Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bhedarganj
1 MSRDP/S/18-19/BC/115 Part-1: Improvement of Road by Paprail Baitul Aka Lam-E Mosque to paprail Jobber Sarder Bari Road at Ch.800-1550m under Bhedarganj Upazila, District Shariatpur. Part-2: Improvement of Road by Bituminous Carpating at Ch.00-630m on Monua Bazar – Aterpara PS Via Monua Madrasha Road under Bhedarganj Upazila, District Shariatpur. 1.3800 115.310 M/S Samim Traders 115.310 02/09/2019 01/09/2020 100 12/07/2020
2 MSRDP/S/18-19/BC/114 Part-1: Improvement of Road by Bituminous carpeting at Ch. 00-490.00m on Monua H/O Mazid Bioati- H/O Sorab Ali Biswas road under Bhedarganj Upazila District Shariatpur. Part-2: (A). Improvement of Road by at Sajonpur pry.school- Mirjapur via Sardar Bari Road Ch.580-1800m. (B). Construction 01 Nos (One) U-Drain on Sajonpur pry.school-Mirjapur via Sardar Bari Road at Ch.1692m under Bhedarganj Upazila District Shariatpur. 1.7100 139.450 M/S Mollah Enterprise 139.450 02/09/2019 01/09/2020 75 12/07/2020
3 MSRDP/S/18-19/BC/100 Part-1: Improvement of road by BC at H/O Satter Howlader to H/O Giasuddin Howlader via H/O Harun Sayal road Ch.0.00m – 2300.00m under Bhedargonj, Upazila, District: Shariatpur ( Road ID No: 386145045). Part-2: Improvement of road by BC Ferangi Kandi- Bhedarganj road – Singjala RPS Road Ch.0.00m – 600.00m under Bhedargonj, Upazila, District: Shariatpur ( Road ID No: 386145242). 2.9000 254.370 M/S Mollah Enterprise 254.370 03/06/2019 30/06/2020 45 12/07/2020
4 MSRDP//18-19/BC/95 1)Improvement of road by BC at Kartickpur Bridge- Sanilkandi Bazar road via Miarchar road Ch.2000.00m – 3200.00m under Bhedargonj Upazila, District: Shariatpur.2)Improvement of road by BC at Charchanda Kalu Munshikandi – Char Chanda Abul Halder Master House road ( Starting point Bhedargonj- Shakhipur GC road Near of Culvert ) Ch.0.00m – 1800.00m under Bhedargonj Upazila District: Shariatpur.Details Estimate for construction of 16.00m RCC Girder Bridge on Shanti Nagar Sayial bazaar -101 No Char Mohishkhali Sarkandi GPS road at Ch.5Km under Bhedargonj Upazila, District: Shariatpur. 2.8000 336.400 M/S Mollah Enterprise 336.400 03/06/2019 30/06/2020 80 09/07/2020
5 MSRDP//18-19/BC/89 Part-1: Improvement of road by BC at Nadu Sarker House to Char Sajonpur Primary School road Ch.0.00m – 1480.00m under BhedargonjUpazila, District: Shariatpur.Part-2:Improvement of road by BC at Rup Nagar bazar to Arshinagar road via Sarker Bari road Ch.0.00m – 1590.00m under Bhedargonj, Upazila, District: Shariatpur.Part-3: Improvement of road by BC at Nowsha Bala Bridge to Shakhipur Boarder road Ch.0.00m – 1690.00m under Bhedargonj, Upazila, District: Shariatpur. 4.7600 344.040 Md: Younus Ali Brothers 344.040 17/06/2019 16/06/2020 30 09/07/2020
6 MSRDP/S/17-18/SR/39 Construction of 2x4.50mx4.50m RCC Box Culvert (w=3.66m) on Kashempur - Kader Sarker Kandi road at ch. 250.00m under Bhedargonj Upazila, Dist. Shariatpur. 0.0090 21.525 M/s. Aziz Construction 21.525 27/06/2018 25/03/2019 100 09/07/2020 Final Bill paid.
7 MSRDP/S/17-18/BC/40 Improvement of BC Road on Kasimpur - Kader Sarkarkandi road at ch. 0.00 - 1590.00m & Construction of 1 nos U-Drain on Kasimpur - Kader Sarkarkandi road at ch. 1050.00m under Bhedargonj Upazila Dist. Shariatpur. 1.5900 105.220 M/s. Acila Enterprise 105.220 27/06/2018 25/06/2019 100 09/07/2020 Final Bill paid.
8 MSRDP/S/17-18/SR/41 Construction of 2x4.50mx4.50m RCC Box Culvert (w=3.66m) on Bhedarganj - Shakhipur road-Kartickpur Bridge road at ch. 04.00m under Bhedargonj Upazila, Dist. Shariatpur. 22.178 M/s. Tarongo Traders 22.178 27/06/2018 26/03/2019 75 09/07/2020
9 MSRDP/S/17-18/SR/42 Construction of 2x4.50mx4.50m RCC Box Culvert (w=3.66m) on Bhedarganj - Shakhipur road-Kartickpur Bridge road at ch. 860.00m under Bhedargonj Upazila, Dist. Shariatpur. 22.178 M/s. Habiba Enterprise 22.178 12/06/2018 11/04/2019 100 09/07/2020 Final Bill paid.
10 MSRDP/S/17-18/BC/43 Improvement of BC Road on Shakhipur GC road to Payatoli road via Charchanda Munshi Bari School road at ch. 0.00 - 1500.00m & Construction of 1 nos 1x3.00x3.00m RCC Box Culvert at ch. 834.00 & 1 nos U-Drain at ch. 472.00 on same road under Bhedargonj Upazila Dist. Shariatpur. 2.2250 142.047 M/s. Nuha&Fiha Enterprise 142.047 27/06/2018 11/06/2019 100 09/07/2020 Final Bill paid.
11 MSRDP/S/17-18/BC/44 Improvement of BC Road on Highway road - H/O Azharul Bala road at ch. 0.00 - 2130.00m under Bhedargonj Upazila Dist. Shariatpur, (Road ID No- 386144026). 2.1300 151.382 M/s. Mim Traders 151.382 27/06/2018 25/06/2019 100 09/07/2020 Final Bill paid.
12 MSRDP/S/17-18/BC/45 Improvement of BC Road on Char Chanda Ukil Kandi Pucca Road-Bakaul Kandi road at ch. 0.00 - 1070.00m & Cosntruction of 1 nos U-Drain ch. 1015.00m on the same road under Bhedargonj Upazila Dist. Shariatpur.Improvement of BC Road on High Way road-Zia Kandi Anu Madbor House road at ch. 0.00 - 1500.00m & Cons. of 1 nos 1x3.00x3.00m RCC Box Culvert at ch. 1340.00m & Cons. 1 nos U-Drain at ch. 1050.00m on the same road under Bhedargonj Upazila Dist. Shariatpur. 2.5700 173.683 M/s. Shifa Enterprise 173.683 27/06/2018 25/06/2019 100 09/07/2020 Final Bill paid.
13 MSRDP/S/17-18/SR/46 Construction of 2x4.50mx4.50m RCC Box Culvert (w=3.66m) on D.M Khali Bazar - Sadar Kandi road at ch. 47.00m under Bhedargonj Upazila, Dist. Shariatpur. 22.084 M/s. Iqbal Hossain Mridha 22.084 18/06/2018 15/03/2019 100 09/07/2020 Final Bill paid.
14 MSRDP/S/17-18/BC/47 Improvement of BC Road on Chaygoan Madrasha to Venopa Bazar via H/O Krisna Master road at ch. 2200.00 - 3100.00m under Bhedargonj Upazila Dist. Shariatpur. Improvement of BC Road on Bhedarganj Burirhat road - Akkasia Primary School via H/O Hamid Gazi road at ch. 2160.00 - 2750.00m under Bhedargonj Upazila Dist. Shariatpur.Improvement of BC Road on Ferangeykandi P.S to Bhedarganj Bridge road at ch. 0.00 - 791.00m under Bhedargonj Upazila Dist. Shariatpur. 2.2810 161.728 M/s. Rishad Traders 161.728 14/06/2018 11/05/2019 100 09/07/2020 Final Bill paid.
15 MSRDP/S/17-18/BC/48 Improvement of BC Road on H/O Manggal Sarder - Koraltali GPS road at ch. 0.00 - 566.00m & Cosn. of 1x3.00x3.00 RCC Box Culvert at ch. 156.00m on the same road under Bhedargonj Upazila Dist. Shariatpur.Improvement of BC Road on Pachim Chaygoan - Sayal Bari Bridge (Mothkhola) - Burirhat road at ch. 770.00 - 1220.00m & Cosn. of 1x3.00x3.00m RCC Box Culvert at ch. 1160.00m on the same road under Bhedargonj Upazila Dist. Shariatpur. 1.0160 108.113 M/s. Delawar Hossain Mollik & Co 108.113 18/06/2018 16/06/2019 100 09/07/2020 Final Bill paid.
