Loading...

Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Sreepur
1 CRMIDP/MGR/W-175 Bhabonhati Bazar 247.000 KMR-PK(JV) 247.000 08/12/2021 04/07/2022 65 26/07/2022
Total : 0.0000 (Km) 247.00 (Lac) 247.00 (Lac)