SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Adamdighi
1 FDR/BOG/UZR/20-21/W10 Champapur-Abadpukur Road.Ch 00m to 4560m 4.5000 233.510 M/S Raj Construction & Rakib Traders JV 233.510 01/02/2020 20/06/2020 30 24/08/2020 On going
2 Sariakandi
1 FDR/BOG/UZR/18-19/W05 Sariakandi HQ-Baluahata GC Road Ch 4000m to 7965m 3.9500 102.710 M/S Alef Enterprise 102.710 30/09/2018 30/05/2019 100 24/08/2020 Completed
2 FDR/BOG/UZR/18-19/W04 Sariakandi HQ-Baluahata GC Road Ch00m to 4000m 4.0000 63.980 M/S Shomprity Constrution 63.980 30/09/2018 30/04/2019 100 24/08/2020 Completed
3 Shajahanpur
1 FDR/Bog/UZR/18-19/W09 Gohail GCM-Muruil RHW via Kalmahat (Shajahanpur Portion)Ch 00m to 3700m 3.7000 174.450 M/S Rabeya International 174.450 20/11/2018 20/03/2019 100 24/08/2020 Completed
4 Sherpur
1 FDR/Bog/18-19/UNR/W01 Rehabilitation of Mirzapur GC- Sughat UP Road. 5.9750 366.425 M/S Islam Enterprise 366.425 15/07/2018 30/05/2019 100 24/08/2020 Final
5 Shibganj
1 FDR/Bog/18-19/UZR/W02 Rehabilitation of Shibgonj Upazila H/Q -Chowkirghat via Anchlai Road. 4.0000 266.139 M/S Islam Enterprise 266.139 15/07/2018 30/05/2019 100 24/08/2020 Final
2 FDR/Bog/18-19/UZR/W06 Rehabilitation of Rahabal NHW-Baluahat GC via Boriahat Road. 9.0000 629.037 Ataur Rahman khan Ltd. & md. Monjurul Alam Mohon JV 629.037 10/10/2018 30/06/2019 100 09/07/2019 Final
6 Sonatala
1 FDR/Bog/UZR/18-19/W08 Baluahat-Sariakandi Upazila Road via karamja hat.Ch 16180 m to 17045m 0.8600 32.130 Matlubur Rahman_Shobin Traders JV 32.130 05/12/2018 30/06/2019 100 24/08/2020 Completed
2 FDR/Bog/UNR/18-19/W07 Horikhali GC - Pakulla UP via Millonerpara Ch 00m m to 5690m 5.6900 231.920 Matlubur Rahman_Shobin Traders JV 231.920 05/12/2018 30/06/2019 100 24/08/2020
Total : 41.6750 (Km) 2100.30 (Lac) 2100.30 (Lac)