Government of the People’s
Republic of
Local Government Engineering
Department
Office of the Executive
Engineer,Rajshahi.
Memo No.
LGED/XEN/Raj/SRIIP/NOA/XXIX-06/2013/2589 Dated t 05-08-2013.
Contract Package No:
LGED/SRIIP/RJS/W-072
Date t 14-02-2013.
To M/s. Hossain Enterprise (JV) Authorised Partner : M/s.
Hossain Enterprise Prop. S/o. Ramchandrapur,
Ghoramara, Boalia, Rajshahi. Mobile No. 01719-792957. |
|
This is to notify you that your
Tender dated 17-04-2013 (IFT No. 29/2012-13, dated 12-03-2013 for the execution of the Works
for (a) Improvment of Arani GC to Horipur Ghat (Ch. 4,920m to 5,790m) UZR
(Road ID No. 181102009),
Upazila : Bagha & (b) Improvment of Kakonhat to Hatbakoil via Koilhat (Ch. 16,000m to
20,135m) UZR (Road ID No. 181942013), Upazila :
Tanore, District: Rajshahi, for the Contract Price of Tk. 4,74,23,024.17
(Tk. Four crore seventy four lac twenty three thousand twenty four & paisa seventeen)
only as
corrected and modified in accordance with the Instructions to Tenderers, has
been approved by the Project Director, Sustainable Rural Infrastructure
Development Project, Level-6, RDEC Bhaban, LGED, Agargaon, Sher-e-Banglanagar,
Dhaka-1207.
|
i. |
Accept in writing the Notification of Award within 7(Seven) working days of its issuance pursuant to ITT Sub-clause 63.1. |
|
|
|
|
ii. |
Furnishing a Performance Security in the form of a Bank Draft, Pay Order or an Irrevocable Bank Guarantee {Irrevocable Bank Guarantee should be valid for a period not less than 560 (Five hundred sixty days)} and in the amount of Tk. 23,72,000.00 (Tk. Twenty three lac seventy two thousand) only, within 14 (Fourteen) working days of acceptance of this Notification of Award but not letter than 08-09-2013 in accordance with ITT Clause 65. |
|
|
|
|
iii. |
Sign the Contract within 28 (Twenty eight) working days of issuance of this Notification of Award but not letter than 17-09-2013 in accordance with ITT Sub Clause 69.2 (Please attach one copy of your attested present passport size Photographs with contract documents & Contract will be signed in a Non-judicial Stamp of Tk.300.00). |
|
|
|
You may proceed with the execution of the works only upon completon of the above tasks. You may also please note that this Notification of Award shall constitute the formation of this Contract which shall become binding upon you.
We attach the draft Contract and all other documents for your perusal and signature.
|
( Executive Engineer LGED. Rajshahi. |
Memo
No. LGED/XEN/Raj/SRIIP/NOA/XXIX-06/2013/2589/2013/2589/1(5) Date t
05-08-2013.
Copy for information & taking necessary
action to:-
1. |
Audit & Accounts Officer, Office of the D C A, Rajshahi. |
2. |
Senior Assistant Engineer, of this Office. |
3. |
Upazila Engineer. Local Government Engineering Department, Bagha
& Tanore, Rajshahi. He is responsible for the full time works supervision
to ensure quality implementation. He may assign a Sub-Assistant Engineer
& a Work Assistant to supervise the implementation of works and inform
the undersigned accordingly. |
4. |
Assistant Engineer (Civil), of this Office. |
|
Executive Engineer LGED. Rajshahi. |
Memo
No.
LGED/XEN/Raj/SRIIP/NOA/XXIX-06/2013/2589/1(5)/1(7) Date t
05-08-2013.
Copy for kind information & necessary
action to:-
1. |
Chief Engineer, Local Government Engineering Department, LGED Bhaban,
Agargapn, Sher-e-Bangla Nagar, Dhaka-1207. |
2. |
Additional Chief Engineer, Local Government Engineering Department,
Rajshahi Division, Rajshahi. |
3. |
Superintending Engineer, Local Government Engineering Department,
Rajshahi Region,
Rajshahi. |
4. |
Project Director, Sustainable Rural Infrastructure Development
Project, Level-6, RDEC Bhaban, LGED, Agargaon, Sher-e-Banglanagar,
Dhaka-1207. This has reference to his Memo.No. LGED/PD/SRIIP/137.2012/ 867, dated.23-07-2013. |
5. |
Deputy Project Director, Sustainable Rural Infrastructure Development
Project, LGED, Rajshahi. |
6. |
Team leader, DS&M Consultant, SRIIP, LGED H/Q, Agargaon, |
7. |
Field Engineer, DS&M Consultant, SRIIP, LGED, Rajshahi. |
|
Executive Engineer LGED. Rajshahi. |
Government of the People’s
Republic of
Local Government Engineering
Department
Office of the Executive
Engineer,Rajshahi.
