SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Baraigram
1 FDR/Nat/18-19/UZR/W08 Rehabilitation of Bonpara GC -Bagdob Bazar RHD via Baghat Hat (Grom shol) Road from Ch. . 1.5330 181.040 Hamidia Enterprise, Gopalpur, Lalpur Natore. 181.040 05/02/2019 07/05/2019 100 17/09/2020 Final Bill Paid
2 Gurudaspur
1 FDR/Nat/20-21/UZR/W14 Rehabilitation of Nazipur GC - Halsa GC Road (Gurudaspur Part) from Ch 4000m- 7970m 3.9700 391.788 391.788 0 17/09/2020 Tender Opening on 16-09-2020
2 FDR/Nat/19-20/UZR/W09 Rehabilitation of Nazipur GC - Halsa GC Road (Gurudaspur Part) from Ch. 0m 4000m. 4.0000 421.706 Rithin Enterprise & Holyhope Enterprise JV 421.706 16/04/2019 25/01/2020 100 17/09/2020 Final Bill Paid
3 FDR/Nat/18-19/UNR/W07 Rehabilitation of Biaghat UP - Subgari Hat Road from Ch. 3750m - 6035m 2.2850 76.702 Satya Narayan Roy (Tipu), Dokkin Borogacha, Natore. 76.702 29/01/2020 07/04/2019 100 17/09/2020 Final Bill Paid
3 Lalpur
1 FDR/Nat/19-20/UZR/W01 Rehabilitation of Gopalpur G.C-Rajapur GC Road from Ch. 2000m 0 11895m. 9.8950 815.820 M/S Dhurbo Construction 815.820 02/05/2019 10/03/2020 100 17/09/2020 Final Bill Paid
4 Naldanga
1 FDR/Nat/20-21/UZR/W13 Rehabilitation of Naldanga GC-Sherkole RHD via Kaligonj hat Road(Naldanga part)from CH. 0m - 2172m 2.1720 112.012 112.012 0 17/09/2020 tender Opening on 01/09/2020
5 Natore-s
1 FDR/Nat/20-21/UZR/W12 Rehabilitation of Upazila H/Q to Biprobelghoria RHD Road from Ch. 0m - 2600m 2.6000 234.788 234.788 0 17/09/2020 Tender Opening on 16/09/2020
2 FDR/Nat/18-19/UZR/W02 Rehabilitation of Upazila H/Q to Biprobelghoria RHD Road from Ch. 2600m - 5660m 3.0600 259.326 M/S. Islam Construction 259.326 27/03/2019 30/06/2019 90 17/09/2020 Time Expired
6 Singra
1 FDR/Nat/20-21/UZR/W19 Rehabilitation of Khezurtala RHD Samshpara GC via Dakmondop Road from Ch. 4000m - 10550 6.5500 150.106 M/S. Sinthia Enterprise 150.106 11/07/2020 09/11/2020 0 17/09/2020 Very Slow Progress (Contract made on 05-07-2020)
2 FDR/Nat/20-21/UZR/W18 Rehabilitation of Sherkol GC - Atrai via Tamukh Road from Ch. 0m - 4048m 4.0480 657.363 Mir Habibul Alam & M/S. Islam Construction JV 657.363 04/07/2020 02/01/2021 0 17/09/2020 Progress Slow. Contract made on 28/06/2020
3 FDR/Nat/18-19/UNR/W03-W06 Rehabilitation of (a) Damdama Sluice Gate via Rakhalgacha Road from Ch. 1500m - 2750m; (b) Singra - Baruhas - Tarash Submarsable Road from Ch. 0m - 3118m & 11660m - 14950m;(c) Choto Chwgram Bazar - Holderpara Road from Ch. 0m - 1000m & (d) Itali UP Office - Satpukuria Hat Road from Ch. 0m - 1500m 10.1580 255.607 M/S. Islam Construction & M/S. MN Trade JV 255.607 01/04/2019 15/02/2020 100 17/09/2020
Total : 50.2710 (Km) 3556.26 (Lac) 3556.26 (Lac)