SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
1
|
Bhedarganj
|
1
|
MSRDP/S/18-19/BC/115
|
Part-1: Improvement of Road by Paprail Baitul Aka Lam-E Mosque to paprail Jobber Sarder Bari Road at Ch.800-1550m under Bhedarganj Upazila, District Shariatpur. Part-2: Improvement of Road by Bituminous Carpating at Ch.00-630m on Monua Bazar – Aterpara PS Via Monua Madrasha Road under Bhedarganj Upazila, District Shariatpur.
|
1.3800
|
115.310
|
M/S Samim Traders
|
115.310
|
02/09/2019
|
01/09/2020
|
100
|
12/07/2020
|
|
2
|
MSRDP/S/18-19/BC/114
|
Part-1: Improvement of Road by Bituminous carpeting at Ch. 00-490.00m on Monua H/O Mazid Bioati- H/O Sorab Ali Biswas road under Bhedarganj Upazila District Shariatpur.
Part-2: (A). Improvement of Road by at Sajonpur pry.school- Mirjapur via Sardar Bari Road Ch.580-1800m.
(B). Construction 01 Nos (One) U-Drain on Sajonpur pry.school-Mirjapur via Sardar Bari Road at Ch.1692m under Bhedarganj Upazila District Shariatpur.
|
1.7100
|
139.450
|
M/S Mollah Enterprise
|
139.450
|
02/09/2019
|
01/09/2020
|
75
|
12/07/2020
|
|
3
|
MSRDP/S/18-19/BC/100
|
Part-1: Improvement of road by BC at H/O Satter Howlader to H/O Giasuddin Howlader via H/O Harun Sayal road Ch.0.00m – 2300.00m under Bhedargonj, Upazila, District: Shariatpur ( Road ID No: 386145045).
Part-2: Improvement of road by BC Ferangi Kandi- Bhedarganj road – Singjala RPS Road Ch.0.00m – 600.00m under Bhedargonj, Upazila, District: Shariatpur ( Road ID No: 386145242).
|
2.9000
|
254.370
|
M/S Mollah Enterprise
|
254.370
|
03/06/2019
|
30/06/2020
|
45
|
12/07/2020
|
|
4
|
MSRDP//18-19/BC/95
|
1)Improvement of road by BC at Kartickpur Bridge- Sanilkandi Bazar road via Miarchar road Ch.2000.00m – 3200.00m under Bhedargonj Upazila, District: Shariatpur.2)Improvement of road by BC at Charchanda Kalu Munshikandi – Char Chanda Abul Halder Master House road ( Starting point Bhedargonj- Shakhipur GC road Near of Culvert ) Ch.0.00m – 1800.00m under Bhedargonj Upazila District: Shariatpur.Details Estimate for construction of 16.00m RCC Girder Bridge on Shanti Nagar Sayial bazaar -101 No Char Mohishkhali Sarkandi GPS road at Ch.5Km under Bhedargonj Upazila, District: Shariatpur.
|
2.8000
|
336.400
|
M/S Mollah Enterprise
|
336.400
|
03/06/2019
|
30/06/2020
|
80
|
09/07/2020
|
|
5
|
MSRDP//18-19/BC/89
|
Part-1: Improvement of road by BC at Nadu Sarker House to Char Sajonpur Primary School road Ch.0.00m – 1480.00m under BhedargonjUpazila, District: Shariatpur.Part-2:Improvement of road by BC at Rup Nagar bazar to Arshinagar road via Sarker Bari road Ch.0.00m – 1590.00m under Bhedargonj, Upazila, District: Shariatpur.Part-3: Improvement of road by BC at Nowsha Bala Bridge to Shakhipur Boarder road Ch.0.00m – 1690.00m under Bhedargonj, Upazila, District: Shariatpur.
|
4.7600
|
344.040
|
Md: Younus Ali Brothers
|
344.040
|
17/06/2019
|
16/06/2020
|
30
|
09/07/2020
|
|
6
|
MSRDP/S/17-18/SR/39
|
Construction of 2x4.50mx4.50m RCC Box Culvert (w=3.66m) on Kashempur - Kader Sarker Kandi road at ch. 250.00m under Bhedargonj Upazila, Dist. Shariatpur.
|
0.0090
|
21.525
|
M/s. Aziz Construction
|
21.525
|
27/06/2018
|
25/03/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
7
|
MSRDP/S/17-18/BC/40
|
Improvement of BC Road on Kasimpur - Kader Sarkarkandi road at ch. 0.00 - 1590.00m & Construction of 1 nos U-Drain on Kasimpur - Kader Sarkarkandi road at ch. 1050.00m under Bhedargonj Upazila Dist. Shariatpur.
|
1.5900
|
105.220
|
M/s. Acila Enterprise
|
105.220
|
27/06/2018
|
25/06/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
8
|
MSRDP/S/17-18/SR/41
|
Construction of 2x4.50mx4.50m RCC Box Culvert (w=3.66m) on Bhedarganj - Shakhipur road-Kartickpur Bridge road at ch. 04.00m under Bhedargonj Upazila, Dist. Shariatpur.
|
|
22.178
|
M/s. Tarongo Traders
|
22.178
|
27/06/2018
|
26/03/2019
|
75
|
09/07/2020
|
|
9
|
MSRDP/S/17-18/SR/42
|
Construction of 2x4.50mx4.50m RCC Box Culvert (w=3.66m) on Bhedarganj - Shakhipur road-Kartickpur Bridge road at ch. 860.00m under Bhedargonj Upazila, Dist. Shariatpur.
|
|
22.178
|
M/s. Habiba Enterprise
|
22.178
|
12/06/2018
|
11/04/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
10
|
MSRDP/S/17-18/BC/43
|
Improvement of BC Road on Shakhipur GC road to Payatoli road via Charchanda Munshi Bari School road at ch. 0.00 - 1500.00m & Construction of 1 nos 1x3.00x3.00m RCC Box Culvert at ch. 834.00 & 1 nos U-Drain at ch. 472.00 on same road under Bhedargonj Upazila Dist. Shariatpur.
|
2.2250
|
142.047
|
M/s. Nuha&Fiha Enterprise
|
142.047
|
27/06/2018
|
11/06/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
11
|
MSRDP/S/17-18/BC/44
|
Improvement of BC Road on Highway road - H/O Azharul Bala road at ch. 0.00 - 2130.00m under Bhedargonj Upazila Dist. Shariatpur, (Road ID No- 386144026).
|
2.1300
|
151.382
|
M/s. Mim Traders
|
151.382
|
27/06/2018
|
25/06/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
12
|
MSRDP/S/17-18/BC/45
|
Improvement of BC Road on Char Chanda Ukil Kandi Pucca Road-Bakaul Kandi road at ch. 0.00 - 1070.00m & Cosntruction of 1 nos U-Drain ch. 1015.00m on the same road under Bhedargonj Upazila Dist. Shariatpur.Improvement of BC Road on High Way road-Zia Kandi Anu Madbor House road at ch. 0.00 - 1500.00m & Cons. of 1 nos 1x3.00x3.00m RCC Box Culvert at ch. 1340.00m & Cons. 1 nos U-Drain at ch. 1050.00m on the same road under Bhedargonj Upazila Dist. Shariatpur.
|
2.5700
|
173.683
|
M/s. Shifa Enterprise
|
173.683
|
27/06/2018
|
25/06/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
13
|
MSRDP/S/17-18/SR/46
|
Construction of 2x4.50mx4.50m RCC Box Culvert (w=3.66m) on D.M Khali Bazar - Sadar Kandi road at ch. 47.00m under Bhedargonj Upazila, Dist. Shariatpur.
|
|
22.084
|
M/s. Iqbal Hossain Mridha
|
22.084
|
18/06/2018
|
15/03/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
14
|
MSRDP/S/17-18/BC/47
|
Improvement of BC Road on Chaygoan Madrasha to Venopa Bazar via H/O Krisna Master road at ch. 2200.00 - 3100.00m under Bhedargonj Upazila Dist. Shariatpur. Improvement of BC Road on Bhedarganj Burirhat road - Akkasia Primary School via H/O Hamid Gazi road at ch. 2160.00 - 2750.00m under Bhedargonj Upazila Dist. Shariatpur.Improvement of BC Road on Ferangeykandi P.S to Bhedarganj Bridge road at ch. 0.00 - 791.00m under Bhedargonj Upazila Dist. Shariatpur.
|
2.2810
|
161.728
|
M/s. Rishad Traders
|
161.728
|
14/06/2018
|
11/05/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
15
|
MSRDP/S/17-18/BC/48
|
Improvement of BC Road on H/O Manggal Sarder - Koraltali GPS road at ch. 0.00 - 566.00m & Cosn. of 1x3.00x3.00 RCC Box Culvert at ch. 156.00m on the same road under Bhedargonj Upazila Dist. Shariatpur.Improvement of BC Road on Pachim Chaygoan - Sayal Bari Bridge (Mothkhola) - Burirhat road at ch. 770.00 - 1220.00m & Cosn. of 1x3.00x3.00m RCC Box Culvert at ch. 1160.00m on the same road under Bhedargonj Upazila Dist. Shariatpur.