Memo No. LGED/XEN/Raj/SRIIP/NOA/XXIX-05/2013/2588 Dated t 05-08-2013.
Contract Package No: LGED/SRIIP/RJS/W-068
Date t 14-02-2013.
To M/s. Podder Construction Prop. Modhu Podder S/o. Late
Horendranath Podder Lalbazar, Natore. Mobile No.01711-289337. |
|
This is to notify you that your
Tender dated 17-04-2013 (IFT No. 29/2012-13, dated 12-03-2013 for the execution of the Works
for Improvement of road
from
Jholmolia to Mominpur via
Sayaidpur & Bilmaria (Ch. 0m to 10,500m), UZR (Road ID No. 181822020), Upazila : Puthia, District: Rajshahi, for the
Contract Price of Tk. 4,60,69,883.13
(Tk. Four crore sixty lac sixty nine thousand eight hundred eighty three &
paisa thirteen) only as corrected and modified in accordance with the Instructions to
Tenderers, has been approved by the Project Director, Sustainable Rural
Infrastructure Development Project, Level-6, RDEC Bhaban, LGED, Agargaon,
Sher-e-Banglanagar, Dhaka-1207.
|
i. |
Accept in writing the Notification of Award within 7(Seven) working days of its issuance pursuant to ITT Sub-clause 63.1. |
|
|
|
|
ii. |
Furnishing a Performance Security in the form of a Bank Draft, Pay Order or an Irrevocable Bank Guarantee {Irrevocable Bank Guarantee should be valid for a period not less than 560 (Five hundred sixty days)} and in the amount of Tk. 23,04,000.00 (Tk. Twenty three lac four thousand) only, within 14 (Fourteen) days of acceptance of this Notification of Award but not letter than 08-09-2013 in accordance with ITT Clause 65. |
|
|
|
|
iii. |
Sign the Contract within 28 (Twenty eight) working days of issuance of this Notification of Award but not letter than 17-09-2013 in accordance with ITT Sub Clause 69.2 (Please attach one copy of your attested present passport size Photographs with contract documents & Contract will be signed in a Non-judicial Stamp of Tk.300.00). |
|
|
|
You may proceed with the execution of the works only upon completon of the above tasks. You may also please note that this Notification of Award shall constitute the formation of this Contract which shall become binding upon you.
We attach the draft Contract and all other documents for your perusal and signature.
|
( Executive Engineer LGED. Rajshahi. |
Memo No. LGED/XEN/Raj/SRIIP/NOA/XXIX-05/2013/2588//1(4) Date t 05-08-2013.
Copy for information & taking necessary
action to:-
1. |
Audit & Accounts Officer, Office of the D C A, Rajshahi. |
2. |
Senior Assistant Engineer, of this Office. |
3 |
Upazila Engineer. Local Government Engineering Department, Puthia,
Rajshahi. He is responsible for the full time works supervision to ensure
quality implementation. He may assign a Sub-Assistant Engineer & a Work
Assistant to supervise the implementation of works and inform the undersigned
accordingly. |
4 |
Assistant Engineer (Civil), of this Office. |
|
Executive Engineer LGED. Rajshahi. |
Memo No.
LGED/XEN/Raj/SRIIP/NOA/XXIX-05/2013/2588/1(4)/1(7) Date t 05-08-2013.
Copy for kind information & necessary
action to:-
1. |
Chief Engineer, Local Government Engineering Department, LGED Bhaban,
Agargapn, Sher-e-Bangla Nagar, Dhaka-1207. |
2. |
Additional Chief Engineer, Local Government Engineering Department,
Rajshahi Division, Rajshahi. |
3. |
Superintending Engineer, Local Government Engineering Department,
Rajshahi Region,
Rajshahi. |
4. |
Project Director, Sustainable Rural Infrastructure Development
Project, Level-6, RDEC Bhaban, LGED, Agargaon, Sher-e-Banglanagar,
Dhaka-1207. This has reference to his Memo.No. LGED/PD/SRIIP/137.2012/ 867, dated.23-07-2013. |
5. |
Deputy Project Director, Sustainable Rural Infrastructure Development
Project, LGED, Rajshahi. |
6. |
Team leader, DS&M Consultant, SRIIP, LGED H/Q, Agargaon, |
7. |
Field Engineer, DS&M Consultant, SRIIP, LGED, Rajshahi. |
|
Executive Engineer LGED. Rajshahi. |
Government of the People’s
Republic of
Local Government Engineering
Department
Office of the Executive
Engineer,Rajshahi.
