Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Shibganj
1 UIIP-BC/PCO/W-485 A) Construction of One Storied Vegetables & Agricultural Products Market of 5 Storied Foundation (Floor Area=314 sqm) at Shibganj Kacha Bazer under Shibganj Pourashava Chapai Nawabganj. 104.167 M/S Nisha Enterprise 104.167 21/07/2022 20/07/2023 0 27/09/2022 0.13% Less
2 UIIP-BC/PCO/W-357 A) Construction of Single vent Box Culvert (2.6mx2.6m ) at jalmachmary behind Primary School in Shibganj Pourashava Area ward no. 07 under Shibganj Pourashava length- 7.00m B) Construction of Single vent Box Culvert (2.6mx2.6m ) at Chondipur beside H/O Hazrat in Shibganj Pourashava Area. ward no. 07 under Shibganj Pourashava length- 7.00m C) Construction of Single vent Box Culvert (2.6mx2.6m ) at Pitholitala Boglauril in Shibganj Pourashava Area. ward no. 07 under Shibganj Pourashava length- 7.00m D) Construction of Single vent Box Culvert (2.6mx2.6m) at Salimabad Khanpara H/O Gudha Hazil in Shibganj Pourashava Area. ward no. 07 under Shibganj Pourashava length- 7.00m E) Construction of Single vent Box Culvert at Choturpur beside H/O Rakib in Shibganj Pourashava Area. ward no. 07 under Shibganj Pourashava . length- 7.00m 77.381 Rithin & G.R (JV) 77.381 22/02/2022 21/08/2022 100 27/09/2022 15.14% Less
3 UIIP-BC/PCO/W-356 A) Construction & Re-construction of drain by RCC start from Shibganj Girls School mour to Barendro Road drain via Contractor's Somiti & H/O Lotif ( Ch. 0.00-500.00m) under Shibganj Pourashava .B) Construction of drain by RCC start from Choto Chalk mour to Jalmachmary Barendro Road via Kadomtala Culb ( Ch. 0.00-410.00m) under Shibganj Pourashava . 162.055 Rithin & G.R (JV) 162.055 21/08/2022 15 27/09/2022 14.34% Less
4 UIIP-BC/PCO/W-355 Construction & Re-Construction of drain by RCC start from Shibganj Bazar Bisu's Shop to Barandro Road via Shibganj Pourashava uttar Gate and H/O Lotif (Ch.: 0.00-623.00m) under Shibganj Pourashava . 107.122 MD. Abdul mannan 107.122 21/08/2022 40 27/09/2022 17.01% Less
5 UIIP-BC/PCO/W-301 (a) Improvement of existing HBB road by BC start from Dowlatpur Hazipara mosque to H/O Alauddin at Dowlatpur Kabirajpara via Hazaridanga H/O late Sadek to Babupara H/O late Kalu Member. Ch. 00-500.00m ward no. 04 Under Shibganj Pourashava. (b) Improvement of existing HBB road by BC start from Dowlatpur Kadomtala moor to H/O Monirul Principal vai H/O Badol at Dowlatpur Mondoltola. Ch. 00-420.00m. Ward no. 04 Under Shibganj Pourashava. (c) Rehabilitation of Alidanga damage BC road by BC start from H/O Nabokanto dadu to R&H Road Ch. 00-510.00m Under Shibganj Pourashava. 1.4300 99.826 M/S Rony Enterprise & M/S Shefat International JV 99.826 30/04/2021 09/09/2021 100 27/09/2022 17.68% Less
6 UIIP-BC/PCO/W-248 (a) Improvement of Kacha Road by RCC with Protective work starting from Club Road to House of Oni mia via House of Diamond at Mordana Miapara. Ch. 00-125.00m. Under Shibganj Pourashava. b) Improvement of Kacha Road by RCC with Protective work starting from Club Road to House of Yeasin Ali at Mordana. Ch. 00-100.00m. Under Shibganj Pourashava. (c) Improvement of Mordana existing HBB Road by RCC starting from moon light Club to H/O Kalam. Ch. 00-450.00m. Under Shibganj Pourashava (d) Improvement of Kacha Road by RCC Starting from Mordana HBB Road H/O. Khudi to House of Dablu at Mordana. Ch. 00-300.00m. ward no. 09. Under Shibganj Pourashava. 0.9750 140.808 Opal-Pathbangl- JV 140.808 30/04/2021 09/09/2021 100 27/09/2022 15.17% Less, Revised
7 UIIP-BC/PCO/W-247 Improvement of existing earthen Road by BC starting from H/O Polash at Choturpur to H/O Abdul Mannan via H/O Hazrat Ali at Jalmachmary. Ch. 00-1000.00m, ward no. 05, Under Shibganj Pourashava. 1.0000 83.083 Opal-Pathbangl- JV 83.083 30/04/2021 09/09/2021 100 27/09/2022 13.97% Less
8 UIIP-BC/PCO/W-246 (a) Improvemrnt of damage existing BC & WBM Road by Bituminous carpeting starting from Barendro Road to H/O Al-Abdur Razzak via H/O Hazrat Mistiry at Jalmachmary Ch. 00-1400.00m ward no. 07, Shibganj Pourashava. (b) Improvement of existing WBM Road by BC starting from Shop of Tohid to H/O Anamul Maulana at Roshulpur Ch. 00-500.00m. ward no. 06, Under Shibganj Pourashava. 1.9000 92.432 Hanzu Enterprise & Selim Reza- JV 92.432 30/04/2021 09/09/2021 100 27/09/2022 15.24% Less
9 UIIP-BC/PCO/W-240 Rehabilitation of existing damage Selimabab BC & HBB road by BC starting from Shimul Talal Moure to Babupukur via paikor tala. Ch. 00-1110.00m Under Shibganj Pourashava. 1.1100 89.104 M/S Rony Enterprise & M/S Shefat International JV 89.104 30/04/2021 09/09/2021 100 27/09/2022 14.49% Less
10 UIIP-BC/PCO/W-97 Improvement of existing earthen & HBB road by BC start from H/O Humayon to H/O Hazrat via Oktiya Mosjid twowards bottala moor at Chondipur Ch. 00-1000.00m, in ward no. 07. Under Shibganj Pourashava, Dist: Chapai Nawabganj. 1.0000 94.692 Opal International 94.692 09/09/2021 100 27/09/2022 1.20% Less, Revised
11 UIIP-BC/PCO/W-96 (a) Improvement of Existing damage WBM road by BC start from H/O Late Menu Master to H/O Sayed former councilor at Pitholitala with 02 nos R.C.C cross drain. Total length= 1325.00m, ward no. 08 Under Shibganj Pourashava, Dist: Chapai Nawabganj. (b) Improvement of exiting damage HBB road by BC start from H/O Cethu to H/O Alauddin via H/O Subed at Pitholitala north para Ch. 00-650.00m ward no. 03 Under Shibganj Pourashava, Dist: Chapai Nawabganj. 1.9750 121.547 Opal International 121.547 11/11/2020 10/11/2021 100 27/09/2022 10.00% Less
12 UIIP-BC/PCO/W-95 Improvement of existing HBB road by BC start from Mohisgara Borendo road to towards culvert at Mithupur Jagnathpur.Ch. 00-1115.00m, ward no. 09 Under Shibganj Pourashava, Dist: Chapai Nawabganj. 1.1150 108.826 Opal International 108.826 09/09/2021 100 27/09/2022 10.00% Less
Total : 10.5050 (Km) 1281.04 (Lac) 1281.04 (Lac)