Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Anwara
1 FDR/CTG/18-19/UNR/W08 Rehabilitation of Anwara Joikali GC.-Barakhain Up officel Road from Ch. 0m -990m & 1680m - 2250m 1.5600 40.051 40.051 22/04/2019 29/10/2019 100 13/09/2020
2 FDR/CTG/19-20/UZR/CW32 Construction of 2m Culvert on Hazrat Mohsin Awolia-Gahira-Fakirhat-Dhalghat Roiad at Ch. 4957m(4959m). 13.933 M/S. Anjuman Construction 13.933 26/12/2019 02/01/2021 5 11/09/2020 Very Slow Progress
3 FDR/CTG/19-20/UZR/CW31 Construction of 6m Culvert on Khaikhaine-Chamuduria-Hazrat Sha Ali Reza Rd. (Morali G hat, Chamoduria , Barkal connecting Rd) at Ch. 5880m (5886m) 34.230 M/s. Anjuman Construction 34.230 26/12/2019 02/01/2021 90 11/09/2020
4 FDR/CTG/18-19/UZR/W08 Rehabilitation of Surat bibi Masjid R&H-Rustamhat G.C Road from Ch. 0m - 4650m. 4.6500 207.741 M/s. Jashim & Brothers and M/s. Hossan & Brothers(JV) 207.741 22/04/2019 29/10/2019 96 11/09/2020 Time Expired
5 FDR/CTG/18-19/UZR/W09 Upazila H/Q (Hospital) Churamoni (Al Haj Momtaz Oli) Sattar Hat G.C Road from Ch. 0m- 5400m. 5.4000 250.431 M.A.H. Construction Ltd. 1307/2, Monipur, Mirpur, Dhaka-1216 250.431 24/03/2019 31/03/2020 95 11/09/2020 Time Expired
2 Banskhali
1 FDDRIRP/W11 Arabsha Bazar GC - Ishwar Babur Hat GC Road via Bashirullah Miazi hat Choua, Gandamara, Saral, Shadinpur UP (Moulana Ashraf Ali Road) Length 37.20km (Ch: 29724-30144m & 32779-35039m) 2.6800 120.378 The Paramount International, 438/C, Solakbahar, Panchlish, Chattagram 120.378 27/03/2019 08/02/2020 60 13/09/2020 Time Expired
2 FDR/CTG/19-20/UNR/W28 Rehabilitation of Saroatali up-Patiya ghosherhat (LM) Road (R.A Khan Road) from Ch. 0m - 1150m 1.1500 114.582 M/s. G R M Traders 114.582 14/11/2019 14/08/2020 60 11/09/2020 Time Expired
3 Boalkhali
1 FDR/CTG/19-20/UNR/W30 Rehabilitation of Shakpura Up-Noniarmar Ghat Sorf Ali Munshi Road (Shaid Dhearanda Aminul Huq Road) from Ch. 0m - 1824m; 2306m - 3092m & 3092m - 3690m (1.824m+0.786m+598m) 3.2080 174.491 M/s. Saleha and Rony JV 174.491 13/02/2020 13/11/2020 90 11/09/2020
2 FDR/CTG/19-20/UZR/W27 Rehabilitation of Upazila H/Q-Murad munshirhat GC Road from Ch. 0m-1920m 1.9200 150.364 M/s. Forak Ahmed & Sons - Rafi Enterprise (JV) 150.364 13/11/2019 13/08/2020 100 11/09/2020
3 FDR/CTG/19-20/UNR/W26 Rehabilitation of Shakpura up-Goluk munshirhat (LM) Pachim Gomdandi up Road.(Shakpura Dc Road) from Ch. 0m - 1058m 1.0580 126.672 M/s. Forak Ahmed & Sons - Rafi Enterprise (JV) 126.672 13/11/2019 13/08/2020 100 11/09/2020
4 FDR/CTG/18-19/CW02 Construction of Hajee Akmal Ali road. 8.581 M/s. Jannat Enterprise, Boalkhali, chittagong. 8.581 25/06/2018 31/12/2018 100 23/08/2020 Final Bill Paid
4 Chandanish
1 FDR/CTG/20-21/UZR/BW36 Construction of 20m Bridge on Boroma collage Dhamerhat-GC to -Moulavibazar (RHD) Road at Ch. 845m (865m) 200.211 MNK-JSE (JV) 200.211 0 11/09/2020 NOA issued
2 FDR/CTG/18-19/UNR/W09 Rehabilitation of Kanchanabd Up- Shabandandi up-Morali hat Road from Ch. 0m - 1130m 1.1300 70.500 M.A.H. Construction Ltd. 1307/2, Monipur, Mirpur, Dhaka-1216 70.500 24/03/2019 31/03/2020 100 11/09/2020 Time Expired
5 Fatikchari
