Government of the People’s Republic of Bangladesh

Local Government Engineering Department

Office of the Executive Engineer

District: Satkhira.

 

Memo No : LGED/XEN/Sat/11/913                                                                                                                    Dated  :  02/06/2011

 

 

Invitation for Tender (Works)

Tender Notice Number: 18/2010 - 2011

 

Sealed tenders are hereby invited from the tenders enlisted  under Clause No. 52 (I) & (2)  of  PPR - 2008 for limited tender Method up to Taka 2.00  Crore and as defined in the tender documents for the under mentioned works as per terms and conditions stated below:

Package

 No.

Gr

No

Name of Works

Tender

security

(Tk.)

Time for

completion

( days )

Price of tender document

(Tk.)

 

Important Rural Infrastructure Development Project on Priority Basis

 

 

LGED/XEN/Sat/T-12/84

1

(a) Improvement of  Kazla Alahi Box house-Nalta Tarali  road at Tiger Club via Kazla Donpar, Sardarbari, Kollouck house, Swapan house, Ismail house & Samsu house road  by 25mm BC & 7mm thick seal coat at Ch:00 - 1000m (b) Construction of  1 Nos U-Type drain culvert at Ch:210m on the same road under Kaligonj Upazila, Satkhira (Package No: IRIDP/STK/W-44).

65,000/-

365 days

1,000/-

LGED/XEN/Sat/T-12/85

2

Improvement of  Kazla LGED - Sannashirchalk Bazar road by 25mm BC & 7mm thick seal coat at Ch:2204 - 3204m under Kaligonj Upazila, Satkhira (Package No: IRIDP /STK/W-45).

70,000/-

365 days

1,000/-

LGED/XEN/Sat/T-12/86

3

(a) Improvement of  East Tarali UZR-Kashipbati GPS (Nalta-Tarali UZR road) road  by 25mm BC & 7mm thick seal coat at Ch:2300 - 3300m (b) Construction of  4 Nos U-Type drain culvert at Ch:2420m, Ch:2568m, Ch:2675m & Ch:3282m on the same road under Kaligonj Upazila, Satkhira (Package No: IRIDP/STK/W-46).

75,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/95

4

Improvement of Sathalia Junior High School-Sathalia BOP via Kasaripara road by HBB at Ch:00-1380m under Kaligonj Upazila, Satkhira (Package No: IRIDP/STK/W-51).

53,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/96

5

(a) Improvement of  Dhohakula FRB-Dhohakula R&H (Assasuni) road by BC at Ch:1160-2004m & Link road at Ch:00-200m (b) Construction of  1 No 625x600mm size U-Type drain culvert at Ch:1340m and 6 Nos 375mmx450mm size U-Type drain culvert at Ch:1436m, 1472m, 1536m, 1723m, 1810m  & Link road Ch:180m  on the same road under Sadar Upazila, Satkhira (Package No: IRIDP/STK/W-52).

75,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/97

6

(a) Improvement of Bhomra bazar-WAPDA via Lakkhidari road by BC at Ch:00-1057m (b) Construction of  3 Nos 625x600mm size U-Type drain culvert at Ch:467m, 508m, 817m  and 4 Nos 375mmx450mm size U-Type drain culvert at Ch:245m, 424m, 713m & 750m  on the same road under Sadar Upazila, Satkhira (Package No: IRIDP/STK/W-53).

75,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/98

7

(a) Improvement of Alipur Burir Battala Mosqlue-Talbaria via Rishipara road by BC at Ch:00-1000m (b) Construction of  2 Nos 625x600mm size U-Type drain culvert at Ch:552m & 972m  and 3 Nos 375mmx450mm size U-Type drain culvert at Ch:200m, 340m & 459m  on the same road under Sadar Upazila, Satkhira (Package No: IRIDP /STK/W-54).

60,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/99

8

(a) Improvement of Ellarchor Govt. Primary School-Brahmmorajpur bazar via Balitha road by BC at Ch:00-926m (b) Construction of  3 Nos 625x600mm size U-Type drain culvert at Ch:8m, 370m, 450m  and 4 Nos 375mmx450mm size U-Type drain culvert at Ch:157m, 312m, 395m & 523m  on the same road under Sadar Upazila, Satkhira (Package No: IRIDP /STK/W-55).