|
1.0160
|
108.113
|
M/s. Delawar Hossain Mollik & Co
|
108.113
|
18/06/2018
|
16/06/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
16
|
MSRDP/S/17-18/HBB/49
|
Improvement of HBB Road on Chaygoan Govt. Pry. School - Burirhat road via Ranishar road at ch. 0.00 - 1830.00m & Cosn. of 2x4.50x4.50 RCC Box Culvert (w=3.66m) at ch. 610.00m on the same road under Bhedargonj Upazila Dist. Shariatpur.
|
1.8300
|
146.602
|
M/s. T.T.M. Trading
|
146.602
|
27/06/2018
|
25/06/2018
|
100
|
09/07/2020
|
Final Bill paid.
|
17
|
MSRDP/S/17-18/BC/55
|
Part-A: Improvement of BC Aterpara Pucca Bridge - Aterpara GPS road via H/O Karim Molaah road at ch. 800.00 - 1060.00m under Bhedargonj Upazila Dist. Shariatpur. Part-B: Improvement of BC Rambhadrapur Lanchghat - Naria Border via Saner Bazar road at ch. 2400.00 - 3200.00m under Bhedargonj Upazila Dist. Shariatpur.Part-C: Improvement of HBB Lakarta ICE Factory-Digambory road at ch. 2000.00 - 3060.00m under Bhedargonj Upazila Dist. Shariatpur.
|
2.1200
|
136.822
|
M/s. Jorasako International
|
136.822
|
21/06/2018
|
17/08/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
18
|
MSRDP/S/17-18/BC/Maint-01
|
Maintenance of H/O Sekandar Madbor - Shakhipur GC road from Ch. 0.00 - 1540m by bc under Bhedargonj Upazila, Dist. Shariatpur. Maintenance of K.M Pry. School - Paprail road from Ch. 0.00 - 1190.00m by bc under Bhedargonj Upazila, Dist. Shariatpur .Maintenance of Lakarta IC Fectory - Digambory road from Ch. 0.00 - 555.00m by BC under Bhedargonj Upazila, Dist. Shariatpur
|
3.2850
|
51.812
|
M/s. Delwar Hossian Mollil
|
51.812
|
01/07/2018
|
29/04/2019
|
100
|
09/07/2020
|
Final bill paid.
|
19
|
MSRDP/S/17-18/BC/54
|
Part-A: Improvement of BC Charchanda Kalu Munshikandi-Char Chanda Abul Halder Master House road at ch. 1800.00 - 2900.00m & Madasha Link-230.00m b. Construction of 1x3.00x3.00m RCC Box Culvert on Same Road at Ch. 2320.00m under Bhedargonj Upazila Dist. Shariatpur,Part-B: Improvement of HBB Munshi Kandi GPS-Mozai Mollar Kandi road at ch. 0.00 - 1710.00m under Bhedargonj Upazila Dist. Shariatpur.
|
2.3000
|
142.150
|
M/S USA TRADERS
|
142.150
|
18/06/2018
|
16/06/2019
|
100
|
08/07/2020
|
Final Bill Paid.
|
20
|
MSRDP/S/18-19/BC/91
|
Improvement of road by BC at Bangla Bazar – Upazila Sadar road via Ali Akbar Lasker at Charkumaria road Ch.1150.00m – 2000.00m under Bhedargonj Upazila, District: Shariatpur. (Road ID No: 386145087).
|
0.8500
|
64.100
|
M/S Soikot enterprise
|
64.100
|
13/05/2019
|
13/02/2020
|
100
|
08/07/2020
|
Final Bill Paid.
|
21
|
MSRDP/S/17-18/BC/90
|
Improvement of road by HBB Charbhaga Pada Kandi – H/O Moti Master via Bokaul Kandi road Ch.1600.00m – 2600.00m. Construction of 2x4.50mx4.50m RCC Box Culvert (w=3066m) Charbhaga Pada Kandi – H/O Moti Master via Bokaul Kandi road Ch.2028.00m.Construction of 01 Nos (One) U-Drain HBB on Charbhaga Pada Kandi – H/O Moti Master via Bokaul Kandi road Ch.2470.00m under Bhedargonj Upazila, District: Shariatpur.
|
1.0000
|
51.690
|
m/s Alomgir traders
|
51.690
|
26/02/2019
|
25/11/2019
|
100
|
08/07/2020
|
|
22
|
MSRDP//18-19/BC/94
|
Part-1: Improvement of road by BC at Mazi Kandi – Station bazar via Ananda Bazar road Ch.750.00m – 3000.00m under Bhedargonj, Upazila District: Shariatpur. (Road ID No: 386144022).
Part-2: Improvement of road by BC at Afamollah Bazar – Char- Sheris P/S. road Ch.0.00m – 2750.00m Construction of 2x4.50mx4.50m RCC Box Culvert (w=3066m) Afamollah Bazar – Char- Sheris P/S. road Ch.1410.00m under Bhedargonj, Upazila, District: Shariatpur.( Road ID No: 386145069).
Part-3: Improvement of road by BC at Saifullah Master School – Prodhania Kandi road Ch.0.00m – 1520.00m & School Link -50m under Bhedargonj Upazila, District: Shariatpur. (Road ID No: ).
|
6.5200
|
336.400
|
m/s mollah enterprise
|
336.400
|
|
|
0
|
08/07/2020
|
NOA issue
|
23
|
MSRDP/S/17-18/SR/38
|
Construction of 2x4.50mx4.50m RCC Box Culvert (w=3.66m) on Charchanda Puran Bazar-D.M Khali UP road (Near of Munshi Bari) at ch. 525.00m under Bhedargonj Upazila, Dist. Shariatpur.
|
|
21.525
|
M/s. Hawlader Enteprise
|
21.525
|
27/06/2018
|
25/03/2019
|
100
|
08/07/2020
|
|
|
2
|
Damuddya
|
1
|
MSRDP//18-19/BC/107
|
Improvement road by BC Shidulkura bazar- Baroghar Road at Ch.1570.00m – 3460.00m. Damuddya Upazila, District: Shariatpur.
|
1.8900
|
204.390
|
M/S Samim Traders
|
204.390
|
03/06/2019
|
02/06/2020
|
75
|
12/07/2020
|
|
2
|
MSRDP/S/17-18/BC/66
|
Improvement of BC Dhanhata Steel Bridge - Food Godwon at ch. 136.00 – 625.00m under Damuddya Upazila Dist. Shariatpur.
|
0.4900
|
21.790
|
M/S Himu Enterprise
|
21.790
|
26/07/2018
|
25/04/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
3
|
MSRDP/S/17-18/SR/34
|
Construction of 2-Vent (4.00x4.00m) Box Culvert on Tilai DC road-Dakhin Para via Kanaikati road at Ch. 222.00m under Damuddya Upazila, Dist. Shariatpur.
|
|
28.934
|
M/s. Zerin Traders
|
28.934
|
04/06/2018
|
03/04/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
4
|
MSRDP/S/17-18/BC/35
|
a) Improvement of BC Road on Mazirtek - Syedbasta via Ekori road at Ch. 1300.00 - 1597.00m under Damuddya Upazila Dist. Shariatpur.b) Improvement of BC Road on Modernhat - Balakandi road at Ch. 1687.00 - 3340.00.00m under Damuddya Upazila Dist. Shariatpur.
|
1.3560
|
130.124
|
M/s. Irin Enterprise
|
130.124
|
24/05/2018
|
23/05/2019
|
70
|
09/07/2020
|
|
5
|
MSRDP/S/17-18/BC/67
|
Improvement of BC Malgong Ataimkhana D. C road–Anandobazar via Bhuabazar, chairs Danukati Gps. at ch. 1680.00 - 3388.00m under Damuddya Upazila Dist. Shariatpur.
|
1.7080
|
116.698
|
M/s. Madbar Enterprise
|
116.698
|
02/08/2018
|
01/08/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
6
|
MSRDP/S/17-18/BC/68
|
Part-1: Improvement of BC Tilai DC road- Dakhin para via Kkanaikati road at ch. 427.00 – 1200.00m under Damuddya Upazila Dist. Shariatpur.Part-2: Improvement of BC Syedbosta Kheyagaat- Damudya at ch. 0.00 –
775.00m under Damuddya Upazila Dist. Shariatpur.
|
1.5480
|
103.508
|
M/s. Nusrat Zahan Enterprise
|
103.508
|
02/08/2018
|
01/04/2019
|
60
|
09/07/2020
|
Final Bill paid.
|
7
|
MSRDP/S/17-18/BC/69
|
Improvement of BC Dhani Bazar- Amin Bazar via Akan bari Mosque .at ch 00.00 - 3137.00m under Damuddya Upazila Dist. Shariatpur.
|
3.1370
|
205.750
|
M/s. Alif Enterprise
|
205.750
|
08/08/2018
|
07/11/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
8
|
MSRDP/S/17-18/BC/70
|
Improvement of BC Thanger Bari Bidge- Gani Sarder Bridge Via Kotal Bari .at ch 00.00 - 1762.00m under Damuddya Upazila Dist. Shariatpur.
|
1.7620
|
118.530
|
M/s. Nova Enterprse
|
118.530
|
08/08/2018
|
07/11/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
9
|
MSRDP/S/17-18/BC/71
|
Improvement of BC Charbhoyrabig river- Salauddin MollahviaMojibor Peda .at ch 00.00 - 2264.00m under Damuddya Upazila Dist. Shariatpur.
