SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Magura-s
1 SP24118/Lakshmipur Khal Subproject Re-excavation of Lakshmipur Khal (Ch: 0.00 - 2.1 m) and Provisional Sum. Reference Lined Section (3 nos.) and SP Identification Signboard (2 nos.) Repairing of WMCA Building (Semi pacca) - 27.124 OTM 27.124 10/09/2020 28/04/2021 100 13/08/2024 Completed
Total : 0.0000 (Km) 27.12 (Lac) 27.12 (Lac)