75,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/100

9

(a) Improvement of Kayer beel Mosque more-Hawalkhali Primary School road by BC at Ch:570-1960m (b) Construction of  3 Nos 375mmx450mm size U-Type drain culvert at Ch:860m, 1140m & 1577m  and 1 No 1000mmx1300mm size U-Type drain culvert at Ch:960m on the same road under Sadar Upazila, Satkhira (Package No: IRIDP /STK/W-56).

75,000/-

365 days

1,000/-

 

Rural Infrastructure development (Khulna, Bagarhat & Satkhira) Project.

 

 

LGED/XEN/Sat/T-18/101

10

Improvement of Nakipur-Chaltaghata R&H road at Ch:1058-1713m by 25mm carpeting+7mm seal coat under Shyamnagar Upazila, Satkhira.

55,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/102

11

Improvement of Shimulbaria Govt. Primary School -Shimulbaria Dakhinpara Jam-E-Mosque road by BC at Ch:00-437m under Sadar Upazila, Satkhira. (Package No:RIDP(KBS)/VR(BC)-01/ Sat/12)

28,000/-

365 days

750/-

LGED/XEN/Sat/T-18/103

12

Construction of 20.00m Long RCC Bridge on Sriula FRB-Kheaghat via B.D.Chowdhury house (At kheaghat near Shashir Bari) road under Assasuni Upazila, Satkhira (Package No:RIDP (KBS)/ VR(Structure-01/Sat/12).

1,80,000/-

365 days

2,000/-

 

Union Infrastructure development (Khulna, Bagarhat & Satkhira) Project.

 

 

LGED/XEN/Sat/T-18/104

13

Development of Kushlia Hat Growth Centre  under Kaligonj Upazila,Satkhira.(Package No:UIDP(KBS)/GC-01 /Sat/12)

55,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/105

14

Development of Zada Hat Growth Centre under Shyamnagar Upazila, Satkhira. (Package No:UIDP(KBS)/ GC-02/Sat/12)

48,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/106

15

Improvement of Bejorati BC road-Matikomra Primary school road by 25mm thick Carpeting & 7mm thick seal coat at Ch:00-1000m under Debhata Upazila, Satkhira. (Package No:UIDP(KBS)/ VR(BC)-01/Sat/12)

80,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/107

16

Improvement of Sovnali Kheyaghat to Bangdah GC  road  by BC at Ch:4000-4766m under Assasuni Upazila, Satkhira. (Package No:UIDP(KBS)/ VR(BC)-02/Sat/12)

60,000/-

365 days

1,000/-

 

Contd....P/2

 

 

(  2  )

 

Package

 No.

Gr

No

Name of Works

Tender

security

(Tk.)

Time for

completion

( days )

Price of tender document

(Tk.)

LGED/XEN/Sat/T-18/108

17

Improvement of Godaipur - Rautara road at Ch:6222 - 7772.38m under Assasuni Upazila, Satkhira.(Package No:UIDP (KBS)/ VR(BC)-03/Sat/12)

50,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/109

18

Improvement of Senergati - Sarsha road by 25mm BC + 7mm thick seal coat at Ch:3900 - 4860m under Tala Upazila, Satkhira. (Package No:UIDP(KBS)/VR(BC)-04/ Sat/12)

60,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/110

19

Improvement of  Bardal-Baintala road  at Ch:5353 - 5953m & Ch:6509-6961.852m under Assasuni Upazila, Satkhira. (Package No:UIDP (KBS) / VR(HBB)-01/Sat/12)

35,000/-

365 days

750/-

LGED/XEN/Sat/T-18/111

20

(a) Improvement of Rasulpur R&H (Circket House)-Baikari UP via Pairadanga-Aruakhali via Mirgidanga road by BC at Ch:13984-15298m (b) Construction of 4 Nos 375mm x 450mm size U-Type drain culvert at Ch:14,314m, 14426m, 14806m & 14854m on the same road under Sadar Upazila, Satkhira. (Package No:UIDP(KBS)/ UNR(BC)-01/Sat/11-12)

1,10,000/-

365 days

2,000/-

LGED/XEN/Sat/T-18/112

21

(a) Improvement of Tujulpur more to Madhokati via Mohonnpur  road by BC at Ch:00-778m (b) Construction of 3 Nos 375mm x 450mm size U-Type drain culvert at Ch:513m, 563m & 740m on the same road under Sadar Upazila, Satkhira. (Package No:UIDP(KBS)/ VR(BC)-05/Sat/11-12)

65,000/-

365 days

1,000/-

LGED/XEN/Sat/T-18/113

22

Development of  Damdam bazar to Helatala UP road by 25mm BC+7mm seal coat at Ch:890-1890m under Kalaroa Upazila, Satkhira. (Package No:UIDP(KBS)/ UNR(BC)-02/Sat/11-12)

80,000/-

365 days

1,000/-

 

 

 

 

 

 

1.