|
2.2640
|
133.754
|
M/s. Nova Enterprse
|
133.754
|
07/08/2018
|
06/08/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
10
|
MSRDP/S/18-19/ BC /75
|
Improvement the road By BC of Keorbhanga- Dakhinpara D.C road via Darishkati pry Road at Ch.500.00m – 1934.00m under Damudya Upazila, District: Shariatpur.
|
1.4340
|
118.530
|
m/s nova enterprise
|
118.530
|
15/01/2019
|
14/01/2020
|
80
|
09/07/2020
|
|
11
|
MSRDP/S/18-19/ BC /76
|
Part-1: Improvement the road By BC of Ramrayerkandi- char Narayanpur Road at Ch.850.00m – 1304.00m under Damudya Upazila, District: Shariatpur.Part-2: Improvement the road By BC of Dhanokati Main road to Dogerpar Road at Ch.486.00m – 1166.00m under Damudya Upazila, District: Shariatpur
|
1.1340
|
81.704
|
m/s shariatpur construction ;
|
81.704
|
21/01/2019
|
20/01/2020
|
80
|
09/07/2020
|
|
12
|
MSRDP/S/18-19/ BC /81
|
Improvement the road By BC of Charbhoyar-Charnarayanpur Road Ch. 800.00m – 1900.00m under Damudya Upazila, District: Shariatpur.
|
1.1000
|
81.836
|
m/s suborna construction
|
81.836
|
10/01/2019
|
09/01/2020
|
65
|
09/07/2020
|
|
13
|
MSRDP/S/18-19/BC/Maint-02
|
1.Maintenance of Atimkhana-Malgaon Road Via Talukder Kandi Road at ch.00-988m under Damuddya Upazila Dist. Shariatpur
2.Improvement of BC Bindaikati Madradha-D.C road at ch. 510.00 - 1190.00m under Damuddya Upazila Dist. Shariatpur
.3.Improvement of BC H/O Dr Yusuf Alim-Darulaman H/O Rashid road at ch. 0.00- 658.00m under Damuddya Upazila Dist. Shariatpur. 4.Improvement of BC Moderhat-Blakandi road .at ch 00.00 - 655.00m under Damuddya Upazila Dist. Shariatpur .
|
2.9810
|
64.115
|
M/s. Nusrat Zahan Enterprise
|
64.115
|
02/08/2018
|
01/04/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
14
|
MSRDP/S/18-19/BC/Maint-04
|
1.Improvement of BC Charpatalia Bazar-School road .at ch 00.00 - 745.00m under Damuddya Upazila Dist. Shariatpur .2.Improvement of BC Shdulkura Bazar-Baroghar road .at ch 00.00 - 706.00m under Damuddya Upazila Dist. Shariatpur 3.Improvement of BC R & H near Chairman Bari-Thengerbari UZR via Taltola Lnchghat road .at ch 00.00 - 780.00m under Damuddya Upazila Dist. Shariatpur
|
2.2310
|
83.379
|
M/s.Sumi Traders
|
83.379
|
21/06/2018
|
18/03/2019
|
100
|
09/07/2020
|
Final Bill paid.
|
15
|
MSRDP/S/18-19/BC/Maint-10
|
1.Improvement of BC Charpatalia Bazar-Mamudpaty School road .at ch 00.00 - 745.00m under Damuddya Upazila Dist. Shariatpur.2.Improvement of BC Shdulkura Bazar-Baroghar road .at ch 00.00 - 706.00m under Damuddya Upazila Dist. Shariatpur.3.Improvement of BC R & H near Chairman Bari-Thengerbari UZR via Taltola Lnchghat road .at ch 00.00 - 780.00m under Damuddya Upazila Dist. Shariatpur.
|
1.6970
|
21.214
|
M/s. Rishad Traders
|
21.214
|
27/12/2018
|
25/04/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
16
|
MSRDP/S/18-19/BC/Maint-11
|
Maintenance Work of Dhoni Samur Dokan- H/o Gofur Pagla Road at Ch. 0.00km 700m by BC under Damudda Upazila Dist. Shariatpur
|
0.7000
|
16.177
|
M/s.Sayeed Steel
|
16.177
|
27/12/2018
|
25/04/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
17
|
MSRDP/S/18-19/BC/Maint-12
|
Maintenance Work of Howladerkandi-Subachani via Chairman bari Road at Ch. 0.00km 1000km by BC under Damudda Upazila Dist. Shariatpur
|
1.0000
|
23.631
|
M/s. Mridha Traders
|
23.631
|
20/12/2018
|
19/04/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
18
|
MSRDP/S/18-19/BC/Maint-13
|
Part-01 Maintenance Work of Dhanokati Main road to Dogerpar Road at Ch. 0.00km 486km by BC under Damudda Upazila Dist. Shariatpur Part-02 Maintenance Work of 14 no pry. School-Bele bridge Road at Ch. 0.00km 720km by BC under Damudda Upazila Dist. Shariatpur
|
1.2060
|
20.726
|
M/s. Amena Traders
|
20.726
|
27/12/2018
|
25/04/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
|
3
|
Goshairhat
|
1
|
MSRDP/S/18-19/ BC /103
|
Part-1: Estimate for Construction of Improvement of Kodalpur Tahsil Office- purba Damudya road via uttar Malpara road by BC at Ch.0.00m – 2250.00m (Effective Length=2087.00m). under Goshairhat, Upazila, District: Shariatpur.Part-2: Estimate for (A) Construction of 3x4.50mx4.50m RCC Box Culvert on Pakhamsar – Bashgari via Dhalir hat road at Ch.240.00m. (B) Construction of 3x4.50mx4.50m RCC Box Culvert on Pakhamsar – Bashgari via Dhalir hat road at Ch.742.00m. under Goshairhat, Upazila, District: Shariatpur .Part-3: Estimate for Construction of 2x4.5x4.50m RCC Box Culvert On Harichar Khayaghat to Purbo Kodalpur Simania Via Abull Dargi Kandi Road at Ch.827.00.00m Under Goshairhat Upazila, District.
|
2.2500
|
259.050
|
M/S Mollah Enterprise
|
259.050
|
16/06/2019
|
15/06/2020
|
75
|
12/07/2020
|
|
2
|
MSRDP/S/17-18/ BC/01
|
Improvement of BC Road on Pakhamasr- Bashgari Via Dhalirhat road at ch. 3117.00-4054.00m.
|
0.9180
|
63.033
|
M/s. R.K.Construction
|
63.033
|
01/05/2018
|
28/02/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
3
|
MSRDP/S/17-18/BC/02
|
Improvement of BC Road on UZR Mazi Bari to Chamonpura Imrania Madrasha road at ch. 600.00 -825.00m.
|
0.2250
|
15.866
|
M/s. Shamim Traders
|
15.866
|
17/05/2018
|
16/02/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
4
|
MSRDP/S/17-18/BC/03
|
Improvement of BC Road on Nagarpara Mokaram Mosque- Molonchra road at ch. 00.00 -1000.00m.
|
1.0000
|
64.884
|
M/s. Almas Aman Traders
|
64.884
|
14/05/2018
|
13/02/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
5
|
MSRDP/S/17-18/BC/04
|
Improvement of BC Road on Nagarpara GC at Holy potty- Char Patalia Bazar via Talucder bari road at ch. 1000.00 -2000.00m.
|
1.0000
|
62.720
|
M/s. Foysal
|
62.720
|
01/05/2018
|
28/02/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
6
|
MSRDP/S/17-18/BC/05
|
Improvement of BC Road on Shamontasar UP (RHD)- Charpatalia Bazar road at ch. 00.00 -540.00m.
|
0.5400
|
30.590
|
M/s USA Traders
|
30.590
|
17/05/2018
|
16/01/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
7
|
MSRDP/S/17-18/SR/06
|
Construction of 2x4.50x4.50m. RCC Box Culvert on Pakhamsar- Bashgari via Dhalirhat road at ch.3202.00m.
|
9.0000
|
29.814
|
M/S Pilot enterprise
|
29.814
|
01/05/2018
|
31/01/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
8
|
MSRDP/S/17-18/SR/07
|
Construction of 1x4.00x4.00m. RCC Box Culvert on Nagarpara GC to Holy Potty - Char Patalia Bazar via Talucder bari raod at ch. 1738.00m.
|
4.0000
|
12.972
|
M/s AR Enterprise
|
12.972
|
29/04/2018
|
28/01/2018
|
100
|
09/07/2020
|
Final Bill Paid.
|
9
|
MSRDP/S/17-18/SR/08
|
Construction of 2x4.50x4.50m. RCC Box Culvert on Nagarpara GC to Holy Potty - Char Patalia Bazar via Talucder bari raod at ch. 00.00m.
|
9.0000
|
29.367
|
M/S Alomgir Traders
|
29.367
|
17/05/2018
|
16/02/2018
|
100
|
09/07/2020
|
Final Bill Paid.
|
10
|
MSRDP/S/17-18/SR/09
|
Construction of 2x4.50x4.50m. RCC Box Culvert on Nagarpara GC to Holy Potty - Char Patalia Bazar via Talucder bari raod at ch. 1203.00m.
|
9.0000
|
29.255
|
M/s. A.R.M. Construction
|
29.255
|
17/05/2018
|
16/02/2018
|
100
|
09/07/2020
|
Final Bill Paid.