16 MSRDP/S/17-18/HBB/49 Improvement of HBB Road on Chaygoan Govt. Pry. School - Burirhat road via Ranishar road at ch. 0.00 - 1830.00m & Cosn. of 2x4.50x4.50 RCC Box Culvert (w=3.66m) at ch. 610.00m on the same road under Bhedargonj Upazila Dist. Shariatpur. 1.8300 146.602 M/s. T.T.M. Trading 146.602 27/06/2018 25/06/2018 100 09/07/2020 Final Bill paid.
17 MSRDP/S/17-18/BC/55 Part-A: Improvement of BC Aterpara Pucca Bridge - Aterpara GPS road via H/O Karim Molaah road at ch. 800.00 - 1060.00m under Bhedargonj Upazila Dist. Shariatpur. Part-B: Improvement of BC Rambhadrapur Lanchghat - Naria Border via Saner Bazar road at ch. 2400.00 - 3200.00m under Bhedargonj Upazila Dist. Shariatpur.Part-C: Improvement of HBB Lakarta ICE Factory-Digambory road at ch. 2000.00 - 3060.00m under Bhedargonj Upazila Dist. Shariatpur. 2.1200 136.822 M/s. Jorasako International 136.822 21/06/2018 17/08/2019 100 09/07/2020 Final Bill paid.
18 MSRDP/S/17-18/BC/Maint-01 Maintenance of H/O Sekandar Madbor - Shakhipur GC road from Ch. 0.00 - 1540m by bc under Bhedargonj Upazila, Dist. Shariatpur. Maintenance of K.M Pry. School - Paprail road from Ch. 0.00 - 1190.00m by bc under Bhedargonj Upazila, Dist. Shariatpur .Maintenance of Lakarta IC Fectory - Digambory road from Ch. 0.00 - 555.00m by BC under Bhedargonj Upazila, Dist. Shariatpur 3.2850 51.812 M/s. Delwar Hossian Mollil 51.812 01/07/2018 29/04/2019 100 09/07/2020 Final bill paid.
19 MSRDP/S/17-18/BC/54 Part-A: Improvement of BC Charchanda Kalu Munshikandi-Char Chanda Abul Halder Master House road at ch. 1800.00 - 2900.00m & Madasha Link-230.00m b. Construction of 1x3.00x3.00m RCC Box Culvert on Same Road at Ch. 2320.00m under Bhedargonj Upazila Dist. Shariatpur,Part-B: Improvement of HBB Munshi Kandi GPS-Mozai Mollar Kandi road at ch. 0.00 - 1710.00m under Bhedargonj Upazila Dist. Shariatpur. 2.3000 142.150 M/S USA TRADERS 142.150 18/06/2018 16/06/2019 100 08/07/2020 Final Bill Paid.
20 MSRDP/S/18-19/BC/91 Improvement of road by BC at Bangla Bazar – Upazila Sadar road via Ali Akbar Lasker at Charkumaria road Ch.1150.00m – 2000.00m under Bhedargonj Upazila, District: Shariatpur. (Road ID No: 386145087). 0.8500 64.100 M/S Soikot enterprise 64.100 13/05/2019 13/02/2020 100 08/07/2020 Final Bill Paid.
21 MSRDP/S/17-18/BC/90 Improvement of road by HBB Charbhaga Pada Kandi – H/O Moti Master via Bokaul Kandi road Ch.1600.00m – 2600.00m. Construction of 2x4.50mx4.50m RCC Box Culvert (w=3066m) Charbhaga Pada Kandi – H/O Moti Master via Bokaul Kandi road Ch.2028.00m.Construction of 01 Nos (One) U-Drain HBB on Charbhaga Pada Kandi – H/O Moti Master via Bokaul Kandi road Ch.2470.00m under Bhedargonj Upazila, District: Shariatpur. 1.0000 51.690 m/s Alomgir traders 51.690 26/02/2019 25/11/2019 100 08/07/2020
22 MSRDP//18-19/BC/94 Part-1: Improvement of road by BC at Mazi Kandi – Station bazar via Ananda Bazar road Ch.750.00m – 3000.00m under Bhedargonj, Upazila District: Shariatpur. (Road ID No: 386144022). Part-2: Improvement of road by BC at Afamollah Bazar – Char- Sheris P/S. road Ch.0.00m – 2750.00m Construction of 2x4.50mx4.50m RCC Box Culvert (w=3066m) Afamollah Bazar – Char- Sheris P/S. road Ch.1410.00m under Bhedargonj, Upazila, District: Shariatpur.( Road ID No: 386145069). Part-3: Improvement of road by BC at Saifullah Master School – Prodhania Kandi road Ch.0.00m – 1520.00m & School Link -50m under Bhedargonj Upazila, District: Shariatpur. (Road ID No: ). 6.5200 336.400 m/s mollah enterprise 336.400 0 08/07/2020 NOA issue
23 MSRDP/S/17-18/SR/38 Construction of 2x4.50mx4.50m RCC Box Culvert (w=3.66m) on Charchanda Puran Bazar-D.M Khali UP road (Near of Munshi Bari) at ch. 525.00m under Bhedargonj Upazila, Dist. Shariatpur. 21.525 M/s. Hawlader Enteprise 21.525 27/06/2018 25/03/2019 100 08/07/2020
2 Damuddya
1 MSRDP//18-19/BC/107 Improvement road by BC Shidulkura bazar- Baroghar Road at Ch.1570.00m – 3460.00m. Damuddya Upazila, District: Shariatpur. 1.8900 204.390 M/S Samim Traders 204.390 03/06/2019 02/06/2020 75 12/07/2020
2 MSRDP/S/17-18/BC/66 Improvement of BC Dhanhata Steel Bridge - Food Godwon at ch. 136.00 – 625.00m under Damuddya Upazila Dist. Shariatpur. 0.4900 21.790 M/S Himu Enterprise 21.790 26/07/2018 25/04/2019 100 09/07/2020 Final Bill Paid.
3 MSRDP/S/17-18/SR/34 Construction of 2-Vent (4.00x4.00m) Box Culvert on Tilai DC road-Dakhin Para via Kanaikati road at Ch. 222.00m under Damuddya Upazila, Dist. Shariatpur. 28.934 M/s. Zerin Traders 28.934 04/06/2018 03/04/2019 100 09/07/2020 Final Bill paid.
4 MSRDP/S/17-18/BC/35 a) Improvement of BC Road on Mazirtek - Syedbasta via Ekori road at Ch. 1300.00 - 1597.00m under Damuddya Upazila Dist. Shariatpur.b) Improvement of BC Road on Modernhat - Balakandi road at Ch. 1687.00 - 3340.00.00m under Damuddya Upazila Dist. Shariatpur. 1.3560 130.124 M/s. Irin Enterprise 130.124 24/05/2018 23/05/2019 70 09/07/2020
5 MSRDP/S/17-18/BC/67 Improvement of BC Malgong Ataimkhana D. C road–Anandobazar via Bhuabazar, chairs Danukati Gps. at ch. 1680.00 - 3388.00m under Damuddya Upazila Dist. Shariatpur. 1.7080 116.698 M/s. Madbar Enterprise 116.698 02/08/2018 01/08/2019 100 09/07/2020 Final Bill paid.
6 MSRDP/S/17-18/BC/68 Part-1: Improvement of BC Tilai DC road- Dakhin para via Kkanaikati road at ch. 427.00 – 1200.00m under Damuddya Upazila Dist. Shariatpur.Part-2: Improvement of BC Syedbosta Kheyagaat- Damudya at ch. 0.00 – 775.00m under Damuddya Upazila Dist. Shariatpur. 1.5480 103.508 M/s. Nusrat Zahan Enterprise 103.508 02/08/2018 01/04/2019 60 09/07/2020 Final Bill paid.
7 MSRDP/S/17-18/BC/69 Improvement of BC Dhani Bazar- Amin Bazar via Akan bari Mosque .at ch 00.00 - 3137.00m under Damuddya Upazila Dist. Shariatpur. 3.1370 205.750 M/s. Alif Enterprise 205.750 08/08/2018 07/11/2019 100 09/07/2020 Final Bill paid.
8 MSRDP/S/17-18/BC/70 Improvement of BC Thanger Bari Bidge- Gani Sarder Bridge Via Kotal Bari .at ch 00.00 - 1762.00m under Damuddya Upazila Dist. Shariatpur. 1.7620 118.530 M/s. Nova Enterprse 118.530 08/08/2018 07/11/2019 100 09/07/2020 Final Bill paid.
