Government
of the People’s Republic of Bangladesh
Local Government Engineering Department
Office of the Project Manager
Agargoan,
Sher-e-bangla Nagar
Dhaka-1207
Memo
No. : LGED/CE/KCBPPCR/D-01/2014/36 Dated: 10-06-2014
Addendum of IFP
01/2014
Khulna
Coal Based Power Plant Connecting Road Project
pre- Pre-qualification Meeting
Date : 10.06.2014, 11
AM. Venue : LGED Bhavan
Participants : Signature sheet attached.
A pre- Pre-qualification meeting was held
at LGED H/Q, Dhaka between LGED, BPDB and the Applicants who have purchased the Pre-qualification
Document regarding
clarify issues and to answer
questions on any matter arising in the Pre-qualification Document,.
After detail discussion, the following decisions were made. This Addendum will
be the part and parcel of the Prequalification Document.
SN |
Clause |
Issues |
Decisions |
01 |
ITA
14.1(b) |
The
required number of similar contract constructed over a period of last 10
(Ten) years shall be at least 1(one)
construction contract of 10 km 4
lane road........ |
The
required number of similar contract constructed over a period of last 10
(Ten) years shall be at least 1(one)
construction contract of 5 km 2
lane road........ |
02 |
|
A minimum
number of 2(two) construction experience in Deep pilling works in
rivers with rotary drill and
Concrete mixing plants. |
A minimum
number of 2(two) construction experience in Deep pilling works with
rotary drill and Concrete
mixing plants |
03 |
ITA 14.1(c) |
A satisfactory construction of similar works of at least contract value
of BDT 80 (Eighty) Crore in a single contract over a period
of last 10(ten) years shall be required |
A satisfactory construction of similar works of at least contract value
of BDT 50 (Fifty) Crore in a single contract over a period
of last 10(ten)years shall be required |
04 |
ITA 15.1 |
The required average annual construction turnover shall be minimum BDT 80
(Eighty) Crore
over the last 5 years. |
The required average annual construction turnover shall be minimum BDT 60(Sixty)
Crore
over the last 5 years. |
05 |
ITA
17.1 1 |
Sand pile equipments 150
set |
Sand pile equipments 60
set or Hudraulic Sand Piling equipment 2 nos. |
|
2 |
Bored Piling Equipment (Hydraulic
Rotary Type) 2 set |
Bored Piling Equipment (Rotary
Type) 1set |
|
5 |
Cleaning Bucket 2 set |
Deleted |
|
8 |
Bentonite mixture machine (cyclone) 2 set |
Bentonite mixture machine (cyclone) 1 set |
|
9 |
Desanding machine 2 set |
Deleted |
|
10 |
Asphalt plant 2 set |
Asphalt plant 1 set |
|
11 |
Excavator with chain doser 20set |
Excavator with chain doser 4 set |
|
12 |
Vibratory roller (8-10 Ton) 10 |
Vibratory roller (8-10 Ton) 3 nos |
|
13 |
Water tanker 3 |
Water tanker 1 |
|
17 |
Stone crushing plant |
Stone crushing plant 1no |
|
27 |
Stone Crushing Plant |
Overlapping SN 17, Deleted |
06 |
ITA
18.5 ADS Clauses References ITA-14.1(b) |
Requirements for other
Partner(s) At least one contract of
similar nature, complexity and method of construction technology |
Requirements for other
Partner(s) At least 25% of similar
nature, complexity and method of construction technology |
07 |
Road
X-Section |
Provision for Dredge
filling in embankment. |
Dredge filling directly in embankment will not be allowed. Instead of that,
sand (FM 0.5) to be stock piled out of the right of way of road by dredge
filling or other method. Road embankment to be constructed 150mm thick layer
by layer with necessary compaction. |
08 |
Question |
Is there any provision for
Mobilization Advance? |
No, Mobilization Advance will not be provided. |
Bipul Chandra Banik
Project Manager
Memo
No. : LGED/CE/KCBPPCR/D-01/2014/36/1(12) Dated: 10-06-2014
Copy (Not in
order of seniority):
6.
Project
Director, Khulna Coal Based Power Plant Connecting Road, BPDB, Biddyut bhavan (8th
floor), 1 Abdul Goni Road, Dhaka.
Bipul Chandra Banik
Project
Manager
Memo
No.
: LGED/CE/KCBPPCR/D-01/2014/36/2(12) Dated: 10-06-2014
Copy:
For information and necessary action to-
_____________________________________________________
_____________________________________________________
_____________________________________________________
Bipul Chandra Banik
Project
Manager