|
11
|
MSRDP/S/17-18/SR/10
|
Construction of 2x4.50x4.50m. RCC Box Culvert on Nagarpara GC to Holy Potty - Char Patalia Bazar via Talucder bari raod at ch. 1984.00m. (Road ID 386364012)
|
9.0000
|
29.405
|
M/s. Khan Enterprie
|
29.405
|
30/05/2018
|
29/12/2018
|
100
|
09/07/2020
|
Final Bill Paid.
|
12
|
MSRDP/S/17-18/BC/11
|
Improvement of BC Road on Charmonpur GPS- Chitalia road at ch. 700.00 - 1145.00m.
|
0.4800
|
29.410
|
M/s. Toma Enterprise
|
29.410
|
17/05/2018
|
16/02/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
13
|
MSRDP/S/17-18/BC/12
|
Improvement of BC Road on Goriberchar GC Purbo Damuddya Shimana via Rashid Kazir kandi road at ch. 00.00 - 1800.00m.
|
1.4360
|
109.414
|
M/s. Irin Enterpriwe
|
109.414
|
17/05/2018
|
16/05/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
14
|
MSRDP/S/17-18/BC/36
|
Improvement of BC Road on Shaykhya H/O Hasem Munshi - Madrasha Bazar via Bangla Bazar Bridge road at Ch. 0.00 - 3050.00m under Goshairhat Upazila Dist. Shariatpur,
|
3.0500
|
187.618
|
M/s. Sristi Enterprise
|
187.618
|
24/05/2018
|
26/09/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
15
|
MSRDP/S/17-18/BC/37
|
a) Improvement of BC Road on Nagarpara Govt. Ahmadia Dakhil Madrasha to Sree Krisna Pal House via Nagarpara 2 Nos GPS road at Ch. 0.00 - 1100.00m under Goshairhat Upazila Dist. Shariatpur.Improvement of BC Road on Nandigram Box Culvert - Tarulia Ukilbari via fakir bari Jame Mosque road at Ch. 0.00 - 600.00m under Goshairhat Upazila Dist. Shariatpur.
|
1.1000
|
118.969
|
M/s. Reza Constrution
|
118.969
|
27/06/2018
|
26/06/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
16
|
MSRDP/S/18-19/BC/Maint-07
|
Maintenance of Nagerpara GC at Holy Potty-Char patalia Bazar via Talkderbar at Ch. 0.00m 1055m by BC under Goshairhat Upazila Dist. Shariatpur
|
1.0550
|
30.413
|
M/s. Sufia Enterprise
|
30.413
|
20/12/2018
|
18/04/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
17
|
MSRDP/S/18-19/BC/Maint-08
|
Maintenance of Pakamshar-Basgari via dhalirhat Road at Ch. 0.00m 2117m by BC under Goshairhat Upazila Dist. Shariatpur
|
2.1100
|
55.962
|
M/s. Nusab Enterprise
|
55.962
|
18/12/2018
|
17/04/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
18
|
MSRDP/S/18-19/BC/Maint-09
|
Maintenance of Kodalpur GCCR at Dewan bari-Shakya Bazar road at Ch. 0.00m 2015m by BC under Goshairhat Upazila Dist. Shariatpur
|
2.0150
|
62.744
|
M/s. Misu Enterprise
|
62.744
|
20/12/2018
|
19/04/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
19
|
MSRDP/R/18-19/BC/maint-07
|
Maintenance of Nagerpara GC at Holy Potty-Char patalia Bazar via Talkderbar at Ch. 0.00m – 1055m by BC under Goshairhat Upazila, Dist. Shariatpur.
|
1.0550
|
30.410
|
m/s shufia enterprise
|
30.410
|
20/12/2018
|
19/04/2019
|
100
|
08/07/2020
|
Final Bill Paid.
|
20
|
MSRDP/S/18-19/BC/88
|
Part-1: Estimate for Rehabilitation Work of Dasherjungle GC – Dhanusikder hat via Kutchipatti up Road By BC Ch.00-7520.00m ( Effective length= 7149.00m) & 4 Nos RCC Box Culvert (1.00x1.00m) at ch.812.00m, 1190.00m, 1880.00m & 2350.00m Under Goshairhat Upazila District : Shariatpur.Part-2: Estimate For Improvement of BC Road On Jushairgoan Bazar- Boxsompotty GPS via Nandi Gram road at Ch. 1000- 1500.00m Under Goshairha Upazila District: Shariatpur.Part-3: Estimate For Improvement of Dasherjungle- Machuakhali tulatali Madrasha Road by BC at Ch. 2480- 3700.00m Under Goshairhat Upazila, District: Shariatpur.
|
9.2720
|
603.720
|
haji sheikh progoti
|
603.720
|
30/05/2019
|
29/11/2020
|
100
|
08/07/2020
|
Final Bill Paid.
|
|
4
|
Janjira
|
1
|
MSRDP//18-19/BC/123
|
Part-1: Improvement of Bilaspur GC road at Akand Kandi to Bilaspur GC road by BC at ch.610-1870m(Effective Length =1260.00m) under Janjira Upazila, District: Shariatpur. Part-2: Improvement of Janjira-Kewrakandi GCCR- Ramkishnopur via Sobus Chata road by BC at ch.00 -700.00m under Janjira Upazila, District: Shariatpur.
|
1.9600
|
166.850
|
|
166.850
|
18/05/2020
|
17/05/2021
|
100
|
14/07/2020
|
Final Bill Paid
|
2
|
MSRDP/S/18-19/BC/ Maint /14
|
Shibchar border road at ch.1233-3040m (Effective Length =1737.00m) under Janjira Upazila, District: Shariatpur. Part-2: Maintenance of A.M.M kandi- Dhalirhat road Ch.0.00m-1235.00m.under Janjira Upazila, District Shariatpur. Part-3: Maintenance of Nawduba hat north side bridge-Char Chanda (Shibchar border) via west side Graveyard & Golam Sarwar house road at ch.00 -1610m(Effective Length =1602.00m) under Janjira Upazila, District: Shariatpur. Part-4: Maintenance of Janjira PS Shariatpur Janjira RHD via Dhalirhat road at ch.1730-2330m under Janjira Upazila, District: Shariatpur.
|
5.1520
|
289.930
|
M/S Sheikh Enterprise
|
289.930
|
18/05/2020
|
09/11/2021
|
30
|
12/07/2020
|
|
3
|
MSRDP/S/18-19/BC/110
|
Madaripur Shibchar road by at Ch.0. 00m-1570.00 m under Janjira, Upazila, District: Shariatpur. Part-B: Imp. of Kazirhat –Durgarhat Road by HBB at ch.0.00m-1360.00m & Construction of 1x1.5x1.00m RCC Box culvert at Kazirhat –Durgarhat Road 700.00m under Janjira Upazilla, District: Shariatpur.
|
2.9300
|
148.070
|
M/S Mizan Enterprise
|
148.070
|
16/06/2019
|
25/06/2020
|
100
|
12/07/2020
|
Final Bill Paid.
|
4
|
MSRDP//18-19/HBB/82
|
Part-1: Improvement of Khoratola Primary School- H/O Nuru Madbor Road by H.B.B at Ch. 0.00m – 805.00m under Janjira Upazila, District: Shariatpur.Part-2: Improvement of Dakhin Dubisibor Mollah Kandi Razumadbor bari- Delowarmadbor bari Road by H.B.B at Ch. 0.00m – 300.00m under Janjira Upazila, District: Shariatpur.Part-3: Improvement of Paschi Nawduba- Kutubpur Road by H.B.B at Ch. 0.00m – 885.00m under Janjira Upazila, District: Shariatpur.
|
1.9900
|
94.850
|
M/S Himu Enterprise
|
94.850
|
23/01/2019
|
22/01/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
5
|
MSRDP/S/17-18/SR/18
|
Construction of 3x4.50x4.00m RCC Box Culvert on Dubsaiber hat - Rupbabur hat road at Ch.2105.00m under Janjira Upazila Dist. Shariatpur.
|
|
38.910
|
M/S Samim Traders
|
38.910
|
31/05/2018
|
29/01/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
6
|
MSRDP/S/17-18/SR/16
|
Construction of 3x4.50x4.00m RCC Box Culvert on Dubisaiber hat - Rupbabur hat via MC Kandi road at Ch.834.00m under Janjira Upazila Dist. Shariatpur.
|
|
38.750
|
M/S Sadiya Enterprise
|
38.750
|
30/05/2018
|
29/03/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
7
|
MSRDP/S/17-18/SR/15
|
Construction of 3x4.50x4.00m RCC Box Culvert on Sarder Kandi - Shimultala UZR road at Ch.170.00m under Janjira Upazila Dist. Shariatpur.
|
|
39.925
|
M/s. Tonmoy Enterprise
|
39.925
|
22/05/2018
|
21/03/2019
|
100
|
08/07/2020
|
Final bill paid.
|
8
|
MSRDP/S/17-18/HBB/17
|
(Part-A) Improvement of HBB Road on Palerchar to Dangi Kandi Pry. School road at Ch. 1000.00 - 3580.00m (Part-B) Construction of 1x7.50x0.925x0.90m Box Culvert. (U-Drain) on Palerchar to Dangi Kandi Pry. School road at Ch. 1728.00m under Janjira Upazila Dist. Shariatpur.
|
2.5700
|
132.057
|
M/s. Khan Enterprise
|
132.057
|
30/05/2018
|
29/05/2019
|
100
|
08/07/2020
|
|
9
|
MSRDP/S/17-18/HBB/19
|
Improvement of HBB Road on Uttar Cable Nagor - Khoratola School road via Razzaq Madbor road at Ch. 0.00 - 1450.00m under Janjira Upazila Dist. Shariatpur.
