Loading...

Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bamna
1 FDR/Bar/UZR/W02 Rehabilitation of Bamna GC - Kholpatua GC-Ramna Launch Ghat RHD 8.3200 560.140 M/S Poly Construction,Pro:Md babul Mia,college Road Barguna 560.140 07/09/2018 31/12/2019 80 18/08/2020 6500 BC completed
2 Barguna-s
1 FDR/Bar/19-10/UNR/W08 Rehabilitation of Fuljhuri UP-Mirer hat via Fakirbari Mardraqsha Road. 3.0000 109.020 M/S Jahanara enterprise 109.020 20/02/2020 20/07/2020 15 18/08/2020 Earth work ongoing
2 FDR/Bar/18-19/UNR/W1 Rehabilitation of Keorabunia RHD-Ghatbaria Hat-Chandukhali GC [Length=8.30km] 5.0000 217.630 M/S Mithun Traders,High School Road,barguna sadar,Barguna 217.630 13/08/2018 13/03/2019 100 18/08/2020 Final
3 Betagi
1 FDR/Bar/19-20/UZR/W06 Rehabilitation of Barguna-betagi RHD-(Tulatala mor- Fujuri GC 6.5000 282.930 M/S Abul Kalam Azad, Muslim Para, Patuakhali 282.930 25/04/2019 25/02/2020 100 18/08/2020 Final
2 FDR/Bar/18-19/UNR/W5 b) Rehabilitation of Hosnabad UPC - Kazirhat GC Road 1.0050 39.760 39.760 100 18/08/2020
3 FDR/Bar/18-19/UZR/W04 a) Rehabilitation of Betagi HQ(Bus Stand)- Niamati GC Hosnabad UPC - Kazirhat GC Road 8.0550 605.680 M/S Khan Enterprise . 605.680 12/09/2018 12/07/2019 100 18/08/2020 Final
4 Patharghata
1 FDR/Bar/18-19/UZR/W03 Rehabilitation of Munshigonj Hat (RHD)-Nali (Shaplaja GC) Via Charduani GC. 9.0000 385.038 M/S Poly Construction,Pro:Md babul Mia,college Road Barguna 385.038 13/08/2018 13/04/2019 100 18/08/2020 Final
5 Taltali
1 FDR/Bar/19-10/UZR/W07 Rehabilitation of Kachupatra GC-Bogirhat GC via Panchakoralia Bazar Road 0.9700 38.390 Rezowanul Maksud 38.390 13/12/2019 13/04/2020 100 18/08/2020
Total : 41.8500 (Km) 2238.59 (Lac) 2238.59 (Lac)