SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Azmiriganj
1 SP35180 Hirabari-Monsur khal Sub-project: Re-excavation of Kachura khal(Additional) (Ch.6+600km to Ch.10+004km), Re-excavation of pabiajuri khal(Additional) (Ch.0+000km to Ch.3+700km) 7.1100 188.950 LCS 188.950 30/04/2020 100 21/08/2020 On going
2 Nabiganj
1 SP32023 Raipura Boro khal Sub-project: Re-excavation of Raipura Boro khal (Ch.0+000km to Ch.5+300km) 5.3000 158.430 LCS 158.430 0 21/08/2020 Approved
2 SP31004 Arua-Kalkalia Sub-project: Re-excavation of Arua-Kalkalia Khal 3.875 km (Ch.1+700km to Ch.5+575km) and Reference Bed Block 4 Nos (Ch.2+00km, 3+00km, 4+00km & 5+00km) 3.8800 126.850 LCS 126.850 30/04/2019 100 21/08/2020 On going
Total : 16.2900 (Km) 474.23 (Lac) 474.23 (Lac)