Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Juri
1 CW03 Goalbari RHD - Fultola GC 0.0230 13069015.000 M/S Islam Construction 13069015.000 02/01/2019 25/05/2019 100 23/08/2020
2 Kulaura
1 FDR/MOU/18-19/UZR/W05 Brahman Bazar GC -Fenchugonj GC Via Fulartol GC ch 00m to 15000m 15.0000 822.550 M/S Mahabub Zafar Ahmed Gilma & M/S Suhag Enterprise JV 822.550 02/03/2019 05/09/2019 100 23/08/2020 Completed
3 Sreemangal
1 FDR/Mou/17-18/UZR/W02 Rehabilitation of Bhunabir (RHD) to Dubarhat GC via Mirzapur U.P office Road. 7.2000 557.371 Shahid Brothers and Take & Pay JV 557.371 15/10/2018 11/06/2019 100 23/08/2020
2 FDR/Mou/18-19/UZR/W01 Rehabilitation of Bhunabir (RHD) to Dubarhat GC via Mirzapur U.P office Road. 7.4000 589.602 Shahid Brothers and Take & Pay JV 589.602 15/10/2018 11/06/2019 100 23/08/2020
Total : 29.6230 (Km) 13070984.52 (Lac) 13070984.52 (Lac)