Loading...

Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Banskhali
1 WD-CHITTA-BANSKHALI/W-01 Development of Gondamara Bridge to Gondamara Power Plant Connecting Road (2-Lane Road with 4-Lane Structure Including Sub-GradeImprovement by PVD & other ancillary Works) 2.5200 2013.510 M.A.H Construction Ltd-M/s J K Enterprise (jv) 2013.510 30/03/2021 70 03/01/2021
Total : 2.5200 (Km) 2013.51 (Lac) 2013.51 (Lac)