|
1.4500
|
62.430
|
M/s. Aysa Enterprise
|
62.430
|
17/05/2018
|
16/02/2019
|
100
|
08/07/2020
|
Final bill paid.
|
10
|
MSRDP/S/17-18/HBB/20
|
(Part-A) Improvement of HBB Road on Laukhola bazar - Rayerkandi Pry. School road at Ch. 0.00 - 1700.00m, (rpat-B) Construction of 1x7.50x0.925x0.90m Box Cul. (U-Drain) on Laukhola bazar - Rayerkandi Pry. School road at Ch. 900.00m under Janjira Upazila Dist. Shariatpur.
|
1.7000
|
79.145
|
M/s. Solaimand Traders
|
79.145
|
27/05/2018
|
26/02/2019
|
100
|
08/07/2020
|
Final Bill Paid.
|
11
|
MSRDP/S/17-18/SR/21
|
Construction of 3x4.50x4.00m RCC Box Culvert on Palerchar - Dhangi Kandi PS road at Ch.900.00m under Janjira Upazila Dist. Shariatpur.
|
|
38.751
|
M/s. Awal Traders
|
38.751
|
27/05/2018
|
26/01/2019
|
100
|
08/07/2020
|
Final bill paid.
|
12
|
MSRDP/S/17-18/HBB/22
|
Improvement of HBB Road on Khalek Serthi Shanga R&H-Joynagar GC to Ismail Khan house road at Ch. 0.00 - 750.00m under Janjira Upazila Dist. Shariatpur.
|
0.7500
|
32.117
|
M/s. Mridha Traders
|
32.117
|
14/05/2018
|
13/03/2019
|
100
|
08/07/2020
|
|
13
|
MSRDP/S/17-18/HBB/23
|
Improvement of HBB Road on Janjira Durbadanga bazar - Howladar kandi Pry. School road at Ch. 0.00 - 1000.00m under Janjira Upazila Dist. Shariatpur.
|
1.0000
|
57.309
|
M/s.Mohammad Ali Associates
|
57.309
|
31/05/2018
|
30/03/2019
|
100
|
08/07/2020
|
|
14
|
MSRDP/S/17-18/BC/56
|
Part-A: Improvement of BC Shariatpur - Janjira - Kawarakandi R&H to Shariatpur Gonganagar - Mongol Mazir Ghat R&H road at ch. 2550.00 - 3625.00m under Janjira Upazila Dist. Shariatpur.Part-B: Improvement of BC Bangobazar - Boro Gopalpur road to Uttar Shikder Kandi road at ch. 0.00 - 1150.00m under Janjira Upazila Dist. Shariatpur.Part-C: Improvement of BC Palerchar UP Office - to Mongol Mazir Ghat road at ch. 3104.00 - 3964.00m under Janjira Upazila Dist. Shariatpur.
|
3.0850
|
211.800
|
M/s.Neloy Enterprise
|
211.800
|
21/06/2018
|
17/08/2019
|
100
|
08/07/2020
|
Final Bill Paid.
|
15
|
MSRDP/S/17-18/BC/58
|
Improvement of BC Dabuldia - Taher Madbor hat road at ch. 0.00 - 2500.00m under Janjira Upazila Dist. Shariatpur.
|
2.5000
|
152.079
|
M/s. Irin Enterprise
|
152.079
|
18/06/2018
|
15/06/2019
|
100
|
08/07/2020
|
Final Bill Paid.
|
16
|
MSRDP/S/17-18/BC/57
|
Improvement of BC Dubisaibor Hat - Rupbaburhat via M.Kandi road at ch. 0.00 - 4090.00m & Construction of 1x7.50x0.925m Box Culvert (U-Drain) of Same road under Janjira Upazila Dist. Shariatpur.
|
4.0900
|
268.849
|
M/s. sheikh Enterprise
|
268.849
|
23/07/2018
|
22/09/2019
|
100
|
08/07/2020
|
Final Bill Paid.
|
17
|
MSRDP/S/18-19/HBB/82
|
Part-1: Improvement of Khoratola Primary School- H/O Nuru Madbor Road by H.B.B at Ch. 0.00m – 805.00m under Janjira Upazila, District: Shariatpur.Part-2: Improvement of Dakhin Dubisibor Mollah Kandi Razumadbor bari- Delowarmadbor bari Road by H.B.B at Ch. 0.00m – 300.00m under Janjira Upazila, District: Shariatpur.Part-3: Improvement of Paschi Nawduba- Kutubpur Road by H.B.B at Ch. 0.00m – 885.00m under Janjira Upazila, District: Shariatpur.
|
1.9900
|
94.850
|
M/S H M TRADERS
|
94.850
|
23/01/2019
|
22/01/2019
|
100
|
08/07/2020
|
Finnal Bill Paid.
|
18
|
MSRDP/S/18-19/HBB/83
|
Improvement of Char Laxmikantopur- Shibchar Border Road by H.B.B at Ch. 0.00m – 1365.00m under Janjira Upazila, District: Shariatpur Road ID No: 386945018).
|
1.3650
|
60.850
|
M/S yelies traders
|
60.850
|
23/01/2019
|
22/10/2019
|
100
|
08/07/2020
|
Finnal Bill Paid.
|
19
|
MSRDP/S/18-19/HBB/84
|
Improvement of Rupbabur hat- Rustom madbor hat Road by H.B.B at Ch. 0.00m – 2330.00m under Janjira Upazila, District: Shariatpur .
|
2.3300
|
98.430
|
M/S Mishu enterprise
|
98.430
|
21/01/2019
|
20/11/2019
|
100
|
08/07/2020
|
Final Bill Paid.
|
20
|
MSRDP/S/18-19/HBB/85
|
Improvement of Vodrashan pacca road- Joynagar G.C road via Boro Gopalpur U.P office Road by H.B.B at Ch. 0.00m – 1750.00m under Janjira Upazila, District: Shariatpur.
|
1.7500
|
77.810
|
M/S NUSRAT JAHAN TRADERS
|
77.810
|
23/01/2019
|
22/01/2020
|
100
|
08/07/2020
|
Final bill paid.
|
21
|
MSRDP/S/18-19/HBB/86
|
Improvement of Kathuria Primary School Connecting Road by H.B.B at Ch. 0.00m – 1175.00m under Janjira Upazila, District: Shariatpur Road ID No: 386945026).
|
1.1750
|
57.030
|
MIM FRABIC
|
57.030
|
23/01/2019
|
22/11/2019
|
100
|
08/07/2020
|
Final bill paid.
|
22
|
MSRDP/R/17-18/HBB/87
|
Part-1: Improvement of Laukhola bazar- Chardhupuria Border Road by H.B.B at Ch. 0.00m – 650.00m under Janjira Upazila, District: Shariatpur.Part-2: Improvement of House of Mostofa Kazi – House of Jamal mollah Road by H.B.B at Ch. 0.00m – 335.00m under Janjira Upazila, District: Shariatpur.
|
0.9850
|
49.700
|
M/S ASMA ENTERPRISE
|
49.700
|
23/01/2019
|
22/11/2019
|
100
|
08/07/2020
|
Final bill paid.
|
23
|
MSRDP/S/17-18/BC/maint-05
|
Improvement of BC Sakim Ali Shop to Jhankhar kandi Notun Gram Road By BC at ch 00.00 - 1670.00m under Damuddya Upazila Dist. Shariatpur.
|
1.6700
|
89.220
|
M/S SHEFAT ENTERPRISE
|
89.220
|
17/08/2018
|
07/05/2019
|
100
|
08/07/2020
|
Final bill paid.
|
|
5
|
Naria
|
1
|
MSRDP/S/18-19/SR/120
|
Improvement of RCC Pavement road at Char Atra River side to Nowpara Connecting road at ch. 0.00m – 3300.00m under Naria Upazila, Dist: Shariatpur.
|
3.3000
|
590.310
|
M/S Samim Traders
|
590.310
|
24/02/2020
|
23/02/2020
|
20
|
12/07/2020
|
|
2
|
MSRDP//18-19/HBB/118
|
Improvement of Bhumkhara- Gulmaize Road by HBB from at Ch.3580.00m – 5705.00m. under Naria, Upazila, District: Shariatpur.
|
2.1250
|
101.810
|
M/S Solaiman Traders
|
101.810
|
14/08/2019
|
13/08/2020
|
100
|
12/07/2020
|
|
3
|
MSRDP//18-19/HBB/117
|
Improvement of Bhojeswar GC – Dogree R & H road by HBB at Ch.3615.00m – 4425.00m. (2) Construction of RCC Box Culvert (1x3.50mx3.50m) Ch.3765.00m, under Naria, Upazila, District: Shariatpur.
|
0.8100
|
58.590
|
M/S Rajony Enterprise
|
58.590
|
21/08/2019
|
20/05/2020
|
100
|
12/07/2020
|
Final Bill Paid.
|
4
|
MSRDP//18-19/HBB/116
|
Improvement of HBB on Nowga Dhali Bari Ghata- Khalil Dhali Bari Ghata Road. Ch.0.00m-530.00m.
b.Construction of 2x4.00x4.00m RCC Box culvert on Nowga Dhali Bari Ghata- Khalil Dhali bari Ghata Road. Ch.500.00m Under : Naria, District: Shariatpur.
