SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Sariakandi
1 IRIDP-2/BOG/DW-13 Improvement of Shariakandi LSD Godaun-Paikpara road (Ch. 00-400m). 0.4000 20.920 M/S. Islam Enterprise 20.920 07/02/2016 09/06/2016 100 23/12/2018  
2 IRIDP-2/BOG/DW-12 Improvement of Fulbari UP-Sagoldhara Ghat road via Sagoldhara Bazar (Ch. 1000-2000m) 1.0000 52.370 M/S. Islam Enterprise 52.370 07/03/2016 15/12/2016 100 23/12/2018  
3 IRIDP-2/BOG/DW-11 Improvement of Velabari UP-Sonahata GC via Jorgacha hat Road (Bhelabari-Jorgacha road) (Ch.00-800m). 0.8000 42.610 M/S. Mondul Construction 42.610 07/02/2016 30/04/2016 100 23/12/2018  
4 IRIDP-2/BOG/DW-10 Improvement of Hatsherpur UP-Charpara Bazar via Solur ghat Road (Sariakandi part) (Ch.00-815m). 0.8150 52.250 M/S. Islam Enterprise 52.250 07/02/2016 31/05/2017 100 23/12/2018  
2 Sherpur
1 IRIDP-2/BOG/DW-4 a) Improvement of Chakkallani Mokbul hose-Chalkdhuli road (via Hospital) road (Ch. 1700-2000m). b) Construction of 1 Nos culvert 0.625x0.600m at Ch. 2135m. 0.3000 27.960 Md. Anisur Rahman 27.960 07/02/2016 10/07/2016 100 23/12/2018  
2 IRIDP-2/BOG/DW-3 Improvement of Joylajuan Baher house-Hospital road (Ch. 00-829m). 0.8290 36.630 M/S. Hiemel Enterprise 36.630 07/02/2016 10/07/2016 100 23/12/2018  
3 IRIDP-2/BOG/DW-2 a)Improvement of Ghoga Hat (NHW)-Bishwa Hat-Atail-Bhabanipr UP road (Ch.9250-10500m). b) Construction of 1 Nos 2.00x1.60m RCC Box culvert at Ch. 10181m. b) Construction of 1 Nos culvert 0.625x0.600m at Ch. 10490m. 8.2000 70.850 M/S. Mina Traders 70.850 28/01/2016 10/08/2016 100 23/12/2018  
4 IRIDP-2/BOG/DW-1 Improvement of Ulipur NHW-Dhunat UHQ road Via Jhanjar Ghat (Sherpur Part) (Ch.7754-8904m). 1.1500 69.800 M/S. Mina Traders 69.800 07/02/2016 10/08/2016 100 23/12/2018  
3 Shibganj
1 IRIDP-2/BOG/DW-15 a) Improvement of Mohastan Mazar road (Ch. 00-1472m b)Construction of 6-Nos culvert 0.625x0.600m at ch. 08, 182, 615, 1135, 1358 & 1471m. 1.4720 80.980 M/S. Roxy Enterprise 80.980 08/02/2016 31/03/2017 100 23/12/2018  
2 IRIDP-2/BOG/DW-14 a) Improvement of Mohastan NHW-East Mohastan Village road (Ch. 00-680m) b)Construction of 1-Nos culvert 0.625x0.600m at ch. 432m. 0.6800 49.610 M/S. Tisha Enterprise 49.610 08/02/2016 11/09/2016 100 23/12/2018  
4 Sonatala
1 IRIDP-2/BOG/DW-9 a)Improvement of Milonerpara Pucca Mosque-Padmapara GPS road (Ch. 00-500m). b)Construction of 1-Nos culvert 0.625x0.600m at ch.216m. 0.5000 27.440 M/S. M.R Enterprise 27.440 05/02/2016 10/07/2016 100 23/12/2018  
2 IRIDP-2/BOG/DW-8 Improvement of Burardha-Digdair GPS road Ch. 00-500m 0.5000 25.580 M/S. M.R Enterprise 25.580 05/02/2016 10/07/2016 100 23/12/2018  
3 IRIDP-2/BOG/DW-7 a) Improvement of Jahanabad Madrasha (Hagagari Bridge)-Shagorghat Bridge road (Ch.00-1245m). b) Construction of 1x1.60x1.60m RCC Box culvert at Ch.566m. c)Construction of 1-Nos culvert 0.625x0.600m at ch. 672m. 1.2450 74.510 M/S. Sobin Traders 74.510 05/02/2016 31/12/2016 100 23/12/2018  
4 IRIDP-2/BOG/DW-6 a) Improvement of Karpurhat-Sonaray UP via Rajghat road (Ch. 500-1500m). b) Construction of 1nos 1.60x1.60m RCC Box culvert at Ch. 1031m c) Construction of 1-Nos culvert 0.625x0.600m at ch 973m. 1.0000 59.600 M/S. Mondul Construction 59.600 08/02/2016 28/02/2017 100 23/12/2018  
5 IRIDP-2/BOG/DW-5 a) Improvement of Jorgacha UP-Charpara hat via Sonakania Dokhinpara road (Ch. 3000-4000m). b)Construction of 1-Nos culvert 0.625x0.600m at ch.3190m. 1.0000 62.290 M/S. Sobin Traders 62.290 07/02/2016 31/12/2016 100 23/12/2018  
Total : 19.8910 (Km) 753.40 (Lac) 753.40 (Lac)