1 FDR/CTG/20-21/UNR/CW16 Construction of 28m Culvert on Bibirhat G.C.to Kanchurhat Road via North Rangmatia Natun Bazar Road at Ch. 5100m (5128m) 223.327 SA-HB-MB-JV 223.327 0 11/09/2020 NOA issued
2 FDR/CTG/19-20/UNR/W15 Rehabilitation of Bibirhat G.C.to Kanchurhat Road via North Rangmatia Natun Bazar Road from Ch. 1637m - 5280m 3.6430 260.585 M/s. Mohsin - S Hoque (JV); Uttar Haid Chakia 260.585 06/11/2019 06/04/2020 60 11/09/2020 Time Expired
6 Hathazari
1 FDR/CTG/20-21/UZR/W33 (a) Rehabilitation of Khatirhat RHD to Takirhat GC Road (Katirhat-Takirhat Road) from Ch. 0m - 2470m; (b) Construction of 2x4.5x4.5m RCC Box Culvert at Ch 2253m(2262m) 2.4790 229.026 Sahensha & Brothers (JV) 229.026 0 11/09/2020 NOA issued
2 FDR/CTG/19-20/UZR/W29 Rehabilitation of Nazu Mea Hat GC to Chittagong Hathazari RHD Road (Aman Bazar-Nayamat Ali Road) from Ch 2370m - 4990m. 2.6200 233.585 M/s. J.B International 233.585 19/01/2020 10/10/2020 0 11/09/2020 Very Critical
7 Mirsharai
1 FDR/CTG/18-19/UZR/W03 Rehabilitation of Nizampur R&H to Shaerherkhali R&H via Borerhat GC Road from Ch. 2750-6600m 3.8500 143.739 M/s. Shajahan Construction, Middle Mogadia, Miresarai, Chittagong. 143.739 30/07/2018 06/02/2019 100 13/09/2020 Final Bill Paid
2 FDDRIRP/W10 Mirsharai UP R&H Sufia Bazar Via Sufia Mazar Road (Ch: 00-1000m & 2100-5100) 4.0000 244.678 The New Trade Link; Antapur, Parashuram, Feni 244.678 01/05/2019 28/02/2020 100 13/09/2020
3 FDR/CTG/18-19/CW05 Construction of Nizampur R&H to Shaherkhali R&H via Damdama Bazar and Bhorerhat GC (Oli Ahmed Abdur Rahman Road) (3 Culverts= 3+3+2=8m) 42.090 M/s. Khaja Ajmiri Enterprise, Eidgoun Road, Bibirhat, Fatikchari, Chattagram. 42.090 16/09/2018 23/01/2019 100 14/10/2019 Time Expired. 28 Days Letter issued.
8 Patiya
1 FDR/CTG/19-20/UZR/W24 Rehabilitation of Amjurhat ( RHD) - Kasturight ( RHD) Anower Upazila Via Asia Up (Bipin Behari Nandi Road) Road from Ch. 0m - 5400m. 5.4000 479.288 M/s. Shah Jabbaria Construction- J S Enterprise (JV 479.288 23/10/2019 23/07/2020 40 11/09/2020 Time Expired
2 FDR/CTG/19-20/UZR/W25 Rehabilitation of Olir Hat G.C-Bathua Tangarpool Kasturighat (RHD) Connecting Road ( Chanhara Idris MiaRoad) from Ch. 2400m - 5755m 3.3550 117.682 M/s. Shah Jabbaria Construction- J S Enterprise (JV) 117.682 23/10/2019 23/07/2020 10 11/09/2020 Time Expired
9 Rangunia
1 FDR/CTG/19-20/VR/BW23 Construction of 15m Bridge on RHD Sisutal -Sonargaon High School. - Rafique Miahar Fram (Sonargaon Road) Road at Ch. 85m (100m) 153.801 M/S. Bengal Trading Agency 153.801 07/07/2019 07/07/2020 100 13/09/2020
2 FDR/CTG/20-21/VR/BW37 Construction of 15m Bridge on Kulkurmai Road(College Gate-Moriom Nagar D.C Road at Ch. 395m (410m). 198.406 M/S Bengal Trading Agency 198.406 0 11/09/2020 NOA issued
3 FDR/CTG/18-19/CW05 Construction of RHD Brammon Ghat - Darikope High School- Chipchari Pekua Fruits Farm (Darikope Road) Road at Ch. 310m (322) & 1380m (1389m) (Culvert= 12+9=21m) 86.000 M/s. Ridwanul Hoque & Brothers, Raja Sarder Road, Shelaigora, Anowara, Chattagram 86.000 17/01/2019 17/08/2019 100 11/09/2020 Final Bill Paid
4 FDR/CTG/18-19/BW01 Construction of Katakhali Bridge-Chandraghona Up (Katakhali Old Road) 132.480 M/s. Abhi Enterprise, Betagi, Rangunia, Chittagong. 132.480 20/03/2018 27/03/2019 97 23/08/2020 Time Expired