9 MSRDP/S/17-18/BC/71 Improvement of BC Charbhoyrabig river- Salauddin MollahviaMojibor Peda .at ch 00.00 - 2264.00m under Damuddya Upazila Dist. Shariatpur. 2.2640 133.754 M/s. Nova Enterprse 133.754 07/08/2018 06/08/2019 100 09/07/2020 Final Bill paid.
10 MSRDP/S/18-19/ BC /75 Improvement the road By BC of Keorbhanga- Dakhinpara D.C road via Darishkati pry Road at Ch.500.00m – 1934.00m under Damudya Upazila, District: Shariatpur. 1.4340 118.530 m/s nova enterprise 118.530 15/01/2019 14/01/2020 80 09/07/2020
11 MSRDP/S/18-19/ BC /76 Part-1: Improvement the road By BC of Ramrayerkandi- char Narayanpur Road at Ch.850.00m – 1304.00m under Damudya Upazila, District: Shariatpur.Part-2: Improvement the road By BC of Dhanokati Main road to Dogerpar Road at Ch.486.00m – 1166.00m under Damudya Upazila, District: Shariatpur 1.1340 81.704 m/s shariatpur construction ; 81.704 21/01/2019 20/01/2020 80 09/07/2020
12 MSRDP/S/18-19/ BC /81 Improvement the road By BC of Charbhoyar-Charnarayanpur Road Ch. 800.00m – 1900.00m under Damudya Upazila, District: Shariatpur. 1.1000 81.836 m/s suborna construction 81.836 10/01/2019 09/01/2020 65 09/07/2020
13 MSRDP/S/18-19/BC/Maint-02 1.Maintenance of Atimkhana-Malgaon Road Via Talukder Kandi Road at ch.00-988m under Damuddya Upazila Dist. Shariatpur 2.Improvement of BC Bindaikati Madradha-D.C road at ch. 510.00 - 1190.00m under Damuddya Upazila Dist. Shariatpur .3.Improvement of BC H/O Dr Yusuf Alim-Darulaman H/O Rashid road at ch. 0.00- 658.00m under Damuddya Upazila Dist. Shariatpur. 4.Improvement of BC Moderhat-Blakandi road .at ch 00.00 - 655.00m under Damuddya Upazila Dist. Shariatpur . 2.9810 64.115 M/s. Nusrat Zahan Enterprise 64.115 02/08/2018 01/04/2019 100 09/07/2020 Final Bill paid.
14 MSRDP/S/18-19/BC/Maint-04 1.Improvement of BC Charpatalia Bazar-School road .at ch 00.00 - 745.00m under Damuddya Upazila Dist. Shariatpur .2.Improvement of BC Shdulkura Bazar-Baroghar road .at ch 00.00 - 706.00m under Damuddya Upazila Dist. Shariatpur 3.Improvement of BC R & H near Chairman Bari-Thengerbari UZR via Taltola Lnchghat road .at ch 00.00 - 780.00m under Damuddya Upazila Dist. Shariatpur 2.2310 83.379 M/s.Sumi Traders 83.379 21/06/2018 18/03/2019 100 09/07/2020 Final Bill paid.
15 MSRDP/S/18-19/BC/Maint-10 1.Improvement of BC Charpatalia Bazar-Mamudpaty School road .at ch 00.00 - 745.00m under Damuddya Upazila Dist. Shariatpur.2.Improvement of BC Shdulkura Bazar-Baroghar road .at ch 00.00 - 706.00m under Damuddya Upazila Dist. Shariatpur.3.Improvement of BC R & H near Chairman Bari-Thengerbari UZR via Taltola Lnchghat road .at ch 00.00 - 780.00m under Damuddya Upazila Dist. Shariatpur. 1.6970 21.214 M/s. Rishad Traders 21.214 27/12/2018 25/04/2019 100 09/07/2020 Final Bill Paid.
16 MSRDP/S/18-19/BC/Maint-11 Maintenance Work of Dhoni Samur Dokan- H/o Gofur Pagla Road at Ch. 0.00km 700m by BC under Damudda Upazila Dist. Shariatpur 0.7000 16.177 M/s.Sayeed Steel 16.177 27/12/2018 25/04/2019 100 09/07/2020 Final Bill Paid.
17 MSRDP/S/18-19/BC/Maint-12 Maintenance Work of Howladerkandi-Subachani via Chairman bari Road at Ch. 0.00km 1000km by BC under Damudda Upazila Dist. Shariatpur 1.0000 23.631 M/s. Mridha Traders 23.631 20/12/2018 19/04/2019 100 09/07/2020 Final Bill Paid.
18 MSRDP/S/18-19/BC/Maint-13 Part-01 Maintenance Work of Dhanokati Main road to Dogerpar Road at Ch. 0.00km 486km by BC under Damudda Upazila Dist. Shariatpur Part-02 Maintenance Work of 14 no pry. School-Bele bridge Road at Ch. 0.00km 720km by BC under Damudda Upazila Dist. Shariatpur 1.2060 20.726 M/s. Amena Traders 20.726 27/12/2018 25/04/2019 100 09/07/2020 Final Bill Paid.
3 Goshairhat
1 MSRDP/S/18-19/ BC /103 Part-1: Estimate for Construction of Improvement of Kodalpur Tahsil Office- purba Damudya road via uttar Malpara road by BC at Ch.0.00m – 2250.00m (Effective Length=2087.00m). under Goshairhat, Upazila, District: Shariatpur.Part-2: Estimate for (A) Construction of 3x4.50mx4.50m RCC Box Culvert on Pakhamsar – Bashgari via Dhalir hat road at Ch.240.00m. (B) Construction of 3x4.50mx4.50m RCC Box Culvert on Pakhamsar – Bashgari via Dhalir hat road at Ch.742.00m. under Goshairhat, Upazila, District: Shariatpur .Part-3: Estimate for Construction of 2x4.5x4.50m RCC Box Culvert On Harichar Khayaghat to Purbo Kodalpur Simania Via Abull Dargi Kandi Road at Ch.827.00.00m Under Goshairhat Upazila, District. 2.2500 259.050 M/S Mollah Enterprise 259.050 16/06/2019 15/06/2020 75 12/07/2020
2 MSRDP/S/17-18/ BC/01 Improvement of BC Road on Pakhamasr- Bashgari Via Dhalirhat road at ch. 3117.00-4054.00m. 0.9180 63.033 M/s. R.K.Construction 63.033 01/05/2018 28/02/2019 100 09/07/2020 Final Bill Paid.
3 MSRDP/S/17-18/BC/02 Improvement of BC Road on UZR Mazi Bari to Chamonpura Imrania Madrasha road at ch. 600.00 -825.00m. 0.2250 15.866 M/s. Shamim Traders 15.866 17/05/2018 16/02/2019 100 09/07/2020 Final Bill Paid.
4 MSRDP/S/17-18/BC/03 Improvement of BC Road on Nagarpara Mokaram Mosque- Molonchra road at ch. 00.00 -1000.00m. 1.0000 64.884 M/s. Almas Aman Traders 64.884 14/05/2018 13/02/2019 100 09/07/2020 Final Bill Paid.
5 MSRDP/S/17-18/BC/04 Improvement of BC Road on Nagarpara GC at Holy potty- Char Patalia Bazar via Talucder bari road at ch. 1000.00 -2000.00m. 1.0000 62.720 M/s. Foysal 62.720 01/05/2018 28/02/2019 100 09/07/2020 Final Bill Paid.
6 MSRDP/S/17-18/BC/05 Improvement of BC Road on Shamontasar UP (RHD)- Charpatalia Bazar road at ch. 00.00 -540.00m. 0.5400 30.590 M/s USA Traders 30.590 17/05/2018 16/01/2019 100 09/07/2020 Final Bill Paid.
7 MSRDP/S/17-18/SR/06 Construction of 2x4.50x4.50m. RCC Box Culvert on Pakhamsar- Bashgari via Dhalirhat road at ch.3202.00m. 9.0000 29.814 M/S Pilot enterprise 29.814 01/05/2018 31/01/2019 100 09/07/2020 Final Bill Paid.
8 MSRDP/S/17-18/SR/07 Construction of 1x4.00x4.00m. RCC Box Culvert on Nagarpara GC to Holy Potty - Char Patalia Bazar via Talucder bari raod at ch. 1738.00m. 4.0000 12.972 M/s AR Enterprise 12.972 29/04/2018 28/01/2018 100 09/07/2020 Final Bill Paid.
9 MSRDP/S/17-18/SR/08 Construction of 2x4.50x4.50m. RCC Box Culvert on Nagarpara GC to Holy Potty - Char Patalia Bazar via Talucder bari raod at ch. 00.00m. 9.0000 29.367 M/S Alomgir Traders 29.367 17/05/2018 16/02/2018 100 09/07/2020 Final Bill Paid.
