Loading...

Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bhandaria
1 CRMIDP/PRIP/W-228 Junia Khabiruddin Hat 321.000 EFTE.ETCL (PVT.) LIMITED Bhandaria, Pirojpur 321.000 04/07/2022 95 26/07/2022
2 Nazirpur
1 CRMIDP/PRIP/W-232 Babur Hat 330.000 Shimran Mayan Trade 330.000 28/06/2021 50 26/07/2022
Total : 0.0000 (Km) 651.00 (Lac) 651.00 (Lac)