Method of Tender

:

LTM

2.

Source of Funds

:

GOB

3.

Date, time and place of pre-tender meeting

:

Date: 28th June 2011, Time: 11.00am and

Place: Office of the undersigned

4.

Last date, time and places of selling tender documents

 

:

Date:  5h  July  2011, Time: During Office hours

Places: Office of the undersigned / The concern Upazila Engineer, Upazila: Sadar, Kalaroa, Tala, Assasuni, Kaligonj, Debhata & Shayamnagar, District: Satkhira./ The Executive Engineer, LGED Jessore/The Deputy Commissioner, Satkhira./ The Superintendent of Police, Satkhira./ The Superintending Engineer, LGED, Khulna Region, District: Jessore/The Project Director, Union Infrastructure development/Rural Infrastructure development (Khulna, Bagarhat & Satkhira) Project.. LGED Bhaban, Agargaon Sher-E-Bangla Nagar, Dhaka-1207

 

5.

Last date, time and places of receiving tender

:

Date: 6th  July  2011, Time: 01.00 pm and                                    

Places: Office of the undersigned / The concern Upazila Engineer, Upazila: Sadar, Kalaroa, Tala, Assasuni,Kaligonj, Debhata & Shayamnagar, District: Satkhira./ The Deputy Commissioner, Satkhira./The Superintendent of Police, Satkhira/The Executive Engineer, LGED  Jessore.

6.

Date, time and place of opening of tender

:

Date:  6th   July  2011, Time: 04.00 pm and

Place: Office of the undersigned

 

 

7.

Tender shall be valid for a period of 120 days after tender opening and must be accompanied by the tender security specified above. Interested Tenderer may obtain further information from the office of the undersigned and purchase the tender documents in cash/treasury chalan/ bank draft from the places mentioned above. The Tenderer or their authorized representatives are allowed to attend the opening of tenders. The authority reserves the right to accept or reject any or all the tenders without assigning any reasons whatsoever.

8.

The provisions laid down in the public Procurement Regulation (PRP) 2008, PRP(2nd revision)-2009 & PW-2,PW-3 for procurement of work will be binding upon the contractors

 

9.

In case of official estimate up to take 2.00(Two) crore, the total Quoted amount by the contractor Must not be less or above than 5% of the official estimate, otherwise the tender shall be rejected .

 

This invitation for tender is available on the website http/www.lged.gov.bd

 

 

 

(Md. Anwarul Islam)

Executive Engineer.

Ph:0471-63413

 

 

Memo No : LGED/XEN/Sat/ 11/913/1(100)                                                                                                                         Dated  : 02/06/2011

 

                Copy forwarded for kind information & necessary action to :

 

1.             The Superintending Engineer, LGED, Khulna Region, District: Jessore.

2.             The Project Director, Important Rural Infrastructure Development Project on Priority Basis/ Rural Infrastructure

development (Khulna, Bagarhat & Satkhira) Project/ Union Infrastructure development (Khulna, Bagarhat &

Satkhira) Project.. LGED Bhaban, Agargaon Sher-E-Bangla Nagar, Dhaka-1207

3.             The Deputy Commissioner, District: Satkhira.

4.             The Chief Executive Officer, Zilla Parishad, Satkhira.

5.             The Superintendent of Police, District: Satkhira.

6.             The Mayor, Pourashava, Satkhira.

7.             The Executive Engineer, LGED, District:_____________________.

8.             The Executive Engineer, RHD/PHE/BWDB, Satkhira.

9.             The Upazila Engineer, LGED, Upazila : _________________, Satkhira.

10.           Assistant Engineer, LGED, GIS Unit, Level - 4, LGED Bhaban, Agargaon, Dhaka-1207.

                He is requested to publish  the IFT at the LGED web site.

11.           The Editor .......................................................................  He is requested to publish the tender notice.

12.           Notice Board (All).

 

 

 

( G. M. Mujibor Rahman )

Senior Assistant Engineer.

LGED, Satkhira.