Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bhaluka
1 CRMIDP/MYM/W-256 Mahmudpur Bazar 184.000 Maliha Trade International 184.000 31/08/2022 80 26/07/2022
2 Dhobaura
1 CRMIDP/MYM/W-255 Sharuapara Bazar 255.000 KK Enterprise-BAK construction 255.000 02/04/2022 15/05/2022 10 26/07/2022
3 Fulbaria
1 CRMIDP/MYM/W-253 Babugonj Bazar 310.000 M/S Surma Engineering works 310.000 20/03/2022 20/09/2022 48 26/07/2022
4 Gouripur
1 CRMIDP/MYM/W-251 Pahsar Bazar 216.000 "M/S Mahbub Enterprise 35, Sahab Ali Road Nutun Bazar, Mymensingh " 216.000 24/07/2022 45 26/07/2022
5 Haluaghat
1 CRMIDP/MYM/W-250 Baghitola Hat 326.000 M/S Jerin Enterprise 326.000 03/07/2022 60 26/07/2022
6 Nandail
1 CRMIDP/MYM/W-248 Kali Bazar 207.000 "Noor Hossain-Snaha Enterprise (JV) 105/B, D.B.Raod. Sadar Mymensingh " 207.000 04/07/2022 70 26/07/2022
7 Phulpur
1 CRMIDP/MYM/W-247 Boula Bazar 213.000 "Noor Hossain-Snaha Enterprise (JV) 105/B, D.B.Raod. Sadar Mymensingh " 213.000 04/07/2022 50 26/07/2022
8 Tarakanda
1 CRMIDP/MYM/W-258 Tarakanda Dokkhin Bazar 188.000 SE & EET (JV), Bagmara, Mymensingh Sadar, Mymensingh 188.000 30/11/2020 60 26/07/2022
9 Trishal
1 CRMIDP/MYM/W-249 Danikhola Bazar 205.000 M/S Surma Engineering works 205.000 06/09/2022 45 26/07/2022
Total : 0.0000 (Km) 2104.00 (Lac) 2104.00 (Lac)