Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Fulbaria
1 SP33088 Foliar Khal Sub-project: Foliar Khal WRS 2Vent 1.5mx1.80m, Re-excavation of Foliar Khal 4.10 km (Ch.0.00km to Ch.4.10km) and Re-sectioning of Embankment 1.861 (Ch.0+00km to Ch.1+861km) 5.9600 145.620 LCS 145.620 30/04/2019 90 21/08/2020 On going
2 Phulpur
1 SP32027 Kharia Nadi Sub-project: Construction of Regulator (at ch. 1+690km), Re-excavation of Kharia Nadi at (Ch.0+000km to Ch.12+800km), Re-excavation of suti khal at (Ch.0+00km to Ch.2+275km), Re-sectioning of Embankment 14.7100 238.480 LCS 238.480 30/04/2020 60 21/08/2020 On going
Total : 20.6700 (Km) 384.10 (Lac) 384.10 (Lac)