SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Beanibazar
1 IRIDP-2/SYL/DW-15 Improvement of Matikata-Korolnodi Road (Ch. 00-500m). 0.5000 27.870 M/s. Radif Enterprise 27.870 05/04/2016 10/06/2017 100 23/12/2018  
2 IRIDP-2/SYL/DW-14 Improvement of Fangram-Changram-Nageshor Road (Ch. 00-854m). 0.8540 57.960   57.960 0 23/12/2018  
2 Biswanath
1 IRIDP-2/SYL/DW-13 Improvement of Bairagi Bazar GC - Nowdhar Ujijuri Road (Ch.600-1100m). 0.5000 28.220 Yousup Ali Construction 28.220 14/02/2016 30/06/2017 100 23/12/2018  
2 IRIDP-2/SYL/DW-12 Improvement of Pretigonj Puran Bazar Road to Kabilpur Jame Mosque Road via Vatpara Joynagar Road (Ch.1100-1600m). 0.5000 23.370 Md. Taibur Rahman 23.370 14/02/2016 30/12/2016 100 23/12/2018  
3 IRIDP-2/SYL/DW-11 Improvement of Gagutia- Chaitannar Primary School Road (Ch. 13 - 513m). 0.5000 23.260 Yousup Ali Construction 23.260 08/08/2016 14/06/2016 100 23/12/2018  
4 IRIDP-2/SYL/DW-10 a) Improvement of Amtail Bazar- Gazir Mokam Road (Ch.00-450m). b) Construction of 2Nos. 625mmx600mm Drain Culvert at ch. 28m & 53m on the same road. 0.4500 22.240 Yousup Ali Construction 22.240 08/08/2016 15/03/2017 100 23/12/2018  
5 IRIDP-2/SYL/DW-9 Improvement of Bagichabazar (Seraj Khan Pettrol Pump) - Pachim Kalijuri Road (Ch.00-500m). 0.5000 23.440 Md. Taibur Rahman 23.440 08/08/2016 25/12/2016 100 23/12/2018  
6 IRIDP-2/SYL/DW-8 Improvement of Betsandi BC Road - Sagirshah Mazar Road (Ch.00- 650m). 0.6500 30.260 Humayun Kabir 30.260 08/08/2016 14/06/2016 100 23/12/2018  
7 IRIDP-2/SYL/DW-7 Improvement of Gudamghat Road to Agnapara grame (East side) (Ch.00- 1003m). 1.0030 47.750   47.750 0 23/12/2018  
8 IRIDP-2/SYL/DW-6 a) Improvement of Durjakapon - Habrabazar Road (Ch. 1700-2700m). b) Construction of 2Nos. 625mmx900mm Drain Culvert at ch. 2235m & 2695m on the same road. 1.0000 47.900 Md. Taibur Rahman 47.900 08/08/2016 25/12/2016 100 23/12/2018  
3 Golapganj
1 IRIDP-2/SYL/DW-5 Improvement of Dattarial Eidgha - Salamgaon Road (Ch: 00-320m). 0.3200 16.810 Setu Enterprise 16.810 07/02/2016 20/12/2016 100 23/12/2018  
2 IRIDP-2/SYL/DW-4 a) Improvement of Barkot- BNK Road (Ch: 244-765m). b) Construction of 1No. 625mmx600mm Drain Culvert at ch. 654m on the same road. 0.5210 29.520 Setu Enterprise 29.520 07/02/2016 20/12/2016 100 23/12/2018  
3 IRIDP-2/SYL/DW-3 a) Improvement of Dharabohar Mian Jame Mosjid- Kawolipara- Shailghat Road (Ch: 00-500m). b) Construction of 2Nos. 625mmx600mm Drain Culvert at ch. 140m & 315m on the same road. 0.5000 25.120 Setu Enterprise 25.120 07/02/2016 20/12/2016 100 23/12/2018  
4 IRIDP-2/SYL/DW-2 Improvement of Hazipur-Larifor road (Ch: 1465-1881m). 0.4160 23.260 Setu Enterprise 23.260 07/02/2016 30/05/2017 30 23/12/2018  
5 IRIDP-2/SYL/DW-1 Improvement of Bhadeshwar- Maisbag- Hafizea Madrasha Road (Ch: 900-1400m). 0.5000 29.070 Setu Enterprise 29.070 07/02/2016 20/12/2016 100 23/12/2018  
Total : 8.7140 (Km) 456.05 (Lac) 456.05 (Lac)