10 MSRDP/S/17-18/SR/09 Construction of 2x4.50x4.50m. RCC Box Culvert on Nagarpara GC to Holy Potty - Char Patalia Bazar via Talucder bari raod at ch. 1203.00m. 9.0000 29.255 M/s. A.R.M. Construction 29.255 17/05/2018 16/02/2018 100 09/07/2020 Final Bill Paid.
11 MSRDP/S/17-18/SR/10 Construction of 2x4.50x4.50m. RCC Box Culvert on Nagarpara GC to Holy Potty - Char Patalia Bazar via Talucder bari raod at ch. 1984.00m. (Road ID 386364012) 9.0000 29.405 M/s. Khan Enterprie 29.405 30/05/2018 29/12/2018 100 09/07/2020 Final Bill Paid.
12 MSRDP/S/17-18/BC/11 Improvement of BC Road on Charmonpur GPS- Chitalia road at ch. 700.00 - 1145.00m. 0.4800 29.410 M/s. Toma Enterprise 29.410 17/05/2018 16/02/2019 100 09/07/2020 Final Bill Paid.
13 MSRDP/S/17-18/BC/12 Improvement of BC Road on Goriberchar GC Purbo Damuddya Shimana via Rashid Kazir kandi road at ch. 00.00 - 1800.00m. 1.4360 109.414 M/s. Irin Enterpriwe 109.414 17/05/2018 16/05/2019 100 09/07/2020 Final Bill Paid.
14 MSRDP/S/17-18/BC/36 Improvement of BC Road on Shaykhya H/O Hasem Munshi - Madrasha Bazar via Bangla Bazar Bridge road at Ch. 0.00 - 3050.00m under Goshairhat Upazila Dist. Shariatpur, 3.0500 187.618 M/s. Sristi Enterprise 187.618 24/05/2018 26/09/2019 100 09/07/2020 Final Bill Paid.
15 MSRDP/S/17-18/BC/37 a) Improvement of BC Road on Nagarpara Govt. Ahmadia Dakhil Madrasha to Sree Krisna Pal House via Nagarpara 2 Nos GPS road at Ch. 0.00 - 1100.00m under Goshairhat Upazila Dist. Shariatpur.Improvement of BC Road on Nandigram Box Culvert - Tarulia Ukilbari via fakir bari Jame Mosque road at Ch. 0.00 - 600.00m under Goshairhat Upazila Dist. Shariatpur. 1.1000 118.969 M/s. Reza Constrution 118.969 27/06/2018 26/06/2019 100 09/07/2020 Final Bill Paid.
16 MSRDP/S/18-19/BC/Maint-07 Maintenance of Nagerpara GC at Holy Potty-Char patalia Bazar via Talkderbar at Ch. 0.00m 1055m by BC under Goshairhat Upazila Dist. Shariatpur 1.0550 30.413 M/s. Sufia Enterprise 30.413 20/12/2018 18/04/2019 100 09/07/2020 Final Bill Paid.
17 MSRDP/S/18-19/BC/Maint-08 Maintenance of Pakamshar-Basgari via dhalirhat Road at Ch. 0.00m 2117m by BC under Goshairhat Upazila Dist. Shariatpur 2.1100 55.962 M/s. Nusab Enterprise 55.962 18/12/2018 17/04/2019 100 09/07/2020 Final Bill Paid.
18 MSRDP/S/18-19/BC/Maint-09 Maintenance of Kodalpur GCCR at Dewan bari-Shakya Bazar road at Ch. 0.00m 2015m by BC under Goshairhat Upazila Dist. Shariatpur 2.0150 62.744 M/s. Misu Enterprise 62.744 20/12/2018 19/04/2019 100 09/07/2020 Final Bill Paid.
19 MSRDP/R/18-19/BC/maint-07 Maintenance of Nagerpara GC at Holy Potty-Char patalia Bazar via Talkderbar at Ch. 0.00m – 1055m by BC under Goshairhat Upazila, Dist. Shariatpur. 1.0550 30.410 m/s shufia enterprise 30.410 20/12/2018 19/04/2019 100 08/07/2020 Final Bill Paid.
20 MSRDP/S/18-19/BC/88 Part-1: Estimate for Rehabilitation Work of Dasherjungle GC – Dhanusikder hat via Kutchipatti up Road By BC Ch.00-7520.00m ( Effective length= 7149.00m) & 4 Nos RCC Box Culvert (1.00x1.00m) at ch.812.00m, 1190.00m, 1880.00m & 2350.00m Under Goshairhat Upazila District : Shariatpur.Part-2: Estimate For Improvement of BC Road On Jushairgoan Bazar- Boxsompotty GPS via Nandi Gram road at Ch. 1000- 1500.00m Under Goshairha Upazila District: Shariatpur.Part-3: Estimate For Improvement of Dasherjungle- Machuakhali tulatali Madrasha Road by BC at Ch. 2480- 3700.00m Under Goshairhat Upazila, District: Shariatpur. 9.2720 603.720 haji sheikh progoti 603.720 30/05/2019 29/11/2020 100 08/07/2020 Final Bill Paid.
4 Janjira
1 MSRDP//18-19/BC/123 Part-1: Improvement of Bilaspur GC road at Akand Kandi to Bilaspur GC road by BC at ch.610-1870m(Effective Length =1260.00m) under Janjira Upazila, District: Shariatpur. Part-2: Improvement of Janjira-Kewrakandi GCCR- Ramkishnopur via Sobus Chata road by BC at ch.00 -700.00m under Janjira Upazila, District: Shariatpur. 1.9600 166.850 166.850 18/05/2020 17/05/2021 100 14/07/2020 Final Bill Paid
2 MSRDP/S/18-19/BC/ Maint /14 Shibchar border road at ch.1233-3040m (Effective Length =1737.00m) under Janjira Upazila, District: Shariatpur. Part-2: Maintenance of A.M.M kandi- Dhalirhat road Ch.0.00m-1235.00m.under Janjira Upazila, District Shariatpur. Part-3: Maintenance of Nawduba hat north side bridge-Char Chanda (Shibchar border) via west side Graveyard & Golam Sarwar house road at ch.00 -1610m(Effective Length =1602.00m) under Janjira Upazila, District: Shariatpur. Part-4: Maintenance of Janjira PS Shariatpur Janjira RHD via Dhalirhat road at ch.1730-2330m under Janjira Upazila, District: Shariatpur. 5.1520 289.930 M/S Sheikh Enterprise 289.930 18/05/2020 09/11/2021 30 12/07/2020
3 MSRDP/S/18-19/BC/110 Madaripur Shibchar road by at Ch.0. 00m-1570.00 m under Janjira, Upazila, District: Shariatpur. Part-B: Imp. of Kazirhat –Durgarhat Road by HBB at ch.0.00m-1360.00m & Construction of 1x1.5x1.00m RCC Box culvert at Kazirhat –Durgarhat Road 700.00m under Janjira Upazilla, District: Shariatpur. 2.9300 148.070 M/S Mizan Enterprise 148.070 16/06/2019 25/06/2020 100 12/07/2020 Final Bill Paid.
4 MSRDP//18-19/HBB/82 Part-1: Improvement of Khoratola Primary School- H/O Nuru Madbor Road by H.B.B at Ch. 0.00m – 805.00m under Janjira Upazila, District: Shariatpur.Part-2: Improvement of Dakhin Dubisibor Mollah Kandi Razumadbor bari- Delowarmadbor bari Road by H.B.B at Ch. 0.00m – 300.00m under Janjira Upazila, District: Shariatpur.Part-3: Improvement of Paschi Nawduba- Kutubpur Road by H.B.B at Ch. 0.00m – 885.00m under Janjira Upazila, District: Shariatpur. 1.9900 94.850 M/S Himu Enterprise 94.850 23/01/2019 22/01/2019 100 09/07/2020 Final Bill Paid.
5 MSRDP/S/17-18/SR/18 Construction of 3x4.50x4.00m RCC Box Culvert on Dubsaiber hat - Rupbabur hat road at Ch.2105.00m under Janjira Upazila Dist. Shariatpur. 38.910 M/S Samim Traders 38.910 31/05/2018 29/01/2019 100 09/07/2020 Final Bill Paid.
6 MSRDP/S/17-18/SR/16 Construction of 3x4.50x4.00m RCC Box Culvert on Dubisaiber hat - Rupbabur hat via MC Kandi road at Ch.834.00m under Janjira Upazila Dist. Shariatpur. 38.750 M/S Sadiya Enterprise 38.750 30/05/2018 29/03/2019 100 09/07/2020 Final Bill Paid.
7 MSRDP/S/17-18/SR/15 Construction of 3x4.50x4.00m RCC Box Culvert on Sarder Kandi - Shimultala UZR road at Ch.170.00m under Janjira Upazila Dist. Shariatpur. 39.925 M/s. Tonmoy Enterprise 39.925 22/05/2018 21/03/2019 100 08/07/2020 Final bill paid.
