Project Scheme Detail List
SL No.
Package No.
Name
Length (Km)
Allotment (Lac)
Name of Contractor
Contract Amount (Lac)
Date of Commencement
Date of Completion
Physical Progress (%)
Date of Progress Update
Remarks
1
Kaunia
1
(SHOUIII/Ran/W-14).
Repair Work of Shahidbag Union Parishad Complex Bhaban .
18.570
M/s. Moon Traders, Horishor, Kaunia, Rangpur
18.570
12/11/2018
10/02/2019
100
10/04/2019
on going
2
Pirgacha
1
SHOU III/ Ran/W-13
Repair Work of 01 no. Kallani Union Parishad Complex Bhaban
27.060
M/s.Akhi Enterprise,Alamnagar-5402, Rangpur
27.060
30/10/2018
10/05/2019
100
03/07/2019
Completed
2
SHOU III/ Ran/W-12
Repair Work of Parul Union Parishad Complex Bhaban
27.070
M/s. Masud Enterprise, Fire Service Road, Lalmonirhat.
27.070
11/11/2018
10/05/2019
100
03/07/2019
Completed
Total :
0.0000 (Km)
72.70 (Lac)
72.70 (Lac)