on Same Road (Ch. 175m. 470m, 570m, 857m, 963m)
|
1.0000
|
64.330
|
Md. Sarwar Jahan
|
64.330
|
03/03/2016
|
31/03/2017
|
100
|
28/03/2019
|
|
2
|
IRIDP-2/NTK/DW-9
|
a)Improvement of Netrakona-Mymensingh road (Infront of Petrol Pump)-Jalsuka H/O Mr. Mohammad Ali (Ch.00-725m) b) Construction of 4nos 0.450x0.450m Culvert on Same Road (Ch. 38m, 450m, 495m, 550m)
|
0.7250
|
47.380
|
Md. Sarwar Jahan
|
47.380
|
02/03/2016
|
30/11/2017
|
100
|
23/12/2018
|
|
3
|
IRIDP-2/NTK/DW-8
|
Improvement of Budhi-Barha road (Ch.1000-2800m)
|
1.8000
|
98.160
|
Md. Sarwar Jahan
|
98.160
|
08/03/2016
|
31/07/2018
|
40
|
23/12/2018
|
|
4
|
IRIDP-2/NTK/DW-7
|
a)Improvement of Moudam-Khatuary via Ram Kanda road (Ch. 00-1500m) b) Construction of 8nos 0.450x0.450m Culvert on Same Road (Ch. 56m, 200m, 249m, 410m, 505m, 553m, 815m, 1117m) C) Construction of 2noS 0.600x0.600m Culvert on Same Road (Ch.1288m. 1458m)
|
1.5000
|
105.030
|
Sheikh Hemayet Ali
|
105.030
|
09/02/2016
|
31/12/2017
|
100
|
23/12/2018
|
|
5
|
IRIDP-2/NTK/DW-6
|
a)Improvement of Lawkhai Shop of Moti-Kazla Boarder road (Ch. 00-2300m) b) Construction of 10 nos 0.450x0.450m Culvert on Same Road (Ch. 80m, 180m, 320m, 572m, 608m, 837m, 1051m, 1765m, 1870m, 2263m) c) Construction of 3 nos 1.50mx1.50m RCC Box culvert on
|
2.3000
|
158.910
|
Ashim Singh
|
158.910
|
21/03/2016
|
24/04/2017
|
100
|
23/12/2018
|
|
|
Total :
|
21.4290 (Km)
|
1360.25 (Lac)
|
1360.25 (Lac)
|
|
|
|
|
|
|