SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Akhaura
1 FDR/Bbaria/18-19/UZR/W02 Rehabilitation of Mogra Bazar (GC) - Satpara R&H Road via Kornel Bazar, Dhaturpohela Road from Ch. 0m-7199m & 8049m - 8790m 7.9400 346.186 M/S Hasan Enterprise, TA Road 346.186 10/03/2019 04/07/2019 100 27/08/2020 Final Bill Paid
2 Ashuganj
1 FDR/BBaria/18-19/UZR/W05 Rehabilitation of Ashugonj - Talshahar Road from Ch 0m-8000m 8.0000 529.393 M/S Lokman Hossain & M/S Mostafa Kamal (JV) 529.393 23/06/2019 19/03/2020 100 27/08/2020 Variation approved. BC done & RCC going on
3 B.baria-s
1 FDR/BBari/20-21/UNR/W06 Rehabilitation of Bodal Up-Bariura bazar via Majlishpur up Road from Ch. 1400m- 7800m 6.4000 592.309 592.309 02/07/2020 02/04/2021 15 27/08/2020 Works going on
4 Kasba
1 FDR/B.Bar/18-19/UZR/W01 Rehabilitation of Kasba-Akhaura Road from Ch. 0m-7000m 7.0000 561.748 M/s. Hasan Enterprise 561.748 30/07/2018 29/07/2019 100 27/08/2020 Final Bill Paid
5 Nabinagar
1 FDR/B.Bari/18-19/UNR/W03 Rehabilitation of Barikandi Launchghat Bazar- Sreeghar GC (South of Shyamgram Road )via Barikandi UP Road from Ch. 0m-3120m 3.1200 120.464 M/S SHAHJAHAN BUILDERS, Kawtali Brahmanbaria 120.464 17/02/2019 17/06/2019 100 27/08/2020 Final Bill Paid
6 Sarail
1 FDR/BBaria/18-19/VR/W04 Rehabilitation of Baddapara - Kuchni Road from Ch. 316m - 1846m 1.5300 29.712 M/S A S Construction 29.712 26/03/2019 25/06/2019 100 27/08/2020 Final Bill Paid
Total : 33.9900 (Km) 2179.81 (Lac) 2179.81 (Lac)