Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Faridpur-s
1 SP71006 Kadmi khal Sub-project : Re-excavationof kadmi khal(Ch.1+000km to Ch.6+400km) 4.4000 180.850 LCS 180.850 18/04/2020 70 21/08/2020 On going
2 Madhukhali
1 SP32009 Satgavia Sub-project : Construction of Pipe culvert at (Ch.2+190km),Construction of Pipe culvert at (Ch.3+600km),Re-sectioning fram level road (Ch.1+000km to Ch.4+923km) 3.9200 91.960 LCS 91.960 30/04/2020 90 21/08/2020 Tender Approved
Total : 8.3200 (Km) 272.81 (Lac) 272.81 (Lac)