|
0.5300
|
52.860
|
M/S Arif & Brothers
|
52.860
|
21/08/2019
|
20/05/2020
|
100
|
12/07/2020
|
Final Bill Paid.
|
5
|
MSRDP/S/18-19/ BC /112
|
Improvement of Chekdho Kaderpur Pucca road to bir Muktijoddha Ali Shamed house at Ch.0.00m – 290.00m. Naria Upazila, District: Shariatpur Road ID No: 386655504
|
0.2900
|
30.400
|
M/S Towa Enterprise
|
30.400
|
25/07/2019
|
24/06/2020
|
20
|
12/07/2020
|
|
6
|
MSRDP/S/17-18/BC/24
|
a) Improvement of BC Road on Kolabagan Main rpad-H/O Sohen Madbar road at Ch: 0.00 - 1121.00m Naria Upazila, Dist. Shariatpur. b) Improvement of BC Road on Nalta-Nitira road at Ch: 1000.00 - 1370.00m Naria Upazila, Dist. Shariatpur.c) Improvement of BC Road on Khathugli-Chistinagar road at Ch: 1880.00 - 3290.00m Naria Upazila, Dist. Shariatpur.
|
3.9010
|
147.753
|
M/s. Madbar Traders
|
147.753
|
27/05/2018
|
26/04/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
7
|
MSRDP/S/17-18/BC/25
|
a) Improvement of BC Road on Rahapara-Paglarmor road at Ch: 960.00 - 1730.00m Naria Upazila, Dist. Shariatpur.b) Improvement of BC Road on Gulmaize Dangar House (Chairman Bazar)-Moddho Gulmaize Govt. Pry School (Vatia Border road at Ch: 00.00 - 1200.00m Naria Upazila, Dist. Shariatpur.c) Improvement of BC Road on Garishar Paglarmore-Kolargoan GPS road at Ch: 0.00 - 325.00m Naria Upazila, Dist. Shariatpur.
|
2.2950
|
139.285
|
M/s. Almas Aaman
|
139.285
|
31/05/2018
|
30/05/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
8
|
MSRDP/S/17-18/HBB/26
|
Improvement of HBB Road on Bijhari UP-Nazirpur Ananda Bazar road at Ch: 1000.00 - 2315.00m Naria Upazila, Dist. Shariatpur.
|
1.3150
|
66.074
|
M/s. Molla Enterprise
|
66.074
|
31/05/2018
|
30/03/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
9
|
MSRDP/S/17-18/HBB/27
|
Improvement of HBB Road on Pathanbari R&H road-Char Bhojeswar road at Ch: 0.00 - 1170.00m Naria Upazila, Dist. Shariatpur.
|
1.1700
|
53.513
|
M/s. Zihad Traders
|
53.513
|
22/05/2018
|
21/02/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
10
|
MSRDP/S/17-18/BC/28
|
a) Improvement of BC Road on Sinholmuri Zora Bridge-Sinholmuri Pucca road at Ch: 0.00 - 280.00m Naria Upazila, Dist. Shariatpur.b) Improvement of BC Road on Dingamanik UP-Golar Bazar road at Ch: 2620.00 - 3805.00m Naria Upazila, Dist. Shariatpur. c) Improvement of BC Road on Anakhanda Mirachan Sadar Shop-H/O Mojammal Haque Choder road Ch: 00.00 -795.00m Naria Upazila, Dist. Shariatpur.
|
2.2600
|
165.242
|
M/s. Neloy Enterprise
|
165.242
|
24/05/2018
|
23/05/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
11
|
MSRDP/S/17-18/BC/29
|
a) Improvement of BC Road on Pachak Post Office-Muktijodha Sajahan Khan House road at Ch: 0.00 -600.00m Naria Upazila, Dist. Shariatpur.b) Improvement of BC Road on Ponchapolly-Gulmaize road at Ch: 810.00 - 2200.00m Naria Upazila, Dist. Shariatpur (Road ID: 386654028).
|
1.9900
|
136.127
|
M/s. Hapy Enetrprise
|
136.127
|
24/05/2018
|
23/05/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
12
|
MSRDP/S/17-18/BC/30
|
) Improvement of BC Road on Bhumkhara GPS-Choukeder Kandi road at Ch: 0.00 - 670.00m Naria Upazila, Dist. Shariatpur (Road ID: ) Improvement of BC Road on Bhumkhara GPS-Choukeder Kandi road at Ch: 0.00 - 670.00m Naria Upazila, Dist. Shariatpur . b) Improvement of BC Road on Masura H/O Dr. Abdul Jalil-H/O Ali Pada road at Ch: 0.00 - 875.00m Naria Upazila, Dist. Shariatpur.c) Improvement of BC Road on Achura H/O Rahim Khandakar-H/O Jahangir Khar road at Ch: 0.00 -300.00m Naria Upazila, Dist. Shariatpur.
|
1.8450
|
127.982
|
M/s. Arif Enterprise
|
127.982
|
17/05/2018
|
16/05/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
13
|
MSRDP/S/17-18/BC/31
|
Improvement of BC Road on Bhojeswar-Dogree R&H road at Ch: 1200.00 - 3615.00m Naria Upazila, Dist. Shariatpur.
|
2.4150
|
157.104
|
M/s. Salam Traders
|
157.104
|
22/05/2018
|
20/02/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
14
|
MSRDP/S/17-18/HBB/32
|
Improvement of HBB Road on Bhojeswar GC-Mohiskhola road at Ch: 00.00 - 490.00m Naria Upazila, Dist. Shariatpur.
|
0.4900
|
60.675
|
M/s. Jorasako International
|
60.675
|
31/05/2018
|
30/03/2019
|
0
|
09/07/2020
|
Cancel Tender.
|
15
|
MSRDP/S/17-18/BC/52
|
Part-A: Improvement of BC Shariatpur - Naria RHD road (H/O Chandani Alauddin Saiyal) - Delwar Member Hosue road at ch. 0.00 - 696.00m under Naria Upazila Dist. Shariatpur.Part-B: Improvement of HBB Dulukhanda H/O Sekender Howlader - H/O Babul Sarder road at ch. 0.00 - 705.00m under Naria Upazila Dist. Shariatpur.Part-C: Improvement of BC Maizpara road at ch. 1020.00 - 2150.00m under Naria Upazila Dist. Shariatpur.
|
1.9010
|
169.769
|
M/s. Apu Traders
|
169.769
|
14/06/2018
|
15/06/2019
|
75
|
09/07/2020
|
|
16
|
MSRDP/S/17-18/BC/53
|
Improvement of BC D.Mojibur Rahaman (Hiru Kazi) Bari Semana via D.Soharab Hossain Sorder Bari via Ahmadangar Bazar road at ch. 0.00 - 1000.00m under Naria Upazila Dist. Shariatpur.
|
1.0000
|
86.233
|
M/s. Misu Enterprise
|
86.233
|
19/06/2018
|
17/05/2019
|
75
|
09/07/2020
|
|
17
|
MSRDP/S/17-18/BC/65
|
Improvement of BC Sirangal UP Pacca (Police Shop) – Sirangal Small Bridge Road at ch 0.00 – 326.00m, School Link-120m, under Naria Upazila Dist. Shariatpur.
|
0.3260
|
19.557
|
M/s. Arohi Enterprise
|
19.557
|
22/03/2019
|
22/12/2018
|
100
|
09/07/2020
|
Final Bill Paid.
|
18
|
MSRDP/S/18-19/BC/73
|
Improvement of Masura-Koarag Road Ch. 1240m-2830m under Naria Upazila District Shariatpur .Salvage1418879 BDT,
|
1.5900
|
108.556
|
M/s. Mizan Enterprise
|
108.556
|
24/12/2018
|
23/12/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
19
|
MSRDP/S/18-19/BC/74
|
PartA Improvement of Chistenagar Pucca Road To Lalmia Madbor Idris Malot Bari Road Ch. 00m-510m PartB Construction of 1.00m1.00m RCC U-Type Drain 255m on Sureswar Dorbersorif under Naria Upazila District Shariatpur ..
|
0.5100
|
115.622
|
M/s. Lajuki Fashin Mela
|
115.622
|
24/12/2018
|
23/12/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
20
|
MSRDP/S/18-19/BC/Maint-06
|
Part-01 Maintenance of Munsir More Dhalir More Road Ch. 0.00km 1020km by BC under Naria Upazila Dist. Shariatpur Part-02 Maintenance of Ponchopolly-Telipara Road Ch. 1240km 2930km by BC under Naria Upazila Dist. Shariatpur , Part-03 Maintenance of Bhumkhara Chakda- Kadamtala Bazar via Nayakandi Road from Ch. 0.00km 2460km by BC under Naria Upazila Dist. Shariatpur , Part-04 Maintenance of Rajnagar UP-Budair hat Road from Ch. 0.00km 2320km by BC under Naria Upazila Dist. Shariatpur Part-05 Maintenance of Puragacha Road from Ch. 0.00km 1115km by BC under Naria Upazila Dist. Shariatpur Part-06 Maintenance of Golmaiz abbasia- Darul Karar Society Road from Ch. 0.00km 410km by BC under Naria Upazila Dist. Shariatpur , Part-07 Maintenance of Kathogly-Chisty Nagar road from Ch. 0.00km 1787km & 3290.00km-3836.00km by BC under Naria Upazila Dist. Shariatpur Part-08 Maintenance of Nalta-Sanda Road from Ch. 0.00km 1500km by BC under Naria Upazila Dist. Shariatpur Package No. MSRDP/S/18-19/BC/Maint-06
|
12.8480
|
292.790
|
m/s jamuna enterprise
|
292.790
|
19/02/2019
|
17/09/2019
|
98
|
09/07/2020
|
|
21
|
MSRDP/S/18-19/BC/109
|
1)Improvement of Nasason- Akankandi road at Ch.0.00m – 1200.00m by BC road (2) Construction of RCC Box Culvert (2x4.00mx4.50m) Ch.350.00m. under Naria, Upazila, District: Shariatpur.