8 MSRDP/S/17-18/HBB/17 (Part-A) Improvement of HBB Road on Palerchar to Dangi Kandi Pry. School road at Ch. 1000.00 - 3580.00m (Part-B) Construction of 1x7.50x0.925x0.90m Box Culvert. (U-Drain) on Palerchar to Dangi Kandi Pry. School road at Ch. 1728.00m under Janjira Upazila Dist. Shariatpur. 2.5700 132.057 M/s. Khan Enterprise 132.057 30/05/2018 29/05/2019 100 08/07/2020
9 MSRDP/S/17-18/HBB/19 Improvement of HBB Road on Uttar Cable Nagor - Khoratola School road via Razzaq Madbor road at Ch. 0.00 - 1450.00m under Janjira Upazila Dist. Shariatpur. 1.4500 62.430 M/s. Aysa Enterprise 62.430 17/05/2018 16/02/2019 100 08/07/2020 Final bill paid.
10 MSRDP/S/17-18/HBB/20 (Part-A) Improvement of HBB Road on Laukhola bazar - Rayerkandi Pry. School road at Ch. 0.00 - 1700.00m, (rpat-B) Construction of 1x7.50x0.925x0.90m Box Cul. (U-Drain) on Laukhola bazar - Rayerkandi Pry. School road at Ch. 900.00m under Janjira Upazila Dist. Shariatpur. 1.7000 79.145 M/s. Solaimand Traders 79.145 27/05/2018 26/02/2019 100 08/07/2020 Final Bill Paid.
11 MSRDP/S/17-18/SR/21 Construction of 3x4.50x4.00m RCC Box Culvert on Palerchar - Dhangi Kandi PS road at Ch.900.00m under Janjira Upazila Dist. Shariatpur. 38.751 M/s. Awal Traders 38.751 27/05/2018 26/01/2019 100 08/07/2020 Final bill paid.
12 MSRDP/S/17-18/HBB/22 Improvement of HBB Road on Khalek Serthi Shanga R&H-Joynagar GC to Ismail Khan house road at Ch. 0.00 - 750.00m under Janjira Upazila Dist. Shariatpur. 0.7500 32.117 M/s. Mridha Traders 32.117 14/05/2018 13/03/2019 100 08/07/2020
13 MSRDP/S/17-18/HBB/23 Improvement of HBB Road on Janjira Durbadanga bazar - Howladar kandi Pry. School road at Ch. 0.00 - 1000.00m under Janjira Upazila Dist. Shariatpur. 1.0000 57.309 M/s.Mohammad Ali Associates 57.309 31/05/2018 30/03/2019 100 08/07/2020
14 MSRDP/S/17-18/BC/56 Part-A: Improvement of BC Shariatpur - Janjira - Kawarakandi R&H to Shariatpur Gonganagar - Mongol Mazir Ghat R&H road at ch. 2550.00 - 3625.00m under Janjira Upazila Dist. Shariatpur.Part-B: Improvement of BC Bangobazar - Boro Gopalpur road to Uttar Shikder Kandi road at ch. 0.00 - 1150.00m under Janjira Upazila Dist. Shariatpur.Part-C: Improvement of BC Palerchar UP Office - to Mongol Mazir Ghat road at ch. 3104.00 - 3964.00m under Janjira Upazila Dist. Shariatpur. 3.0850 211.800 M/s.Neloy Enterprise 211.800 21/06/2018 17/08/2019 100 08/07/2020 Final Bill Paid.
15 MSRDP/S/17-18/BC/58 Improvement of BC Dabuldia - Taher Madbor hat road at ch. 0.00 - 2500.00m under Janjira Upazila Dist. Shariatpur. 2.5000 152.079 M/s. Irin Enterprise 152.079 18/06/2018 15/06/2019 100 08/07/2020 Final Bill Paid.
16 MSRDP/S/17-18/BC/57 Improvement of BC Dubisaibor Hat - Rupbaburhat via M.Kandi road at ch. 0.00 - 4090.00m & Construction of 1x7.50x0.925m Box Culvert (U-Drain) of Same road under Janjira Upazila Dist. Shariatpur. 4.0900 268.849 M/s. sheikh Enterprise 268.849 23/07/2018 22/09/2019 100 08/07/2020 Final Bill Paid.
17 MSRDP/S/18-19/HBB/82 Part-1: Improvement of Khoratola Primary School- H/O Nuru Madbor Road by H.B.B at Ch. 0.00m – 805.00m under Janjira Upazila, District: Shariatpur.Part-2: Improvement of Dakhin Dubisibor Mollah Kandi Razumadbor bari- Delowarmadbor bari Road by H.B.B at Ch. 0.00m – 300.00m under Janjira Upazila, District: Shariatpur.Part-3: Improvement of Paschi Nawduba- Kutubpur Road by H.B.B at Ch. 0.00m – 885.00m under Janjira Upazila, District: Shariatpur. 1.9900 94.850 M/S H M TRADERS 94.850 23/01/2019 22/01/2019 100 08/07/2020 Finnal Bill Paid.
18 MSRDP/S/18-19/HBB/83 Improvement of Char Laxmikantopur- Shibchar Border Road by H.B.B at Ch. 0.00m – 1365.00m under Janjira Upazila, District: Shariatpur Road ID No: 386945018). 1.3650 60.850 M/S yelies traders 60.850 23/01/2019 22/10/2019 100 08/07/2020 Finnal Bill Paid.
19 MSRDP/S/18-19/HBB/84 Improvement of Rupbabur hat- Rustom madbor hat Road by H.B.B at Ch. 0.00m – 2330.00m under Janjira Upazila, District: Shariatpur . 2.3300 98.430 M/S Mishu enterprise 98.430 21/01/2019 20/11/2019 100 08/07/2020 Final Bill Paid.
20 MSRDP/S/18-19/HBB/85 Improvement of Vodrashan pacca road- Joynagar G.C road via Boro Gopalpur U.P office Road by H.B.B at Ch. 0.00m – 1750.00m under Janjira Upazila, District: Shariatpur. 1.7500 77.810 M/S NUSRAT JAHAN TRADERS 77.810 23/01/2019 22/01/2020 100 08/07/2020 Final bill paid.
21 MSRDP/S/18-19/HBB/86 Improvement of Kathuria Primary School Connecting Road by H.B.B at Ch. 0.00m – 1175.00m under Janjira Upazila, District: Shariatpur Road ID No: 386945026). 1.1750 57.030 MIM FRABIC 57.030 23/01/2019 22/11/2019 100 08/07/2020 Final bill paid.
22 MSRDP/R/17-18/HBB/87 Part-1: Improvement of Laukhola bazar- Chardhupuria Border Road by H.B.B at Ch. 0.00m – 650.00m under Janjira Upazila, District: Shariatpur.Part-2: Improvement of House of Mostofa Kazi – House of Jamal mollah Road by H.B.B at Ch. 0.00m – 335.00m under Janjira Upazila, District: Shariatpur. 0.9850 49.700 M/S ASMA ENTERPRISE 49.700 23/01/2019 22/11/2019 100 08/07/2020 Final bill paid.
23 MSRDP/S/17-18/BC/maint-05 Improvement of BC Sakim Ali Shop to Jhankhar kandi Notun Gram Road By BC at ch 00.00 - 1670.00m under Damuddya Upazila Dist. Shariatpur. 1.6700 89.220 M/S SHEFAT ENTERPRISE 89.220 17/08/2018 07/05/2019 100 08/07/2020 Final bill paid.
5 Naria
1 MSRDP/S/18-19/SR/120 Improvement of RCC Pavement road at Char Atra River side to Nowpara Connecting road at ch. 0.00m – 3300.00m under Naria Upazila, Dist: Shariatpur. 3.3000 590.310 M/S Samim Traders 590.310 24/02/2020 23/02/2020 20 12/07/2020
2 MSRDP//18-19/HBB/118 Improvement of Bhumkhara- Gulmaize Road by HBB from at Ch.3580.00m – 5705.00m. under Naria, Upazila, District: Shariatpur. 2.1250 101.810 M/S Solaiman Traders 101.810 14/08/2019 13/08/2020 100 12/07/2020
3 MSRDP//18-19/HBB/117 Improvement of Bhojeswar GC – Dogree R & H road by HBB at Ch.3615.00m – 4425.00m. (2) Construction of RCC Box Culvert (1x3.50mx3.50m) Ch.3765.00m, under Naria, Upazila, District: Shariatpur. 0.8100 58.590 M/S Rajony Enterprise 58.590 21/08/2019 20/05/2020 100 12/07/2020 Final Bill Paid.
