Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Kachua
1 UIIP/PCO/G-42 Implementation & Supply 602 nos Waste Basket (120 ltr) & 20 nos Non-motorized vehicle (van) under Kachua Pourashava District: Chandpur. 39.975 RFL Plastrics Limited 39.975 0 09/10/2024
2 UIIP-BC/PCO/W-565 A) Improvement of Road and widening Work at Damaluya Baro bari Road Start From Kachua Taguria Road to Damaluya Baro bari Bridge ch (0.00-1000.00m) infornt of kamal Councillor Home and connected Hossanpur road (Ward No- 07), under Kachua Pourashava B) Improvement work of RCC Road From Kachua Badpur road to kachua postoffice road .(Ch0.00~127.00m). Ward no -08 Under kachua pourashava,Chandpur. 1.1270 88.330 M/S Tanim Traders 88.330 03/09/2023 05/03/2024 100 09/10/2024
3 UIIP-BC/PCO/W-564 A) Improvement of RCC Drain Start from J.B Electric to Banoful Hotel ( Danbazar road) ch 0.00-37.00m link chal Bazar road 122.00m and Bisno pal hope to proposed bridge ch 0.00-43.00m ward no -08,under kachua pourashava   B) Improvement of Road by RCC Start from J.B Electric to Banoful Hotel ( Danbazar road) ch 0.00-37.00m link chal Bazar road 122.00m and Bisno pal hope to proposed bridge ch 0.00-43.00m ward no -08,under kachua pourashava C)Improvement of RCC Road Start from Nurani hotel to chattel Market (Present Wood Market) ward no -08,under kachua pourashava 0.3240 87.266 M/S Tamim Traders 87.266 03/09/2023 05/03/2024 100 09/10/2024
4 UIIP-BC/PCO/W-563 A)  Improvement of BC Road from Kachua-Rogunanthpur Road Kachua Upzilla Hospital to end of Poura Area Ch.0.00-1500.00m Ward no-02 & 03 Kachua Pourashava, Chandpur. B) Improvement of BC Road From Preyotush Podder Shop to Kariya Mojumdar Bari Bridge Ward No-05 (Ch.0.00-615.00m) Under Kachua Pourashava, Chandpur. (Salvage Amount-1,83,680.00) 2.1150 126.859 M/S Abdullah Enterprise 126.859 03/08/2023 05/03/2024 71 09/10/2024
5 UIIP-BC/PCO/W-569 (1) Construction of RCC Road by the side of kachua Upzilla Parishad Road From Preyotush Podder Shop To Kachua Hajigonj by Pass road .(Ch0.00~393.00m)and infront of Upzilla hospital ch(0.00-60.00) Under kachua pourashava,Chandpur. (2) Improvement of BC Road from Kachua Gulbahar Road to Koachanpur Gazirpole Road ch 0.00-990.00 meter Ward no01-02 under kachau pourashava 1.4280 170.688 Jeet-Tanim (JV) 170.688 10/03/2023 05/03/2024 100 09/10/2024
6 UIIP-BC/PCO/W-467 A) Construction of Shed for Public Transport Passenger (28.00 sqm) under Under Kachua Pourashava, Chandpur. B) Construction of One Storied Public Toilet (Type A=56 sqm) under Under Kachua Pourashava, Chandpur. C) Construction of One Storied Vegetables & Agricultural Products Market of 5 Storied Foundation (Floor Area=314 sqm) under Under Kachua Pourashava, Chandpur. 149.270 MS Ousmani and Brothers 149.270 20/02/2023 30/12/2024 33 09/10/2024
7 UIIP-BC/PCO/W-348 A) Construction of RCC Drain from Kachua Gulbahar CNG stand H/O Iqbal to Palashpur Masimpur Road (Ch:0.00-165.00m) Ward No.-03 Under Kachua Pourashava Chandpur. B) Construction of RCC Drain starting from Kachua Post Office to Khal Adjacent H/O Abdul Momin Master (Ch:0.00-126.00m) Ward No.-08 Under Kachua Pourashava Chandpur. 59.723 MIS Abdullah & Basher (JV) 59.723 24/03/2022 22/03/2023 100 09/10/2024 1.59% less
8 UIIP-BC/PCO/W-347 A) Construction of RCC Drain From Kachua Sachar Road mor VIP Hospital to SR Office East site Near Khal (Ch:0.00m-126.00m) Ward No.-07 Under Kachua Pourashava Chandpur. B) Construction of RCC Drain at Nurani Hotel Via Fish Market to Old Cow Market (Ch:0.00m-135.00m) Ward No.-08 Under Kachua Pourashava Chandpur. C) Construction of RCC Drain From Kachua Upazila Prishad Road H/O Mizanur Rahman Near Existing RCC Drain End to H/O Edris Bakaul South Side Near Khal (Ch:0.00-195.00m) Ward No.-03 Under Kachua Pourashava Chandpur. 96.153 M/S Kamal Enterprise 96.153 02/03/2022 02/03/2023 100 09/10/2024 0.403% less
9 UIIP-BC/PCO/W-346 A) Rehabilitation Works at Kachua Sachar Road VIP Hospital to Kachua Taguria Road End of Poura Area (Ch: 0.00-1015.00m) Ward No-07 Under Kachua Pourashava Chandpur . B) Construction Work of RCC Road at Kachua Bedpur road to Karish Bachu Mia Home (Ch:0.00-455.00m) & Link Road H/O Abdur Rab Master to Dr. Fajar Ali Home Pond North Side (Ch:0.00-190.00m) Ward No-08 Under Kachua Pourashava. Chandpur. 1.9600 87.071 M/S Shafiq Enterprise 87.071 10/02/2022 08/02/2023 100 09/10/2024 4.81% less
