Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Kaliakoir
1 FDR/Gaz/18-19/UNR/W07 Rehabilitation of Mouchak UP - Kamarpara Bazar via Lashkarchala nBazar, Mazukhan Bazar Road from 1700m - 8243m 6.5430 510.820 Dolly Construction Ltd 510.820 17/04/2019 17/09/2019 35 13/09/2020 Time Expired
2 FDR/Gaz/18-19/UZR/W04 Rehabilitation of Baraipara (NHW) - Chandabaha GC Road from Ch. 0m - 4315m 4.3150 517.868 M/S Kohinoor Enterprise & Orient Trade International (JV) 517.868 05/02/2019 30/07/2019 100 13/09/2020
3 FDR/Gaz/18-19/UZR/W03 Rehabilitation of Kaliakoir G.C(R&H) - Vowel Mirzapur G.C. via Boraibari Road from Ch. 6700m - 15330m 8.6300 869.413 M/S Dhiman COnstruction 869.413 25/02/2019 25/08/2019 90 13/09/2020 Time Expired
4 FDR/Gaz/20-21/UNR/W09 Rehabilitation of Boardghar UP - Dariapur Bazar Road from Ch. 0m - 3300m 3.3000 574.325 574.325 0 11/09/2020 Tender will be received on 01/09/2020
2 Kaliganj
1 FDR/Gaz/20-21/UNR/W08 Rehabilitation of Tomulia UP H/Q - Bortul Bazar Road Via Bangabandhu Bazar Road from Ch. 0m - 5850m. 5.8500 804.408 Probal Engineers 804.408 01/07/2020 05/03/2021 11 13/09/2020 Progress Slow
3 Kapasia
1 FDR/18-19/Gaz/UZR/W05 Rehabilitation of Kapasia GC - Kaliganj GC Road from Ch. 00-9000m 9.0000 1010.061 M/S Amzad Traders 1010.061 05/02/2019 28/06/2019 100 13/09/2020
2 FDR/Gaz/UZR/W06 Rehabilitation of Kapasia GC (Korim Mill Bazer) - monohordi UZ H/Q (Kapasia Part) Road from Ch. 2900m - 12200m 9.3000 1087.652 M/S Dhiman Construction 1087.652 10/03/2019 10/09/2019 95 13/09/2020 Time Expired
4 Sreepur
1 FDR/Gaz/18-19/UNR/W02 Rehabilitation of Rajendrapur Bazar-Marta-Prohaladpur UPC Road from Ch. 0m - 10230m 10.2300 730.130 M/S Amzad Traders 730.130 04/04/2019 10/03/2020 100 13/09/2020 Time Expired
2 FDR/Gaz/18-19/UZR/W01 Rehabilitation of Bormi GC -Jaina Bazar RHD via Kawraid Road from Ch. 4450m - 19510m. 14.7000 1681.529 M/S Shanta Enterprise 1681.529 10/04/2019 30/11/2019 80 13/09/2020 Time Expired
Total : 71.8680 (Km) 7786.21 (Lac) 7786.21 (Lac)