4 MSRDP//18-19/HBB/116 Improvement of HBB on Nowga Dhali Bari Ghata- Khalil Dhali Bari Ghata Road. Ch.0.00m-530.00m. b.Construction of 2x4.00x4.00m RCC Box culvert on Nowga Dhali Bari Ghata- Khalil Dhali bari Ghata Road. Ch.500.00m Under : Naria, District: Shariatpur. 0.5300 52.860 M/S Arif & Brothers 52.860 21/08/2019 20/05/2020 100 12/07/2020 Final Bill Paid.
5 MSRDP/S/18-19/ BC /112 Improvement of Chekdho Kaderpur Pucca road to bir Muktijoddha Ali Shamed house at Ch.0.00m – 290.00m. Naria Upazila, District: Shariatpur Road ID No: 386655504 0.2900 30.400 M/S Towa Enterprise 30.400 25/07/2019 24/06/2020 20 12/07/2020
6 MSRDP/S/17-18/BC/24 a) Improvement of BC Road on Kolabagan Main rpad-H/O Sohen Madbar road at Ch: 0.00 - 1121.00m Naria Upazila, Dist. Shariatpur. b) Improvement of BC Road on Nalta-Nitira road at Ch: 1000.00 - 1370.00m Naria Upazila, Dist. Shariatpur.c) Improvement of BC Road on Khathugli-Chistinagar road at Ch: 1880.00 - 3290.00m Naria Upazila, Dist. Shariatpur. 3.9010 147.753 M/s. Madbar Traders 147.753 27/05/2018 26/04/2019 100 09/07/2020 Final Bill Paid.
7 MSRDP/S/17-18/BC/25 a) Improvement of BC Road on Rahapara-Paglarmor road at Ch: 960.00 - 1730.00m Naria Upazila, Dist. Shariatpur.b) Improvement of BC Road on Gulmaize Dangar House (Chairman Bazar)-Moddho Gulmaize Govt. Pry School (Vatia Border road at Ch: 00.00 - 1200.00m Naria Upazila, Dist. Shariatpur.c) Improvement of BC Road on Garishar Paglarmore-Kolargoan GPS road at Ch: 0.00 - 325.00m Naria Upazila, Dist. Shariatpur. 2.2950 139.285 M/s. Almas Aaman 139.285 31/05/2018 30/05/2019 100 09/07/2020 Final Bill Paid.
8 MSRDP/S/17-18/HBB/26 Improvement of HBB Road on Bijhari UP-Nazirpur Ananda Bazar road at Ch: 1000.00 - 2315.00m Naria Upazila, Dist. Shariatpur. 1.3150 66.074 M/s. Molla Enterprise 66.074 31/05/2018 30/03/2019 100 09/07/2020 Final Bill Paid.
9 MSRDP/S/17-18/HBB/27 Improvement of HBB Road on Pathanbari R&H road-Char Bhojeswar road at Ch: 0.00 - 1170.00m Naria Upazila, Dist. Shariatpur. 1.1700 53.513 M/s. Zihad Traders 53.513 22/05/2018 21/02/2019 100 09/07/2020 Final Bill Paid.
10 MSRDP/S/17-18/BC/28 a) Improvement of BC Road on Sinholmuri Zora Bridge-Sinholmuri Pucca road at Ch: 0.00 - 280.00m Naria Upazila, Dist. Shariatpur.b) Improvement of BC Road on Dingamanik UP-Golar Bazar road at Ch: 2620.00 - 3805.00m Naria Upazila, Dist. Shariatpur. c) Improvement of BC Road on Anakhanda Mirachan Sadar Shop-H/O Mojammal Haque Choder road Ch: 00.00 -795.00m Naria Upazila, Dist. Shariatpur. 2.2600 165.242 M/s. Neloy Enterprise 165.242 24/05/2018 23/05/2019 100 09/07/2020 Final Bill Paid.
11 MSRDP/S/17-18/BC/29 a) Improvement of BC Road on Pachak Post Office-Muktijodha Sajahan Khan House road at Ch: 0.00 -600.00m Naria Upazila, Dist. Shariatpur.b) Improvement of BC Road on Ponchapolly-Gulmaize road at Ch: 810.00 - 2200.00m Naria Upazila, Dist. Shariatpur (Road ID: 386654028). 1.9900 136.127 M/s. Hapy Enetrprise 136.127 24/05/2018 23/05/2019 100 09/07/2020 Final Bill Paid.
12 MSRDP/S/17-18/BC/30 ) Improvement of BC Road on Bhumkhara GPS-Choukeder Kandi road at Ch: 0.00 - 670.00m Naria Upazila, Dist. Shariatpur (Road ID: ) Improvement of BC Road on Bhumkhara GPS-Choukeder Kandi road at Ch: 0.00 - 670.00m Naria Upazila, Dist. Shariatpur . b) Improvement of BC Road on Masura H/O Dr. Abdul Jalil-H/O Ali Pada road at Ch: 0.00 - 875.00m Naria Upazila, Dist. Shariatpur.c) Improvement of BC Road on Achura H/O Rahim Khandakar-H/O Jahangir Khar road at Ch: 0.00 -300.00m Naria Upazila, Dist. Shariatpur. 1.8450 127.982 M/s. Arif Enterprise 127.982 17/05/2018 16/05/2019 100 09/07/2020 Final Bill Paid.
13 MSRDP/S/17-18/BC/31 Improvement of BC Road on Bhojeswar-Dogree R&H road at Ch: 1200.00 - 3615.00m Naria Upazila, Dist. Shariatpur. 2.4150 157.104 M/s. Salam Traders 157.104 22/05/2018 20/02/2019 100 09/07/2020 Final Bill Paid.
14 MSRDP/S/17-18/HBB/32 Improvement of HBB Road on Bhojeswar GC-Mohiskhola road at Ch: 00.00 - 490.00m Naria Upazila, Dist. Shariatpur. 0.4900 60.675 M/s. Jorasako International 60.675 31/05/2018 30/03/2019 0 09/07/2020 Cancel Tender.
15 MSRDP/S/17-18/BC/52 Part-A: Improvement of BC Shariatpur - Naria RHD road (H/O Chandani Alauddin Saiyal) - Delwar Member Hosue road at ch. 0.00 - 696.00m under Naria Upazila Dist. Shariatpur.Part-B: Improvement of HBB Dulukhanda H/O Sekender Howlader - H/O Babul Sarder road at ch. 0.00 - 705.00m under Naria Upazila Dist. Shariatpur.Part-C: Improvement of BC Maizpara road at ch. 1020.00 - 2150.00m under Naria Upazila Dist. Shariatpur. 1.9010 169.769 M/s. Apu Traders 169.769 14/06/2018 15/06/2019 75 09/07/2020
16 MSRDP/S/17-18/BC/53 Improvement of BC D.Mojibur Rahaman (Hiru Kazi) Bari Semana via D.Soharab Hossain Sorder Bari via Ahmadangar Bazar road at ch. 0.00 - 1000.00m under Naria Upazila Dist. Shariatpur. 1.0000 86.233 M/s. Misu Enterprise 86.233 19/06/2018 17/05/2019 75 09/07/2020
17 MSRDP/S/17-18/BC/65 Improvement of BC Sirangal UP Pacca (Police Shop) – Sirangal Small Bridge Road at ch 0.00 – 326.00m, School Link-120m, under Naria Upazila Dist. Shariatpur. 0.3260 19.557 M/s. Arohi Enterprise 19.557 22/03/2019 22/12/2018 100 09/07/2020 Final Bill Paid.
18 MSRDP/S/18-19/BC/73 Improvement of Masura-Koarag Road Ch. 1240m-2830m under Naria Upazila District Shariatpur .Salvage1418879 BDT, 1.5900 108.556 M/s. Mizan Enterprise 108.556 24/12/2018 23/12/2019 100 09/07/2020 Final Bill Paid.
19 MSRDP/S/18-19/BC/74 PartA Improvement of Chistenagar Pucca Road To Lalmia Madbor Idris Malot Bari Road Ch. 00m-510m PartB Construction of 1.00m1.00m RCC U-Type Drain 255m on Sureswar Dorbersorif under Naria Upazila District Shariatpur .. 0.5100 115.622 M/s. Lajuki Fashin Mela 115.622 24/12/2018 23/12/2019 100 09/07/2020 Final Bill Paid.
