1 Chandpur-s
1 FDR/Cha/18-19/VR/W03 Rehabilitation of Harina Ferryghat - Hanarchar UP office Road from Ch. 0m-490m 0.4900 22.745 22.745 100 27/08/2020
2 FDR/Cha/18-19/UNR/W02 Rehabilitation of Shahmahmudpur U.P to Algi Rajarhat Bazar Road from Ch 0m-1823m. 1.8230 64.614 M/S. Ananto Traders 64.614 31/07/2018 30/06/2019 100 27/08/2020 Final Bill Paid
2 Faridganj
1 FDR/Cha/19-20/CW18 Construction of Rupsha GC-Chandra GC Road via Paikpara (S&N)up and Sahibazar,Banglabazar at Ch 8650m (8658) 51.463 M/S M.Ali & Co. 51.463 24/02/2020 24/05/2020 100 27/08/2020
2 FDR/Cha/18-19/UZR/W14 Rehabilitation of Rupsha GC - Polishara GC (Haziganj Upazila) via Khajuria Road from Ch. 8500m-13790m 5.2900 306.288 Ador Enterprise 306.288 04/08/2019 14/10/2019 80 27/08/2020 Preparing for Carpeting 30-11-2019
3 FDR/Cha/18-19/VR/W06 Rehabilitation of Sollabazar - Kamta Bazar via Sharbazar Road from Ch. 0m-3110m. 3.1100 140.847 M/S Contemporary & Ananto JV 140.847 14/03/2019 06/08/2019 100 27/08/2020
4 FDR/Cha/18-19/UNR/W15 Rehabilitation of Faridganj GC - Patway Bazar Road from Ch. 0m - 8350m 8.3500 372.595 M/S Aziz Brothers 372.595 22/05/2019 21/10/2019 100 27/08/2020
3 Haimchar
1 FDR/Cha/19-20/VR/W17 Rehabilitation of Gazir bazar to Rayer Bazar Road from Ch. 725m - 1334m 0.6090 17.274 17.274 15/12/2019 15/04/2020 100 27/08/2020
4 Haziganj
1 FDR/Cha/18-19/UNR/W12 Rehabilitation of Palishara Bazar to Kashimpur Bazar Road Deshgaon Road from Ch. 0m-2030m 2.0300 61.727 M/S MAE - MBC JV 61.727 15/05/2019 14/10/2019 100 27/08/2020
2 FDR/Cha/18-19/UZR/W11 Rehabilitation of Haziganj RHD to Raghunathpur GC Road from Ch. 6400m-10334m 3.9340 186.240 M/S MAE - MBC JV 186.240 15/05/2019 14/10/2019 100 27/08/2020
5 Kachua
1 FDR/Cha/18-19/UNR/W16 Rehabilitation of Pathoir Suarul Bazar Road from Ch. 0m-800m 0.8000 37.022 M/S Khan Construction 37.022 17/06/2019 16/10/2019 65 27/08/2020 Preparation for Carpeting
2 FDR/Cha/18-19/UNR/W01 Rehabilitation of Bitara UP(Majhigacha)-Ranger Bazar(Nindapur) Road from Ch. 0m-3972m. 3.9720 243.209 M/S. Jashim & Brothers 243.209 27/01/2019 24/09/2019 60 27/08/2020 Final
3 FDR/Cha/18-19/UNR/W05 Rehabilitation of Rahimanagar-Koitoba-Amujan Road from Ch 0m-3400m. 3.4000 120.949 M/S. Nur Hossain Traders 120.949 14/01/2019 11/09/2019 100 27/08/2020 Final
6 Matlab (dakshin)
1 FDR/Cha/18-19/UNR/W08 Rehabilitation of Matlab - Master Bazar - Ghosherhat Road from Ch. 0m-2290m 2.2900 118.254 M/S. Zakir Enterprise 118.254 15/01/2019 14/05/2019 100 27/08/2020 Final
7 Matlab (uttar)
1 FDR/Cha/18-19/UNR/W13 Rehabilitation of Miturkandi bazar to Dhanagoda bazar road via Baganbari UP Office road from Ch. 0m - 3680m 3.6800 187.263 M/S RK Enterprise 187.263 17/01/2019 17/05/2019 100 27/08/2020 Final
2 FDR/Cha/18-19/UNR/W10 Rehabilitation of Islamia bazar-Nowri bazar-Naborkandi-Purba Fatepur Up office Road at Nayakandi bridge from Ch. 0m-3000m 3.0000 138.873 138.873 100 27/08/2020
3 FDR/Cha/18-19/UNR/W09 Rehabilitation of Ludhua Amtala bazar-Shatnal UP Office (Kalipur) via Walipur Maradhan Road from Ch. 0m-1520m. 1.5200 77.895 MRL - OMI JV 77.895 22/01/2019 22/05/2019 100 27/08/2020 Final
8 Shahrasti
1 FDR/Cha/18-19/UNR/W04 Rehabilitation of Ferua bazar-Suchipara (s) UP office Road from Ch 0m-3972m 2.3000 104.457 M/S. Patwary Enterprise 104.457 06/01/2019 06/05/2019 100 27/08/2020 Final Bill Paid
Total : 46.5980 (Km) 2251.72 (Lac) 2251.72 (Lac)