LGED Tender Banner

Government of the People’s Republic of Bangladesh

Local Government Engineering Department

Office of the Project Manager

Khulna Coal Based Power Plant Connecting Road

LGED Bhaban (Level-05)

Agargoan, Sher-e-bangla Nagar

Dhaka-1207

 

Memo No. : LGED/CE/KCBPPCR/D-01/2014/36                          Dated:     10-06-2014

 

Addendum of IFP 01/2014

Khulna Coal Based Power Plant Connecting Road Project

pre- Pre-qualification Meeting

Date : 10.06.2014, 11 AM. Venue : LGED Bhavan

Participants :  Signature sheet attached.

 

A pre- Pre-qualification meeting was held at LGED H/Q, Dhaka between LGED, BPDB and the Applicants who  have purchased the Pre-qualification Document  regarding clarify issues and to answer questions on any matter arising in the Pre-qualification Document,. After detail discussion, the following decisions were made. This Addendum will be the part and parcel of the Prequalification Document.

SN

Clause

Issues

Decisions

01

ITA 14.1(b)

The required number of similar contract constructed over a period of last 10 (Ten) years shall be at least 1(one) construction contract of 10 km 4 lane road........

The required number of similar contract constructed over a period of last 10 (Ten) years shall be at least 1(one) construction contract of 5 km 2 lane road........

02

 

A minimum number of 2(two) construction experience in Deep pilling works in rivers with rotary drill and Concrete mixing plants.

A minimum number of 2(two) construction experience in Deep pilling works with rotary drill and Concrete mixing plants

03

ITA 14.1(c)

A satisfactory construction of similar works of at least contract value of BDT 80 (Eighty) Crore in a single contract over a period of last 10(ten) years shall be required

A satisfactory construction of similar works of at least contract value of BDT 50 (Fifty) Crore in a single contract over a period of last 10(ten)years shall be required

04

ITA 15.1

 

The required average annual construction turnover  shall be minimum BDT 80 (Eighty) Crore over the last 5 years.

The required average annual construction turnover  shall be minimum BDT 60(Sixty) Crore over the last 5 years.

 

05

ITA 17.1

1

 

Sand pile equipments 150 set

Sand pile equipments 60 set

or

Hudraulic Sand Piling equipment 2 nos.

 

2

Bored Piling Equipment (Hydraulic Rotary Type)  2 set

Bored Piling Equipment (Rotary Type) 

1set

 

5

Cleaning Bucket  2 set

Deleted

 

8

Bentonite mixture machine (cyclone) 2 set

Bentonite mixture machine (cyclone)

 1 set

 

9

Desanding machine 2 set

Deleted

 

10

Asphalt plant   2 set

Asphalt plant   1 set

 

11

Excavator with chain doser  20set

Excavator with chain doser  4 set

 

12

Vibratory roller  (8-10 Ton) 10

Vibratory roller  (8-10 Ton) 3 nos

 

13

Water tanker 3

Water tanker 1

 

17

Stone crushing plant

Stone crushing plant 1no

 

27

Stone Crushing Plant

Overlapping SN 17, Deleted

06

ITA 18.5

ADS Clauses References

ITA-14.1(b) 

Requirements for other Partner(s)

At least one contract of similar nature, complexity and method of construction technology

Requirements for other Partner(s)

At least 25% of similar nature, complexity and method of construction technology

07

Road X-Section

Provision for Dredge filling in embankment.

Dredge filling directly in embankment will not be allowed. Instead of that, sand (FM 0.5) to be stock piled out of the right of way of road by dredge filling or other method. Road embankment to be constructed 150mm thick layer by layer with necessary compaction.

08

Question

Is there any provision for Mobilization Advance?

No, Mobilization Advance will not be provided.

 

 

 

Bipul Chandra Banik

Project Manager

 

 

 

 

 

Memo No. : LGED/CE/KCBPPCR/D-01/2014/36/1(12)                               Dated:     10-06-2014

Copy (Not in order of seniority):

 

  1. Chief Engineer, Local Government Engineering Department (LGED), Dhaka.
  2. Chairman, Bangladesh Power Development Board (BPDB), Dhaka.
  3. Director General, Central Procurement Technical Unit (CPTU), Dhaka. He is requested to publish the above Addendum in CPTU website.
  4. Additional Chief Engineer (Implementation), Local Government Engineering Department (LGED), Dhaka.
  5. Director, Public Relations Department, Bangladesh Power Development Board (BPDB). WAPDA Building, Dhaka. He is requested to publish the above Addendum in BPDB website.

6.      Project Director, Khulna Coal Based Power Plant Connecting Road, BPDB, Biddyut bhavan (8th floor), 1 Abdul Goni Road, Dhaka.

  1. Superintending Engineer (Design), Local Government Engineering Department (LGED), Dhaka.
  2. Executive Engineer (MIS/GIS), LGED, Dhaka. He is requested to publish the above Addendum in LGED website.
  3. Executive Engineer, LGED, Bagerhat.
  4. Upazilla Engineer, LGED, Rampal, Bagerhat.

 

 

Bipul Chandra Banik

                                                                                                                             Project Manager

 

Memo No. : LGED/CE/KCBPPCR/D-01/2014/36/2(12)                               Dated:     10-06-2014

Copy: For information and necessary action to-

 

 

_____________________________________________________

 

_____________________________________________________

 

_____________________________________________________

 

 

 

Bipul Chandra Banik

                                                                                                                             Project Manager