SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Gopalganj-s
1 FDR/Gop/19-20/UZR/W01 Rehabilitation of Gopalganj RHD - Puraton Lonch Ghat (Talakekenia GC) Road from Ch 0m - 9840m. 9.8400 1064.725 M/s. Kamrul and Brothers & M./s. Safa Briks 1064.725 26/02/2019 10/06/2020 55 23/08/2020 Time Expired
2 Muksudpur
1 FDR/Gop/18-19/UNR/W03 Rehabilitation of Balnarayon Bazar (UZR)-Ujani GC Road via Bohugram UP Office Road from 0m - 1970m 1.9700 98.470 Nitai Pada Datta 98.470 15/01/2019 15/03/2019 100 23/08/2020 Final
3 Tungipara
1 FDR/Gop/18-19/UNR/W02 Rehabilitation of Gopalpur UP Office- Guadhana Silna Road from Ch 0m - 7870m 7.8700 504.638 M/S DAS Traders - M/S Anamica Traders JV 504.638 23/01/2019 02/05/2020 100 23/08/2020 Final
Total : 19.6800 (Km) 1667.83 (Lac) 1667.83 (Lac)