|
1.2000
|
122.570
|
|
122.570
|
23/06/2019
|
31/07/2020
|
70
|
08/07/2020
|
|
22
|
MSRDP/S/18-19/BC/92
|
Improvement of Pachak Post Office – Muktijodha Sajahan Khan house Road By BC at Ch. 600.00m – 1170.00m under Naria Upazila, District: Shariatpur.
|
0.5700
|
40.400
|
M/S JARIN TRADERS
|
40.400
|
03/11/2019
|
12/10/2019
|
100
|
08/07/2020
|
Final Bill Paid.
|
23
|
MSRDP/S/18-19/HBB/93
|
Improvement of Razzak Hawlader bari to Bijhari Pancholly Pucca Road By BC at Ch. 00.00m – 565.00m under Naria Upazila, District: Shariatpur.
|
0.8000
|
59.920
|
M/S Munia Enterprise
|
59.920
|
26/02/2019
|
25/11/2020
|
100
|
08/07/2020
|
|
24
|
MSRDP/S/18-19/ HBB/96
|
Improvement of Bezari Anondo Bazar road to Kanchanpara Via Degomber Puttri govt. Primary School Road By HBB at Ch. 00.00m – 800.00m under Naria Upazila, District: Shariatpur.
|
0.8000
|
21.530
|
M/S Nur Jahan Construction
|
21.530
|
03/10/2019
|
12/09/2012
|
45
|
08/07/2020
|
|
25
|
MSRDP/S/18-19/SR/97
|
Constructioin of 2 Nos. 1x3.50mx3.50m Box Culvert on sagor Road at Ch. 375.00m & 1128m under Naria Upazila, District: Shariatpur.
|
|
22.700
|
m/s nurjahan connstruction
|
22.700
|
03/10/2019
|
08/09/2019
|
100
|
08/07/2020
|
Final Bill Paid.
|
26
|
MSRDP/S/18-19/BC/98
|
Part-1: Improvement of Naria Banglabazar- Nasasan Up Office Road By BC at Ch. 00.00m – 1332.00m (NER=15m) Effective Length=1317.00m under Naria Upazila,District:Shariatpur.Part-2: Improvement of Maizpara Road By BC at Ch. 2150.00m – 3290.00m by BC under Naria Upazila, District: Shariatpur.Part-3: Constructioin of RCC Box Culvert (2x4.00mx4.50) at Ch. 2557.00m under Naria Upazila, District: Shariatpur.
Part-4: Constructioin of RCC Box Culvert (2x4.00mx4.50) at Ch. 3280.00m under Naria Upazila, District: Shariatpur.
|
2.4720
|
215.300
|
Mohammad Younus and brathers
|
215.300
|
03/06/2019
|
02/06/2020
|
75
|
08/07/2020
|
|
27
|
MSRDP/S/18-19/HBB/99
|
Part-1: Improvement of Bhojeswar- Mohiskhola road to dosai howlader Kandi by HBB road at Ch. 00.00m – 1645.00m under Naria Upazila, District: Shariatpur.Part-2: Constructioin of RCC Box Culvert (1x3.50mx3.50) at Ch. 1440.00m under Naria Upazila, District: Shariatpur.Part-3: Improvement of GC (Mulpara) – Japsa road at Ch.6500.00m – 8500.00m by HBB under Naria Upazila, District: Shariatpur.4Part-4: Construction of RCC Box Culvert (1x3.50mx3.50) at Ch. 7600.00m under Naria Upazila, District: Shariatpur
|
3.6450
|
200.370
|
M/S Jamuna Enterprise
|
200.370
|
27/06/2019
|
26/06/2020
|
40
|
08/07/2020
|
|
28
|
MSRDP/S/17-18/BC/105
|
Part-1: Improvement of Laxmipur- Vanopa Bazar Road at Ch.0.00m – 1000.00m. under Naria, Upazila, District: Shariatpur. Part-2: Improvement of Gourango – Sreeangar Road at Ch. 0.00m – 693.00m & Ch. 1930.00m – 2700.00m. under Naria, Upazila, District: Shariatpur.Part-3: (A) Improvement of Andermanik Bazaar to Punikhar Kandi via Akber Chairman House road at Ch.0.00m – 1380.00m by BC Road. (B) Construction of RCC Box Culvert (1x3.50mx3.50m) Ch.516.00m. under Naria, Upazila, District: Shariatpur.Part-4: Construction of RCC Box Culvert (2x4.00mx4.00m) Khathugli- Chistinagar bc road at Ch.2367.00m Under Naria. Shariatpur.
|
2.4630
|
297.660
|
M/s Shamim Enterprise.
|
297.660
|
03/06/2019
|
02/06/2020
|
90
|
08/07/2020
|
|
29
|
MSRDP/S/17-18/SR/111
|
Part-A: Construction of Approach road including 9.00m high reinforced earth (RE) Wall of 99.00m long PC girder on Bhojeswar-Mohiskhola road over Kirtinasa river under Naria Upazila, District: Shariatpur.Part-B: Construction of Approach road 99.00m long PC girder on Bhojeswar-Mohiskhola road over Kirtinasa river under Naria Upazila, District: Shariatpur.
|
|
1321.040
|
Dard engineering ltd
|
1321.040
|
25/07/2019
|
24/06/2020
|
22
|
08/07/2020
|
|
|
6
|
Shariatpur-s
|
1
|
MSRDP//18-19/SR/122
|
Part-1: Construction of 20.0m long RCC Girder Bridge on Chikondi UP Office to Gonganagar GC via West Atpara Bazar Road at Ch.110.00m. under Sadar Upazila, District: Shariatpur (Road ID No: 386693023).
Part-2: Construction of 20.0m long RCC Girder Bridge on Chikondi UP Office to Gonganagar GC via West Atpara Bazar Road at Ch.1900.00m. under Sadar Upazila, District: Shariatpur (Road ID No: 386693023).
|
|
411.880
|
M/S Sheikh Enterprise
|
411.880
|
01/04/2020
|
01/09/2021
|
100
|
14/07/2020
|
Final Bill Paid
|
2
|
MSRDP//18-19/SR/121
|
Part-1: Construction of 42.0m long RCC Girder Bridge on Subachani Hat (UZR) – Tolatala Bazar (UZR) Road at Ch.2780.00m. under Sadar Upazila, District: Shariatpur.Part-2: Construction of 30.0m long RCC Girder Bridge on Chitolia GPS Union Road to Taker Hat Tumchar Akon Bari Road At Ch.2150.00m. under Sadar Upazila, District: Shariatpur.
|
|
710.210
|
m/s Hamim International
|
710.210
|
01/04/2020
|
01/10/2021
|
0
|
12/07/2020
|
|
3
|
MSRDP/S/18-19/ BC /113
|
Part-1-Construction of 1x4.50mx.00m.RCC Box Culvert W 4.88m & WW 3.40m on Kasipur Nesaria Dakhil Madrasa to Shil Dangi Road at ch.825.00m under Sadar Upazila Dist. Shariatpur.Part-2- Improvement of 300.00m Flexible pavement of Binodpur UP- Nilkuthi Bazar via Mahmudpur & Kodomtali GPS road at Ch.6386.00m-6686.00m under Sadar, Upazila, District: Shariatpur.
|
0.3000
|
43.390
|
M/S Diba Enterprise
|
43.390
|
25/06/2019
|
24/12/2019
|
100
|
12/07/2020
|
|
4
|
MSRDP/S/17-18/BC/13
|
Improvement of BC road from Char Sonamukhi boroi Tala Bridge (UZR- 2005)- Monohar Bazar Cattle Hat road at ch. 00.00 - 1000.00m.
|
1.0000
|
73.850
|
M/s. Foysal Enterprise
|
73.850
|
30/05/2018
|
29/05/2019
|
70
|
09/07/2020
|
Final Bill Paid.
|
5
|
MSRDP/S/17-18/BC/14
|
Improvement of BC road from Ghoraghat (UZR) - Parchim Sonamukhi Mia Chan Bepari UNR Via parchikm sonamukhi GPS road at ch. 00.00 - 550.00m.
|
0.5500
|
41.076
|
M/s. Delwar Hossain & Co.
|
41.076
|
30/05/2018
|
28/02/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
6
|
MSRDP/S/17-18/BC/33
|
Improvement of BC Road on Charar Kandi - GCCR road at Ch. 0.00 - 1522.00m under Sadar Upazila Dist. Shariatpur.
