Memo no.LGED/UE/Mat(Uttar)/2012/1016                                                                                   Date: 11/11/2012

 

Notification of Award (Form W-4)

 

Latest Date of Commencement  : 18/11/2012

Date of Completion                     : 17/08/2013

To

                M/S Akkas Construction

                Pro.Md.Kawsar Alam

                1085/1, Malibag Chowdhurypara

                Dhaka.

 

                This is to notify you that your Tender date 15-10-2012 for the execution of the Works of Construction of  Islamabad Union Parishad Complex Bhaban including Electrification, Tube-well, Sanitary Work and Furniture Supply Package No. 01 for the Contract Price of Taka 93,23,370.00(Ninety three lac twenty three thousand  three hundred seventy taka only) as corrected and modified in accordance with the Instructions to Tenderers Has been approved by Project Director, Union Parishad Complex Bhaban Project (2nd Phase), LGED, LGED Bhaban, Agargaon, Shere-E-Bangla Nagar, Dhaka-1207.

 

                You are requested to take following action:

 

            a) accept in writing the notification of Award with in (7) days of its issuance pursuant to ITT Sub Cluse 45

            b) Furnish a performance security in the specified format and in the amount of tk 466170.00(Four lac sixty six thousand one hundred seventy taka only) within fourteen (14) days of issuance of this letter by not later than  26/11/2012, in accordance with ITT Clause 46.1

           c) Sign the contract within twenty eight (28) days of issuance of this letter but not later than (09/12/2012) in accordance with ITT Clause 47.2

 

                You may precede with the execution of the works for Construction of  Islamabad Union Parishad Complex Bhaban including Electrification, Tube-well, Sanitary Work and Furniture Supply upon completion of the above tasks. You may also please note that his notification of award shall constitute the formation of this contract which shall become binding upon you.

 

 

 

(A.T.M.Rabiul Alam)

Upazila Engineer

Matlab Uttar, Chandpur.

C.C

01. The Project Director, Union Parishad Complex Bhaban Project (2nd Phase) LGED, LGED Bhaban, Agargaon, Shere-E-Bangla Nagar, Dhaka-1207.

02. The Executive Engineer, LGED, Chandpur.

03. The Upazila Nirbahi Officer, Matlab Uttar, Chandpur.

04.  Mr......................................................................... SAE,LGED, Matlab Uttar, Chandpur.

05.  Mr......................................................................... Work Assistant ,LGED, Matlab Uttar, Chandpur.

06. Chairman, Islamabad Union Parishad, Matlab Uttar, Chandpur.

07. Office Copy.