Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Barura
1 FDR/Cum/18-19/UNR/W02 Rehabilitation of Galimpur UP Office-Paranpur bazar Road from Ch. 0m-2600m 2.6000 101.144 M/S Shanto Construction 101.144 30/10/2018 03/06/2019 100 25/08/2020 Final Bill Paid
2 Brahmanpara
1 FDR/Cum/18-19/UZR/W13 Rehabilitation of Brahmanpara-Dulalpur GC Road from Ch. 0m-5073m. 5.0730 92.477 M/S Badsha Enterprise 92.477 25/04/2019 23/07/2019 100 27/08/2020 Final Bill Paid
2 FDR/Ban/18-19/UNR/W04 Rehabilitation of Brahmanpara UP office-Harimongal bazar Road from Ch. 0m-4530m. 4.5300 128.412 M/S E.F Trade International 128.412 27/01/2019 12/06/2019 100 25/08/2020 Final Bill Paid
3 Chandina
1 FDR/Cum/18-19/UZR/W11 Rehabilitation of Ranichara-Bangla Bazar Fawai Road from Ch. 0m - 12824m.` 12.8240 674.851 M/S R-TA Enterprise 674.851 14/04/2019 13/10/2019 100 27/08/2020 Final Bill Paid
4 Chouddagram
1 FDR/Cum/18-19/VR/W03 Rehabilitation of Dhaka Ctg.Trank Road(Nalbag)-Samukshar - Dolshamudra Jola Road from Ch. 0m - 2148m 2.1480 102.793 M/S Mozumder Trades 102.793 23/10/2018 03/10/2019 100 25/08/2020 Final Bill Paid
5 Cumilla-s daksin
1 FDR/Cum/19-20/UZR/W06 Rehabilitation of Rajeshpur - Kamalpur - Nalkuri - Matriara - Srimantapur - Chandpur Road from Ch. 19405m-24400m 4.9950 274.743 M/S Nur Enterprise & Sikder Construction JV 274.743 02/09/2019 01/01/2020 40 25/08/2020 Time Expired
6 Daudkandi
1 FDR/Cum/18-19/UNR/W05 Rehabilitation of Barkota-mohammadpur paschim Upoffice-baynagar pry school road from Ch 0m - 3500m 3.5000 153.953 M/S R-TA Enterprise 153.953 12/02/2018 12/08/2019 100 25/08/2020 Final Bill Paid
7 Debidwar
1 FDR/Cum/18-19/UZR/W07 Rehabilitation of Birallah RHD to Dhampti Hat GC Road from Ch 0m - 7630m. 7.6300 648.312 M/S Pioneer Construction & M/S Sumi Enterprise(JV) 648.312 03/03/2019 02/08/2019 100 27/08/2020 Final Bill Paid
2 FDR/Cum/18-19/UZR/W01 Rehabilitation of Kuruin RHD to Mohonpur GC Road from Ch. 0m-1330m. 1.3300 87.000 M/S. Sumi Enterprise 87.000 24/09/2018 30/03/2019 100 25/08/2020 Final Bill Paid
8 Lalmai
1 FDR/Cum/20-21/UNR/W17 Rehabilitation of Birza Bazar - Foyjgonj Road from Ch 0m-760m 0.7600 64.004 64.004 0 27/08/2020 Evaluation under process
2 FDR/Cum/20-21/UNR/W16 Rehabilitation of Darbeshpara Bazar - Gayerbanga - Palpara - Parati Bazar Road from Ch. 0m-4040m 4.0400 196.699 196.699 0 27/08/2020 Technical Evaluation ongoing
9 Monohorganj
1 FDR/Cum/19-20/UNR/W15 Rehabilitation of Tuguria-Munshirhat Road from Ch. 0m-3985m 3.9850 300.735 M/S. Farhana Builders 300.735 05/12/2019 04/05/2020 100 27/08/2020 Final Bill Paid
2 FDR/Cum/19-20/UNR/W14 Rehabilitation of Monohorgonj H/Q - Sorospur UP Road via Betiapara,Vatkor,Sahapur Road from Ch. 2000m-4915m. 2.9150 119.934 M/S. Shadat Traders 119.934 29/07/2019 28/11/2019 100 27/08/2020 Final Bill Paid
10 Nangalkot
1 FDR/Cum/18-19/UZR/W12 Rehabilitation of Nagalkot GC - Bangadda RHD via Sreefolia Road from Ch. 0m - 9670m 9.6700 685.954 Md. Abdur Razzak 685.954 17/03/2019 16/10/2019 100 27/08/2020
2 FDR/Cum/18-19/UNR/W08 Rehabilitation of Gomkot Dipjol Market Khatacho Patwar Omargonj Bazar Road from Ch 0m - 7830m 7.8300 273.392 M/s. Madina & Fatefma Traders 273.392 06/03/2019 02/07/2019 100 27/08/2020 Final Bill Paid
3 FDR/Cum/18-19/UNR/W10 Rehabilitation of Dhalua Bisnaour Changara Noapara Chadia Bazar Road from Ch. 0m-3000m. 3.0000 103.826 M/S Madina &Fatema Traders 103.826 03/03/2019 02/07/2019 100 25/08/2020 Final Bill Paid
4 FDR/Ban/18-19/UNR/W09 Rehabilitation of Mandra Bazar Mokora Sarkar Bazar Narandia Kankapoith Road from Ch. 4755m-7400m 2.6450 107.566 M/S Madina &Fatema Traders 107.566 03/03/2019 02/07/2019 100 25/08/2020 Final Bill Paid
Total : 79.4750 (Km) 4115.80 (Lac) 4115.80 (Lac)