|
1.5220
|
126.941
|
M/s.Nazma Enterprise
|
126.941
|
20/05/2018
|
19/05/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
7
|
MSRDP/S/17-18/BC/50
|
Improvement of BC Charushandi Embankment road at ch. 1000.00 - 5500.00m under Sadarpazila Dist. Shariatpur,
|
4.5000
|
309.548
|
M/s. Sheikh Enterprise
|
309.548
|
23/07/2018
|
22/11/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
8
|
MSRDP/S/17-18/BC/51
|
Improvement of BC Kashipur - Tumchar via Samitir Bazar road at ch. 0.00 - 2555.00m & Construction of 2x4.5x4.5m RCC Box Culvert at Ch. 1440.00m & Construction of 1x0.90x1.20m U-Drain on the Same road under Sadar Upazila Dist. Shariatpur.
|
2.5550
|
223.064
|
M/s. Mayer Doa
|
223.064
|
27/06/2018
|
24/09/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
9
|
MSRDP/S/17-18/BC/59
|
Part-1-Improvement by BC of Kasipur Nesaria Dakhil Madrasa to Shil Dangi Road at ch. 0-00-1000 under Sadar Upazila Dist. Shariatpur. Part-2-Improvement by BC of Tulatala to Surjamoni Bazar Road at ch.0.00-788 under Sadar Upazila Dist. Shariatpur.
|
1.7780
|
131.964
|
M/s. Zihad Traders
|
131.964
|
17/06/2018
|
15/05/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
10
|
MSRDP/S/17-18/BC/60
|
Improvement by BC of Vasanchar Launchghat to Mokbul Sadar House Road at ch. 0-00-2000 under Sadar Upazila Dist. Shariatpur .
|
2.0000
|
144.479
|
M/s. Nilima Construction
|
144.479
|
27/06/2018
|
26/04/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
11
|
MSRDP/S/17-18/BC/61
|
Improvement by BC of Subachani hat (UZR)-Tolatala Bazar (UNR) Road at ch.2038-3808 under Sadar Upazila Dist. Shariatpur.
|
1.7700
|
15.843
|
M/s. Noor Trading
|
15.843
|
27/06/2018
|
26/04/2019
|
100
|
09/07/2020
|
Final Bill Paid.
|
12
|
MSRDP/S/17-18/BC/62
|
Improvement of Flexible Pavement of Angaria UP- Tekerhat Bazar via Chiutulia UP road at ch 2860.00 – 5480.00m under Sadar Upazila Dist. Shariatpur.
|
2.6200
|
152.163
|
M/s. Mridha Traders
|
152.163
|
07/08/2018
|
07/08/2019
|
100
|
08/07/2020
|
Final Bill Paid.
|
13
|
MSRDP/S/17-18/BC/63
|
Part-1: Improvement Flexible Pavement Road from Tulatala bazaar (Saw mill)- Madaripur Dristrict Border (Kader sarder bari) road by BC ch .1400.00 – 1800.00m under Sadar Upazila Dist. Shariatpur.Part-2: Improvement Flexible Pavement on Dadpur Lunch Ghat-Luxmipur road at ch .1000.00 – 1415.00m under Sadar Upazila Dist. Shariatpur.Part-3: Construction of 2x4.50x4.00m RCC Box Culvert on Dewbogh bottola (UZR) – Pourshava Border via Soban sardar Bari Road at Ch: 1350.00m under Sadar Upazila Dist. Shariatpur, .
|
4.0000
|
107.509
|
M/s. Neloy Enterprise
|
107.509
|
30/07/2018
|
29/06/2019
|
100
|
08/07/2020
|
Final bill paid.
|
14
|
MSRDP/S/17-18/SR/64
|
Part-1: Construction of 1x4.50mx4.00m RCC Box Culvert on Dewbogh Bottola (UZR) – Pourshava Border via soban Sardar Bari at ch 700.00m.
Part-2: Construction of 2x4.50x4.00m RCC Box Culvert on Dewbogh bottola (UZR) – Pourshava Border via Soban sardar Bari Road at Ch: 1350.00m under Sadar Upazila Dist. Shariatpur.
|
1.3000
|
109.524
|
Abdul Rob Molla
|
109.524
|
09/12/2018
|
08/12/2019
|
100
|
08/07/2020
|
Final Bill Paid.
|
15
|
MSRDP/S/17-18/ BC /72
|
Improvement of Munshi kandi Bridge (UNR road) – Rashid Kha Kandi road Ch.0.00m – 536m. & Const. of 1x4.50x4.50m RCC Box Culvert at Ch. 200.00m on the same road.
|
0.5360
|
65.890
|
M/s.Rafiqul Islam Milton Pahar
|
65.890
|
10/10/2018
|
14/01/2020
|
100
|
08/07/2020
|
Final bill Paid.
|
16
|
MSRDP/S/18-19/ BC/ 79
|
Part-1: Improvement of 910.00m Flexible Pavement of Ghoraghat (UZR)- Ojakandi (UNR) Road [Sonamukhi Embackment]. at Ch.5080.00m – 5990.00m under sadar Upazila, District: Shariatpur Road ID No: 386694007).
Part-2: Improvement of 770.00m Flexible Pavement Burirhat GC – Damudya Bourder via Chandonkor GPS Road Ch.0.00m –770.00m under sadar Upazila, District: Shariatpur.
|
1.6800
|
132.538
|
m/s sohel enterprise
|
132.538
|
23/01/2019
|
22/11/2019
|
100
|
08/07/2020
|
Final bill paid.
|
17
|
MSRDP/S/18-19/ BC/ 80
|
Part-1: Detail Estimate for Flexible Pavement of Gazar Bazar (UNR) Mollah Bari Mosque Road from Ch.0.00m –860.00m under sadar Upazila, District: Shariatpur.Part-2: Detail Estimate for Flexible Pavement of Kashipur Hindupara GPS- Takerhat R& H Road from Ch.0.00m –465.00m under sadar Upazila, District: Shariatpur.
|
1.3250
|
97.110
|
m/s foisal enterprise
|
97.110
|
15/01/2019
|
14/01/2020
|
55
|
08/07/2020
|
|
18
|
MSRDP/S/18-19/ BC /101
|
Part-1: Improvement of 2325.00m Flexible Pavement of Chitalia UP- Mohamadpur UP road Ch.1010.00m – 3360.00m & Const. of 2x4.50mx4.50m (Road way=4.88m,Wing wall =5.20m) at Ch. 2092.00m same road under Sadar, Upazila, District: Shariatpur Road.Part-2: Improvement of 2988.00m Flexible Pavement of Shamitir bazaar- Nilkuthi Road Ch.0.00m – 3000.00m. Part-3: Construction of 2x4.50mx4.00m RCC Box Culvert (W=4.88m & WW=5.20m) on Shamitir bazaar- Nilkuthi Road at Ch.2323.00m, under Sadar, Upazila, District: Shariatpur.
|
5.3200
|
502.210
|
m/s sheikh enterprise
|
502.210
|
30/05/2019
|
|
70
|
08/07/2020
|
|
19
|
MSRDP/S/18-19/BC/102
|
Part-1: Improvement of 4190.00m Flexible Pavement of Chaikandi up office – Gonganagar GC via Parchim Atpara Bazar road Ch.3000.00m – 7200.00m & 1No Stucture of Same road at Ch.4500.00m Chainange under Sadar, Upazila, District: Shariatpur.Part-2: Improvement of 2006.00m Flexible Pavement of Barail – Guschgram road Ch. 0.00m – 2022.00m & 4 No Stucture of Same road at Different Chainange, under Sadar, Upazila, District: Shariatpur.
|
6.2220
|
596.470
|
Liton traders
|
596.470
|
03/06/2019
|
30/06/2019
|
72
|
08/07/2020
|
|
20
|
MSRDP/S/18-19/ BC /104
|
Part-1: Detail Estimate for 120.00m Flexiable pavement (Ch. 1415.00m-1535.00m) on Dadpur Launch Ghat- Luxmipur road By Bituminous Carpeting under Sadar Upazila District Shariatpur.(386694004)
Part-2: Construction of 2.00 Nos 1x4.00x4.00m RCC Box Culvert on Janjira – Naria Sureswar Road At Ch.632m. & 1868m. (386652006).
|
0.1200
|
68.330
|
m/s said steel king
|
68.330
|
24/04/2019
|
23/01/2020
|
100
|
08/07/2020
|
|
21
|
MSRDP/S/18-19/BC/108
|
Part-A: Detail Estimate for Flexible pavement Kancharikandi (UZR) – Majumderkandi (UNR) road from Ch. 2820.00m – 3730.00m under Sadar, Upazila, District: Shariatpur. Part-B: Construction of U- Drain on Kancharikandi (UZR) – Majumderkandi (UNR) road at Ch.3512.00m under Sadar, Upazila, District: Shariatpur.
|
0.9100
|
69.150
|
M/s Jihad Traders
|
69.150
|
24/04/2019
|
23/01/2019
|
100
|
08/07/2020
|
Final bill Paid.
|
22
|
MSRDP/S/
18-19/ BC /77
|
Improvement of 1384.00m Flexible Pavement of Sundissar UNR- Guripara GPS via Abu Taleb Master High School road Ch.0.00m – 1392.00m & 2(Two) nos ÒU” Drain at Ch.650.00, Ch.1385.00 under sadar Upazila, District: Shariatpur.
|
1.3920
|
105.428
|
|
105.428
|
|
|
0
|
19/01/2019
|
NOA Issued
|
|
Total :
|
275.1230 (Km)
|
18101.24 (Lac)
|
18101.24 (Lac)
|
|
|
|
|
|
|