Loading...

Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Biswamvarpur
1 CRMIDP/SNMG/W-387 Currenter Bazar 247.000 "M/S Marina Construction Associates Ltd Dhaka " 247.000 27/07/2022 87 27/07/2022
2 Chatak
1 CRMIDP/SNMG/W-388 Mohammadganj Bazar 341.000 M/S G.I Trading & Co. 341.000 15/01/2022 20 27/07/2022
3 Doarabazar
1 CRMIDP/SNMG/W-391 Bongobondhu Bazar 457.000 M.I Trading & Co 457.000 28/02/2022 15 27/07/2022
4 Shantiganj
1 CRMIDP/SNMG/W-396 Vomvomi Bazar 23.000 "RR-AE (JV) Sunamganj 01712393624 " 23.000 26/06/2022 76 27/07/2022
Total : 0.0000 (Km) 1068.00 (Lac) 1068.00 (Lac)