Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bhedarganj
1 FDR/Sha/20-21/UNR/CW10 Construction of 1x9.00X9.00 Culvert on Rashid Bepari Bazar- Uttar Tarabunia Up road at Ch 2625m (2634m) 29.235 M/S Arif & Brothers 29.235 12/03/2020 11/09/2020 0 23/08/2020 Very Critical
2 FDR/1Sha/19-20/UZR/W07 Rehabilitation of Bhedarganj -Shakhipur-Kashempur Road from Ch. 0m - 16900m 16.9000 1783.180 Rafiq Construction Co. (Pvt) Ltd. 1783.180 01/09/2019 30/06/2020 73 23/08/2020 Time Expired
3 FDR/Sha/19-20/UZR/W06 Rehabilitation of Shakilpur GC - Chandpur Ferryghat via Tarabunia UP Road from Ch 2200m - 5450m. 3.2500 304.693 M/S Sheikh Enterprise 304.693 03/06/2019 02/12/2019 100 23/08/2020 Final
4 FDR/Sha/19-20/UNR/W05 Rehabilitation of Bhedarganj - Kashempur via DM Khali UP Office Road from Ch. 0m - 5490m 5.4900 398.226 M/S Sheikh Enterprise 398.226 03/06/2019 02/12/2019 100 23/08/2020 Final
2 Goshairhat
1 FDR/Sha/20-21/UNR/W11 Rehabilitation of Dasherjungle GC - Nagerpara Via Machuakhali Road from Ch 0m - 10140m. 10.1400 922.077 M/S Progati-Sheikh (JV) 922.077 15/06/2020 15/03/2021 0 23/08/2020 Progress Slow
3 Naria
1 FDR/Sha/20-21/UZR/BW09 Construction of 20m Bridge on Bhojeswar GC -Dogree R&H road at Ch. 5800m (5820m) 180.679 S.Ananta Bikash Tripura-M/S Abu Siddique (JV) 180.679 01/04/2020 31/03/2021 0 23/08/2020 Progress Slow
2 FDR/Sha/20-21/UZR/W08 Rehabilitation of Janjira -Naria-Sureswar raod from Ch 3000m - 3390m. 0.3900 149.309 M/S Mizan Enterprise 149.309 27/02/2020 25/06/2021 90 23/08/2020
3 FDR/Sha/18-19/UZR/W04 Rehabilitation of Janjira - Naria - Sureswar Road from Ch 0m - 2750m & 5875m - 12400m 9.2750 707.104 M/S Hamim Enterprise 707.104 16/06/2019 15/12/2019 100 23/08/2020
4 FDR/Sha/18-19/UZR/W03 Rehabilitation of Bhojeswar GC-Dogree R&H Road from Ch. 5450m- 6800m 1.3500 76.423 M/S Atika Trading 76.423 20/12/2018 19/04/2019 100 23/08/2020 Final Bill Paid
4 Shariatpur-s
1 FDR/Sha/18-19/BW01/UNR 02 A.Rehabilitation/Construction of Bridge Protection Work By Spurs on Palong-Binodpur UP Via Tolashar UP Road at Ch 0m-2100m. B.Rehabilitation of Bridge Approach on Palong-Binodpur UP Via Tulashar UP Road at 0m (2100m). 2.1000 142.449 M/S Nishi Enterprise 142.449 25/07/2018 30/06/2019 100 23/08/2020 Final Bill Paid
Total : 48.8950 (Km) 4693.38 (Lac) 4693.38 (Lac)