Memo No. LGED/XEN/Raj/SRIIP/NOA/XXIX-04/2013/2587 Dated t 05-08-2013.
Contract Package No: LGED/SRIIP/RJS/W-063 Date
t 03-03-2013.
To M/s. Podder Construction Prop. Modhu Podder S/o. Late
Horendranath Podder Lalbazar, Natore. Mobile No.01711-289337. |
|
This is to notify you that your
Tender dated 17-04-2013 (IFT No. 29/2012-13, dated 12-03-2013 for the execution of the Works
for Improvement of road from Hatgangopara to Keshorhat GC (Ch. 0m to
5,580m) UZR, (Road ID No. 181122012), Upazila
: Bagmara, District: Rajshahi, for the Contract Price of Tk. 4,50,07,122.94
(Tk. Four crore fifty lac seven thousand one hundred twenty two & paisa ninety
four) only as corrected and modified in accordance with the Instructions to
Tenderers, has been approved by the Project Director, Sustainable Rural Infrastructure
Development Project, Level-6, RDEC Bhaban, LGED, Agargaon, Sher-e-Banglanagar,
Dhaka-1207.
|
i. |
Accept in writing the Notification of Award within 7(Seven) working days of its issuance pursuant to ITT Sub-clause 63.1. |
|
|
|
|
ii. |
Furnishing a Performance Security in the form of a Bank Draft, Pay Order or an Irrevocable Bank Guarantee {Irrevocable Bank Guarantee should be valid for a period not less than 560 (Five hundred sixty days)} and in the amount of Tk. 22,51,000.00 (Tk. Twenty two lac fifty one thousand) only, within 14 (Fourteen) days of acceptance of this Notification of Award but not letter than 08-09-2013 in accordance with ITT Clause 65. |
|
|
|
|
iii. |
Sign the Contract within 28 (Twenty eight) working days of issuance of this Notification of Award but not letter than 17-09-2013 in accordance with ITT Sub Clause 69.2 (Please attach one copy of your attested present passport size Photographs with contract documents & Contract will be signed in a Non-judicial Stamp of Tk.300.00). |
|
|
|
You may proceed with the execution of the works only upon completon of the above tasks. You may also please note that this Notification of Award shall constitute the formation of this Contract which shall become binding upon you.
We attach the draft Contract and all other documents for your perusal and signature.
|
( Executive Engineer LGED. Rajshahi. |
Memo No. LGED/XEN/Raj/SRIIP/NOA/XXIX-04/2013/2587/1(4) Date t 05-08-2013.
Copy for information & taking necessary
action to:-
1. |
Audit & Accounts Officer, Office of the D C A, Rajshahi. |
2. |
Senior Assistant Engineer, of this Office. |
3 |
Upazila Engineer. Local Government Engineering Department, Bagmara,
Rajshahi. He is responsible for the full time works supervision to ensure
quality implementation. He may assign a Sub-Assistant Engineer & a Work
Assistant to supervise the implementation of works and inform the undersigned
accordingly. |
4 |
Assistant Engineer (Civil), of this Office. |
|
Executive Engineer LGED. Rajshahi. |
Memo No.
LGED/XEN/Raj/SRIIP/NOA/XXIX-04/2013/2587/1(4)/1(7) Date t 05-08-2013.
Copy for kind information & necessary
action to:-
1. |
Chief Engineer, Local Government Engineering Department, LGED Bhaban,
Agargapn, Sher-e-Bangla Nagar, Dhaka-1207. |
2. |
Additional Chief Engineer, Local Government Engineering Department,
Rajshahi Division, Rajshahi. |
3. |
Superintending Engineer, Local Government Engineering Department,
Rajshahi Region,
Rajshahi. |
4. |
Project Director, Sustainable Rural Infrastructure Development
Project, Level-6, RDEC Bhaban, LGED, Agargaon, Sher-e-Banglanagar,
Dhaka-1207. This has reference to his Memo.No. LGED/PD/SRIIP/137.2012/ 867, dated.23-07-2013. |
5. |
Deputy Project Director, Sustainable Rural Infrastructure Development
Project, LGED, Rajshahi. |
6. |
Team leader, DS&M Consultant, SRIIP, LGED H/Q, Agargaon, |
7. |
Field Engineer, DS&M Consultant, SRIIP, LGED, Rajshahi. |
|
Executive Engineer LGED. Rajshahi. |