20 MSRDP/S/18-19/BC/Maint-06 Part-01 Maintenance of Munsir More Dhalir More Road Ch. 0.00km 1020km by BC under Naria Upazila Dist. Shariatpur Part-02 Maintenance of Ponchopolly-Telipara Road Ch. 1240km 2930km by BC under Naria Upazila Dist. Shariatpur , Part-03 Maintenance of Bhumkhara Chakda- Kadamtala Bazar via Nayakandi Road from Ch. 0.00km 2460km by BC under Naria Upazila Dist. Shariatpur , Part-04 Maintenance of Rajnagar UP-Budair hat Road from Ch. 0.00km 2320km by BC under Naria Upazila Dist. Shariatpur Part-05 Maintenance of Puragacha Road from Ch. 0.00km 1115km by BC under Naria Upazila Dist. Shariatpur Part-06 Maintenance of Golmaiz abbasia- Darul Karar Society Road from Ch. 0.00km 410km by BC under Naria Upazila Dist. Shariatpur , Part-07 Maintenance of Kathogly-Chisty Nagar road from Ch. 0.00km 1787km & 3290.00km-3836.00km by BC under Naria Upazila Dist. Shariatpur Part-08 Maintenance of Nalta-Sanda Road from Ch. 0.00km 1500km by BC under Naria Upazila Dist. Shariatpur Package No. MSRDP/S/18-19/BC/Maint-06 12.8480 292.790 m/s jamuna enterprise 292.790 19/02/2019 17/09/2019 98 09/07/2020
21 MSRDP/S/18-19/BC/109 1)Improvement of Nasason- Akankandi road at Ch.0.00m – 1200.00m by BC road (2) Construction of RCC Box Culvert (2x4.00mx4.50m) Ch.350.00m. under Naria, Upazila, District: Shariatpur. 1.2000 122.570 122.570 23/06/2019 31/07/2020 70 08/07/2020
22 MSRDP/S/18-19/BC/92 Improvement of Pachak Post Office – Muktijodha Sajahan Khan house Road By BC at Ch. 600.00m – 1170.00m under Naria Upazila, District: Shariatpur. 0.5700 40.400 M/S JARIN TRADERS 40.400 03/11/2019 12/10/2019 100 08/07/2020 Final Bill Paid.
23 MSRDP/S/18-19/HBB/93 Improvement of Razzak Hawlader bari to Bijhari Pancholly Pucca Road By BC at Ch. 00.00m – 565.00m under Naria Upazila, District: Shariatpur. 0.8000 59.920 M/S Munia Enterprise 59.920 26/02/2019 25/11/2020 100 08/07/2020
24 MSRDP/S/18-19/ HBB/96 Improvement of Bezari Anondo Bazar road to Kanchanpara Via Degomber Puttri govt. Primary School Road By HBB at Ch. 00.00m – 800.00m under Naria Upazila, District: Shariatpur. 0.8000 21.530 M/S Nur Jahan Construction 21.530 03/10/2019 12/09/2012 45 08/07/2020
25 MSRDP/S/18-19/SR/97 Constructioin of 2 Nos. 1x3.50mx3.50m Box Culvert on sagor Road at Ch. 375.00m & 1128m under Naria Upazila, District: Shariatpur. 22.700 m/s nurjahan connstruction 22.700 03/10/2019 08/09/2019 100 08/07/2020 Final Bill Paid.
26 MSRDP/S/18-19/BC/98 Part-1: Improvement of Naria Banglabazar- Nasasan Up Office Road By BC at Ch. 00.00m – 1332.00m (NER=15m) Effective Length=1317.00m under Naria Upazila,District:Shariatpur.Part-2: Improvement of Maizpara Road By BC at Ch. 2150.00m – 3290.00m by BC under Naria Upazila, District: Shariatpur.Part-3: Constructioin of RCC Box Culvert (2x4.00mx4.50) at Ch. 2557.00m under Naria Upazila, District: Shariatpur. Part-4: Constructioin of RCC Box Culvert (2x4.00mx4.50) at Ch. 3280.00m under Naria Upazila, District: Shariatpur. 2.4720 215.300 Mohammad Younus and brathers 215.300 03/06/2019 02/06/2020 75 08/07/2020
27 MSRDP/S/18-19/HBB/99 Part-1: Improvement of Bhojeswar- Mohiskhola road to dosai howlader Kandi by HBB road at Ch. 00.00m – 1645.00m under Naria Upazila, District: Shariatpur.Part-2: Constructioin of RCC Box Culvert (1x3.50mx3.50) at Ch. 1440.00m under Naria Upazila, District: Shariatpur.Part-3: Improvement of GC (Mulpara) – Japsa road at Ch.6500.00m – 8500.00m by HBB under Naria Upazila, District: Shariatpur.4Part-4: Construction of RCC Box Culvert (1x3.50mx3.50) at Ch. 7600.00m under Naria Upazila, District: Shariatpur 3.6450 200.370 M/S Jamuna Enterprise 200.370 27/06/2019 26/06/2020 40 08/07/2020
28 MSRDP/S/17-18/BC/105 Part-1: Improvement of Laxmipur- Vanopa Bazar Road at Ch.0.00m – 1000.00m. under Naria, Upazila, District: Shariatpur. Part-2: Improvement of Gourango – Sreeangar Road at Ch. 0.00m – 693.00m & Ch. 1930.00m – 2700.00m. under Naria, Upazila, District: Shariatpur.Part-3: (A) Improvement of Andermanik Bazaar to Punikhar Kandi via Akber Chairman House road at Ch.0.00m – 1380.00m by BC Road. (B) Construction of RCC Box Culvert (1x3.50mx3.50m) Ch.516.00m. under Naria, Upazila, District: Shariatpur.Part-4: Construction of RCC Box Culvert (2x4.00mx4.00m) Khathugli- Chistinagar bc road at Ch.2367.00m Under Naria. Shariatpur. 2.4630 297.660 M/s Shamim Enterprise. 297.660 03/06/2019 02/06/2020 90 08/07/2020
29 MSRDP/S/17-18/SR/111 Part-A: Construction of Approach road including 9.00m high reinforced earth (RE) Wall of 99.00m long PC girder on Bhojeswar-Mohiskhola road over Kirtinasa river under Naria Upazila, District: Shariatpur.Part-B: Construction of Approach road 99.00m long PC girder on Bhojeswar-Mohiskhola road over Kirtinasa river under Naria Upazila, District: Shariatpur. 1321.040 Dard engineering ltd 1321.040 25/07/2019 24/06/2020 22 08/07/2020
6 Shariatpur-s
1 MSRDP//18-19/SR/122 Part-1: Construction of 20.0m long RCC Girder Bridge on Chikondi UP Office to Gonganagar GC via West Atpara Bazar Road at Ch.110.00m. under Sadar Upazila, District: Shariatpur (Road ID No: 386693023). Part-2: Construction of 20.0m long RCC Girder Bridge on Chikondi UP Office to Gonganagar GC via West Atpara Bazar Road at Ch.1900.00m. under Sadar Upazila, District: Shariatpur (Road ID No: 386693023). 411.880 M/S Sheikh Enterprise 411.880 01/04/2020 01/09/2021 100 14/07/2020 Final Bill Paid
2 MSRDP//18-19/SR/121 Part-1: Construction of 42.0m long RCC Girder Bridge on Subachani Hat (UZR) – Tolatala Bazar (UZR) Road at Ch.2780.00m. under Sadar Upazila, District: Shariatpur.Part-2: Construction of 30.0m long RCC Girder Bridge on Chitolia GPS Union Road to Taker Hat Tumchar Akon Bari Road At Ch.2150.00m. under Sadar Upazila, District: Shariatpur. 710.210 m/s Hamim International 710.210 01/04/2020 01/10/2021 0 12/07/2020
3 MSRDP/S/18-19/ BC /113 Part-1-Construction of 1x4.50mx.00m.RCC Box Culvert W 4.88m & WW 3.40m on Kasipur Nesaria Dakhil Madrasa to Shil Dangi Road at ch.825.00m under Sadar Upazila Dist. Shariatpur.Part-2- Improvement of 300.00m Flexible pavement of Binodpur UP- Nilkuthi Bazar via Mahmudpur & Kodomtali GPS road at Ch.6386.00m-6686.00m under Sadar, Upazila, District: Shariatpur. 0.3000 43.390 M/S Diba Enterprise 43.390 25/06/2019 24/12/2019 100 12/07/2020
4 MSRDP/S/17-18/BC/13 Improvement of BC road from Char Sonamukhi boroi Tala Bridge (UZR- 2005)- Monohar Bazar Cattle Hat road at ch. 00.00 - 1000.00m. 1.0000 73.850 M/s. Foysal Enterprise 73.850 30/05/2018 29/05/2019 70 09/07/2020 Final Bill Paid.
5 MSRDP/S/17-18/BC/14 Improvement of BC road from Ghoraghat (UZR) - Parchim Sonamukhi Mia Chan Bepari UNR Via parchikm sonamukhi GPS road at ch. 00.00 - 550.00m. 0.5500 41.076 M/s. Delwar Hossain & Co. 41.076 30/05/2018 28/02/2019 100 09/07/2020 Final Bill Paid.
6 MSRDP/S/17-18/BC/33 Improvement of BC Road on Charar Kandi - GCCR road at Ch. 0.00 - 1522.00m under Sadar Upazila Dist. Shariatpur. 1.5220 126.941 M/s.Nazma Enterprise 126.941 20/05/2018 19/05/2019 100 09/07/2020 Final Bill Paid.