10 UIIP-BC/PCO/W-345 A) Construction Work of RCC Road & Palisading work start from Kachua Hajigonj bypass Road H/O Osman Mia to Kariya domria road Kariya North Para Pokania Madrasa (Ch:0.00-275m) Link Osman Mia Bari Pond par (Ch:0.00-120.00m) Ward No-03&04 Under Kachua Pourashava Chandpur. B) Construction Work of RCC Road from Kachua Bedpur Road to Kachua Nobabpur Road Ward No-08 Under Kachua Pourashava Chandpur. ( Ch:0.00-195.00m ) C) Construction Work of RCC Road from Kachua Dhan Bazar Bridge to Taj Tredars start from Dhan Bazer Bridge Ward No-08 Under Kachua Pourashava Chandpur. (Ch:0.00-166.00m) D) Rehabilitation Work at Kariya Domoria Road start from Kachua Paranpur Road Mojumdar Bari Bridge to Kariya Rahim Councillor old Home (Ch:0.00-560.00m) Ward No-04 Under Kachua Pourashava Chandpur. 1.2560 131.177 m/s Tanim Traders 131.177 30/09/2021 29/09/2022 100 09/10/2024 0.42% Less
11 UIIP-BC/PCO/W-456 A) Construction of Three Vent (5.00x4.00m) RCC Box Culvert on Kachua Shoe Maker Market near Khal (connecting road RCC Culvert Bridge) under Kachua Pourashava, Chandpur. B) Construction of One Vent (4.00x5.00m) RCC Box Culvert on Karish Ismail Hafej Bari near Khal (Kachua to Nababpur road RCC Culvert) under Kachua Pourashava, Chandpur. 88.185 Alamgir Hayder Bhuiya 88.185 16/05/2022 16/05/2023 0 27/09/2022 5.15% less
12 UIIP-BC/PCO/W-252 Construction of RCC U Drain with Cover Slab at Kachua Banga Bondhu Degree College North side Khal, ward no.-08 (Ch. 0.00-95.00m) under Kachua Pourosava. 54.087 M/S Alif Enterprise 54.087 30/01/2022 60 27/09/2022 18.62% Less (Final bill will be Aug.-22)
13 UIIP-BC/PCO/W-251 (A) Construction Works of RCC Road & Retaining Wall from Kachua Bedpur Road to Karish Sirajdilar Home Road start fro Kachua Bedpur BC Road, ward no27-06 (Ch. 0.00m-215m) under Kachua Pourosava. (B)Construction Works of RCC Road & Retaining Wall from Kachua Teguria Road to Dhamalua wet8324 Para miazi Bari (Ch. 0.00m-200m) under Kachua Pourosava. 0.4150 121.152 M/S Tanim Traders 121.152 30/01/2022 100 27/09/2022 17.14% Less ( Final bill Done)
14 UIIP-BC/PCO/W-250 Rehabilitation works and widening of Kachua Nababpur Road by BC start from Post Office to Karish thakurbari Pond Par (Ch. 000m-1060m) under Kachua Pourosava. 1.0600 83.370 M/S Renu mia 83.370 19/01/2022 100 27/09/2022 0.15% Less Revised ( Final bill Done)
15 UIIP-BC/PCO/W-249 Rehaliation works and widening of Kachua Nababpur road by BC start from Karish Thakurbari pond par north site to end of poura area (ch 1060m-2405m) Under Kachua pourashava. 1.3450 89.767 M/S Renu mia 89.767 19/01/2022 100 27/09/2022 0.15% Less Revised ( Final bill Done)
16 UIIP-BC/PCO/W-53 (a) Construction work of RCC Road & Retaining wall Start from Kachua Gaulbahar Road to Baliyatoli Rahman hazi bari road. Ward no-01 Under Kachua Pourashava for the year of 2018-19. Ch. 0.00-0.215 b) Construction Work of RCC Road from Kachua Golbahar Road to H/O Abu Sofiyan via Baliyatoly pal Bari Jame mosque Road. Word no-01 under Dachua Pourashava for the year of 2018-19. Ch. 0.00- 0.395 (C) Construction work of RCC Road from Kachua Golbahar Road to h/o bachu mia start from Koachancipur guni mia cashiar home north side corner Word no-02 Under Kachua pourashava for the year of 2018-19.ch 00-270m 0.8460 105.993 MAM Construction Ltd 105.993 19/08/2020 18/08/2021 100 27/09/2022 12.52% Less ( Final bill Done)
17 UIIP-BC/PCO/W-52 (a) Construction work of RCC Road & Retaining wall Start from Kachua Hajigong bypass via H/O Krisna patikor to Kariya Dumoria Road. Ward No-04 Under Kachua pourashava for the year of 2018-19. (b) Construction work of RCC Road & Retaining wall from Kachua paranpur road to kariya H/O Shahidullah. Kariya eidgah road start from BC Road ward no-05 under Kachua pourashavafor the year of 1018-19. 0.8460 156.595 MAM Construction Ltd 156.595 19/08/2020 31/03/2022 100 27/09/2022 12.63% Less ( Final bill Done)
Total : 12.7220 (Km) 1735.66 (Lac) 1735.66 (Lac)