10 Raojan
1 FDR/CTG/20-21/UNR/BW39 Construction of 25m Bridge on Chittagong Kapaty(R&H)Road –Moulana Mohmed Sha Mazar(via Kachukhain Bazar)Road at Ch. 1000m (1025m) 262.469 262.469 0 11/09/2020
2 FDR/CTG/20-21/UNR/BW35 Construction of 6m Bridge on Chittagong Kapty (R&H) R0ad At Bajja Khali Gate - Weat Guzra UP (Via Bajja Khali Bazar)(Anderson Road) Road at Ch. 5800m (5806m) 540.765 M/S. A. Ali Chowdhury 540.765 0 11/09/2020 NOA issued
3 FDR/CTG/19-20/VR/BW19 Construction of 15m Bridge on Gohira (R & H) Hathazari (Khan Bahadur Abdul Jabbar Road-1, Khan Bahadur Abdul Jabbar Road-2, Kagotia (LM) via Sonair Muck Road at Ch. 1100m (1115m) 138.326 M/S. K P Enterprise 138.326 24/09/2019 24/09/2020 80 11/09/2020
4 FDR/CTG/19-20/VR/BW18 Construction of 20m Bridge on From Dost Mohammed Road(UZR)-Akbar Sha (UNR)Road at Gonir Ghat(Md.Amir road) Road at Ch. 2100m (2120m) 145.401 M/s. Chowdhury Enterprise 145.401 15/04/2019 22/04/2020 90 11/09/2020 Time Expired
5 FDR/CTG/19-20/VR/CW04 Construction of 2m Culvert on Binajuri Jarul Tola Road(Raojan Section-2 Road-Lalangara Road) at Ch. 998m (1000m) 12.996 12.996 21/04/2019 28/09/2019 100 11/09/2020
6 FDR/CTG/18-19/VR/CW14 Construction of 1x3.00mx3.00m Culvert on Hamid Ali bari Road(Samid & Co.) Road at Ch. 910m (913m) 20.571 M/S S M Trading 20.571 26/02/2019 05/06/2019 100 11/09/2020 Final Bill Paid
7 FDR/CTG/18-19/VR/CW13 Construction of 1x3.00mx3.00m Culvert on Kabir Ahmed Talikdar road(Gohira) at Ch. 940m (943m) 20.571 M/s. S M Trading 20.571 26/02/2019 05/06/2020 100 11/09/2020 Final Bill Paid
8 FDR/CTG/20-21/UNR/W38 Rehabilitation of Urkirchar UP HQ-Urkirchar Bazar via Khalifarghona Road (Dhaka Khali Khalifarghona Road) from Ch. 0m - 4000m 4.0000 532.012 Hassan & Brothers & Baizid Enterpris (JV) 532.012 0 11/09/2020 NOA issued
9 FDR/CTG/19-20/UNR/W22 Rehabilitation of Chikdair UP Office - Maddya Pattanpara - Kagotia Hat( R&H) Road Via Kundessari Road from Ch. 4440m -8090m. 3.6500 490.828 Tajwar Trade Systems Limited & M/s. Baizid Enterprise (JV) 490.828 05/11/2019 05/08/2020 15 11/09/2020 Time Expired
10 FDR/CTG/19-20/UZR/W21 Rehabilitation of Gohira (R&H) - Halda Ghat at Hatajari ( Khan Bahadur Abdul Jabbar Road.-1) (From RHD #100) Road from Ch. 1600m - 2700m 1.1000 169.242 Tajwar Trade Systems Limited & M/s. Baizid Enterprise (JV) 169.242 05/11/2019 05/08/2020 15 11/09/2020 Time Expired
11 FDR/CTG/19-20/UNR/W20 Rehabilitation of Amir Hat G.C -Fatick Chari Upazilacanect South Kharim Road (Via Holudia UP Office) Road from Ch. 0m - 5800m. 5.8000 674.711 JJT-STN (JV) 674.711 17/07/2019 17/04/2020 50 11/09/2020 Time Expired
12 FDR/CTG/19-20/VR/W17 Rehabilitation of Kadalpur Mowlana Miskin Shaha Road from Ch. 0m - 1030m 1.0300 128.233 M/s. Padma Trade System 128.233 25/04/2019 22/02/2020 100 11/09/2020
11 Sitakunda
1 FDDRIRP/W07 Pontichicila RHD - Mirer Hat GC Road.Via maloti Pul (Bhandary Road) Road from Ch. 233-1255) 1.0220 38.138 M/s. Three Star Enterprise, Akmol Ali Road, South Halishahar, EPZ, Chattogram 38.138 30/01/2019 06/08/2019 100 13/09/2020 Work complete & Final Bill Paid
Total : 64.7050 (Km) 7231.12 (Lac) 7231.12 (Lac)