7 MSRDP/S/17-18/BC/50 Improvement of BC Charushandi Embankment road at ch. 1000.00 - 5500.00m under Sadarpazila Dist. Shariatpur, 4.5000 309.548 M/s. Sheikh Enterprise 309.548 23/07/2018 22/11/2019 100 09/07/2020 Final Bill Paid.
8 MSRDP/S/17-18/BC/51 Improvement of BC Kashipur - Tumchar via Samitir Bazar road at ch. 0.00 - 2555.00m & Construction of 2x4.5x4.5m RCC Box Culvert at Ch. 1440.00m & Construction of 1x0.90x1.20m U-Drain on the Same road under Sadar Upazila Dist. Shariatpur. 2.5550 223.064 M/s. Mayer Doa 223.064 27/06/2018 24/09/2019 100 09/07/2020 Final Bill Paid.
9 MSRDP/S/17-18/BC/59 Part-1-Improvement by BC of Kasipur Nesaria Dakhil Madrasa to Shil Dangi Road at ch. 0-00-1000 under Sadar Upazila Dist. Shariatpur. Part-2-Improvement by BC of Tulatala to Surjamoni Bazar Road at ch.0.00-788 under Sadar Upazila Dist. Shariatpur. 1.7780 131.964 M/s. Zihad Traders 131.964 17/06/2018 15/05/2019 100 09/07/2020 Final Bill Paid.
10 MSRDP/S/17-18/BC/60 Improvement by BC of Vasanchar Launchghat to Mokbul Sadar House Road at ch. 0-00-2000 under Sadar Upazila Dist. Shariatpur . 2.0000 144.479 M/s. Nilima Construction 144.479 27/06/2018 26/04/2019 100 09/07/2020 Final Bill Paid.
11 MSRDP/S/17-18/BC/61 Improvement by BC of Subachani hat (UZR)-Tolatala Bazar (UNR) Road at ch.2038-3808 under Sadar Upazila Dist. Shariatpur. 1.7700 15.843 M/s. Noor Trading 15.843 27/06/2018 26/04/2019 100 09/07/2020 Final Bill Paid.
12 MSRDP/S/17-18/BC/62 Improvement of Flexible Pavement of Angaria UP- Tekerhat Bazar via Chiutulia UP road at ch 2860.00 – 5480.00m under Sadar Upazila Dist. Shariatpur. 2.6200 152.163 M/s. Mridha Traders 152.163 07/08/2018 07/08/2019 100 08/07/2020 Final Bill Paid.
13 MSRDP/S/17-18/BC/63 Part-1: Improvement Flexible Pavement Road from Tulatala bazaar (Saw mill)- Madaripur Dristrict Border (Kader sarder bari) road by BC ch .1400.00 – 1800.00m under Sadar Upazila Dist. Shariatpur.Part-2: Improvement Flexible Pavement on Dadpur Lunch Ghat-Luxmipur road at ch .1000.00 – 1415.00m under Sadar Upazila Dist. Shariatpur.Part-3: Construction of 2x4.50x4.00m RCC Box Culvert on Dewbogh bottola (UZR) – Pourshava Border via Soban sardar Bari Road at Ch: 1350.00m under Sadar Upazila Dist. Shariatpur, . 4.0000 107.509 M/s. Neloy Enterprise 107.509 30/07/2018 29/06/2019 100 08/07/2020 Final bill paid.
14 MSRDP/S/17-18/SR/64 Part-1: Construction of 1x4.50mx4.00m RCC Box Culvert on Dewbogh Bottola (UZR) – Pourshava Border via soban Sardar Bari at ch 700.00m. Part-2: Construction of 2x4.50x4.00m RCC Box Culvert on Dewbogh bottola (UZR) – Pourshava Border via Soban sardar Bari Road at Ch: 1350.00m under Sadar Upazila Dist. Shariatpur. 1.3000 109.524 Abdul Rob Molla 109.524 09/12/2018 08/12/2019 100 08/07/2020 Final Bill Paid.
15 MSRDP/S/17-18/ BC /72 Improvement of Munshi kandi Bridge (UNR road) – Rashid Kha Kandi road Ch.0.00m – 536m. & Const. of 1x4.50x4.50m RCC Box Culvert at Ch. 200.00m on the same road. 0.5360 65.890 M/s.Rafiqul Islam Milton Pahar 65.890 10/10/2018 14/01/2020 100 08/07/2020 Final bill Paid.
16 MSRDP/S/18-19/ BC/ 79 Part-1: Improvement of 910.00m Flexible Pavement of Ghoraghat (UZR)- Ojakandi (UNR) Road [Sonamukhi Embackment]. at Ch.5080.00m – 5990.00m under sadar Upazila, District: Shariatpur Road ID No: 386694007). Part-2: Improvement of 770.00m Flexible Pavement Burirhat GC – Damudya Bourder via Chandonkor GPS Road Ch.0.00m –770.00m under sadar Upazila, District: Shariatpur. 1.6800 132.538 m/s sohel enterprise 132.538 23/01/2019 22/11/2019 100 08/07/2020 Final bill paid.
17 MSRDP/S/18-19/ BC/ 80 Part-1: Detail Estimate for Flexible Pavement of Gazar Bazar (UNR) Mollah Bari Mosque Road from Ch.0.00m –860.00m under sadar Upazila, District: Shariatpur.Part-2: Detail Estimate for Flexible Pavement of Kashipur Hindupara GPS- Takerhat R& H Road from Ch.0.00m –465.00m under sadar Upazila, District: Shariatpur. 1.3250 97.110 m/s foisal enterprise 97.110 15/01/2019 14/01/2020 55 08/07/2020
18 MSRDP/S/18-19/ BC /101 Part-1: Improvement of 2325.00m Flexible Pavement of Chitalia UP- Mohamadpur UP road Ch.1010.00m – 3360.00m & Const. of 2x4.50mx4.50m (Road way=4.88m,Wing wall =5.20m) at Ch. 2092.00m same road under Sadar, Upazila, District: Shariatpur Road.Part-2: Improvement of 2988.00m Flexible Pavement of Shamitir bazaar- Nilkuthi Road Ch.0.00m – 3000.00m. Part-3: Construction of 2x4.50mx4.00m RCC Box Culvert (W=4.88m & WW=5.20m) on Shamitir bazaar- Nilkuthi Road at Ch.2323.00m, under Sadar, Upazila, District: Shariatpur. 5.3200 502.210 m/s sheikh enterprise 502.210 30/05/2019 70 08/07/2020
19 MSRDP/S/18-19/BC/102 Part-1: Improvement of 4190.00m Flexible Pavement of Chaikandi up office – Gonganagar GC via Parchim Atpara Bazar road Ch.3000.00m – 7200.00m & 1No Stucture of Same road at Ch.4500.00m Chainange under Sadar, Upazila, District: Shariatpur.Part-2: Improvement of 2006.00m Flexible Pavement of Barail – Guschgram road Ch. 0.00m – 2022.00m & 4 No Stucture of Same road at Different Chainange, under Sadar, Upazila, District: Shariatpur. 6.2220 596.470 Liton traders 596.470 03/06/2019 30/06/2019 72 08/07/2020
20 MSRDP/S/18-19/ BC /104 Part-1: Detail Estimate for 120.00m Flexiable pavement (Ch. 1415.00m-1535.00m) on Dadpur Launch Ghat- Luxmipur road By Bituminous Carpeting under Sadar Upazila District Shariatpur.(386694004) Part-2: Construction of 2.00 Nos 1x4.00x4.00m RCC Box Culvert on Janjira – Naria Sureswar Road At Ch.632m. & 1868m. (386652006). 0.1200 68.330 m/s said steel king 68.330 24/04/2019 23/01/2020 100 08/07/2020
21 MSRDP/S/18-19/BC/108 Part-A: Detail Estimate for Flexible pavement Kancharikandi (UZR) – Majumderkandi (UNR) road from Ch. 2820.00m – 3730.00m under Sadar, Upazila, District: Shariatpur. Part-B: Construction of U- Drain on Kancharikandi (UZR) – Majumderkandi (UNR) road at Ch.3512.00m under Sadar, Upazila, District: Shariatpur. 0.9100 69.150 M/s Jihad Traders 69.150 24/04/2019 23/01/2019 100 08/07/2020 Final bill Paid.
22 MSRDP/S/ 18-19/ BC /77 Improvement of 1384.00m Flexible Pavement of Sundissar UNR- Guripara GPS via Abu Taleb Master High School road Ch.0.00m – 1392.00m & 2(Two) nos ÒU” Drain at Ch.650.00, Ch.1385.00 under sadar Upazila, District: Shariatpur. 1.3920 105.428   105.428 0 19/01/2019 NOA Issued
Total : 275.1230 (Km) 18101.24 (Lac) 18101.24 (Lac)