SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Jhenaigati
1 FDR/She/18-19/UZR/W04 Rehabilitation of Kurua-Notun Bazar Road (Jhenaigati Part) from Ch. 1515m - 2106m 0.5910 53.350 M/S J.S Trading 53.350 18/03/2019 17/06/2019 100 24/08/2020
2 Nakla
1 FDR/She/19-20/UZR/W06 Rehabilitation of Narayankhola GC - Bhaitkandi GC Road from Ch 0m - 3900m 3.9000 253.468 M/S Eleas Construction 253.468 24/07/2019 23/01/2020 20 24/08/2020 Time Expired
3 Nalitabari
1 FDR/She/19-20/UZR/W05 Rehabilitation of Daharipara - Nakshi - Tarakanda - Kapasia - Dhanakusa Bazar Road from Ch. 0m - 11100m 5.1000 533.633 M/S Das Traders & M/S Eleas Construction (JV) 533.633 24/07/2019 23/01/2020 98 24/08/2020 Time Expired
2 FDR/She/18-19/UZR/W01 Rehabilitation of Nayabill bazar-Baromari via Manupara Road from Ch 0m - 7150m. 7.1500 260.444 M/S Dhrob Trade Agency 260.444 31/12/2018 30/04/2019 100 24/08/2020
4 Sherpur-s
1 FDR/She/18-19/UZR/W02 Rehabilitation of Sherpur-Jhagrarchar Road from Ch 975m - 7475m 6.5000 383.025 M/S Dhrob Trade Agency 383.025 04/02/2019 03/07/2019 100 24/08/2020
5 Sreebordi
1 FDR/She/18-19/UZR/W03 Rehabilitation of Sreebordi-Jhagrarchar GC Road from Ch. 2136m - 10280m 8.1440 509.897 M/S Akram Enterprise 509.897 03/02/2019 02/07/2019 100 24/08/2020
Total : 31.3850 (Km) 1993.82 (Lac) 1993.82 (Lac)