Invitation for Tender (Works)
Sealed tenders are hereby
invited from the tenders enlisted under Clause No. 52 (I) & (2) of PPR - 2008 for limited tender Method up to
Taka 2.00 Crore and as defined in the
tender documents for the under mentioned works as per terms and conditions
stated below:
Package No. |
Gr No |
Name
of Works |
Tender
security
(Tk.) |
Time for completion ( days ) |
Price of tender document (Tk.) |
|
Rehabilitation of AILA Affected Rural
Infrastructure Project |
|
|
||
RAILA/SRT/W-01 |
1 |
Rehabilitation of Noabenki-Munshigonj-Harinagar-Vetkhali-Zadahat-Nurnagar
hat-ZR Khanpur road at Ch:00-8548m under Shyamnagar Upazila, Satkhira. |
1,70,000/- |
365 days |
2,000/- |
RAILA/SRT/W-02 |
2 |
Rehabilitation of
Noabenki-Munshigonj-Harinagar-Vetkhali-Zadahat-Nurnagar hat-ZR Khanpur road
at Ch:8548-15500m under Shyamnagar Upazila, Satkhira. |
1,30,000/- |
365 days |
2,000/- |
RAILA/SRT/W-03 |
3 |
Rehabilitation of Kalbari hat-Nildumur hat road at Ch:3200-5880m
under Shyamnagar Upazila, Satkhira. |
1,20,000/- |
365 days |
2,000/- |
RAILA/SRT/W-04 |
4 |
Rehabilitation of Nakipur-Kashimari-Jhapali road at Ch: 9500-12250m
under Shyamnagar Upazila, Satkhira. |
1,45,000/- |
365 days |
2,000/- |
RAILA/SRT/W-05 |
5 |
Rehabilitation of Ramjannagar UP (Manikkhali) -Ramjannagar
Kheyaghat-Paranpur hat road at Ch:1320-3420m under Shyamnagar Upazila,
Satkhira. |
1,00,000/- |
365 days |
2,000/- |
RAILA/SRT/W-06 |
6 |
Rehabilitation of Ramjannagar UP (Manikkhali) -Ramjannagar Kheyaghat
- Paranpur hat road at Ch:3420-5500m under Shyamnagar Upazila, Satkhira. |
1,00,000/- |
365 days |
2,000/- |
RAILA/SRT/W-07 |
7 |
Rehabilitation of Iswaripur-Gumantoli-Jabakhali hat road at Ch:4230-7900m under Shyamnagar
Upazila, Satkhira. |
60,000/- |
365 days |
1,000/- |
RAILA/SRT/W-08 |
8 |
Rehabilitation of Bardal UP to Dargapur UP Office Via Tekerkhuti
Kheyaghat road at Ch:1910-2850m under Assasuni Upazila, Satkhira. |
65,000/- |
365 days |
1,000/- |
RAILA/SRT/W-09 |
9 |
Rehabilitation of Bardal UP to Dargapur UP Office Via Tekerkhuti
Kheyaghat road at Ch:2850-4685m under Assasuni Upazila, Satkhira. |
1,30,000/- |
365 days |
2,000/- |
RAILA/SRT/W-10 |
10 |
Rehabilitation of Bardal UP to Dargapur UP Office Via Tekerkhuti
Kheyaghat road at Ch:4685-6595m under Assasuni Upazila, Satkhira. |
1,00,000/- |
365 days |
2,000/- |
RAILA/SRT/W-11 |
11 |
Rehabilitation of Kallyanpur Northpara Late Mozdul Haque road at Ch:00-2100m under Assasuni Upazila, Satkhira. |
1,90,00000/- |
365 days |
3,000/- |
RAILA/SRT/W-12 |
12 |
Rehabilitation of Khazra UP-Bardal GC road at Ch:00-2010m under
Assasuni Upazila, Satkhira. |
1,40,000/- |
365 days |
2,000/- |
RAILA/SRT/W-13 |
13 |
Rehabilitation of Khazra UP-Bardal GC road at Ch:2010-4250m under
Assasuni Upazila, Satkhira. |
1,35,000/- |
365 days |
2,000/- |
RAILA/SRT/W-14 |
14 |
Rehabilitation of Khazra UP-Bardal GC road at Ch:4250-6330m under
Assasuni Upazila, Satkhira. |
1,40,000/- |
365 days |
2,000/- |
RAILA/SRT/W-15 |
15 |
Rehabilitation of Khazra UP-Bardal GC road at Ch:6330-8180m under
Assasuni Upazila, Satkhira. |
1,35,000/- |
365 days |
2,000/- |
Contd......P/2
( 2 )
|
|
|
|
|
|
|||
1. |
Tendering
Method
|
: |
LTM |
|||||
2. |
Source
of Funds
|
: |
GOB |
|||||
3. |
Date,
time and place of pre-tender meeting |
: |
Date: 21/11/ 2011, Time:
11.00am and Place: Office of the undersigned |
|||||
4. |
Last
date, time and places of selling tender documents |
: |
Date: 28/11/ 2011, Time:
During Office hours Places: Office of the
undersigned / The concern Upazila Engineer, Upazila: Assasuni/ Shyamnagar,
District: Satkhira./ The Executive Engineer, LGED Khulna/The Deputy
Commissioner, Satkhira./ The Superintendent of Police, Satkhira. / The Project Director, Rehabilitation of AILA Affected Rural Infrastructure Project(RAARIP),
LGED Bhaban,
Agargaon Sher-E-Bangla Nagar, Dhaka-1207 |
|||||
5. |
Last
date, time and places of receiving tender |
: |
Date: 29/11/ 2011, Time: 01.00 pm and Places: Office of the
undersigned / The Upazila Engineer, Upazila: Assasuni/Shyamnagar, District:
Satkhira./ The Deputy Commissioner, Satkhira./The Superintendent of Police,
Satkhira/The Executive Engineer, LGED |
|||||
6 |
Date,
time and place of opening of tender |
: |
Date: 29/11/2011, Time: 04.00
pm and Place: Office of the undersigned |
|||||
7. |
Tender shall be valid for
a period of 120 days after
tender opening and must be accompanied by the tender security specified
above. Interested Tenderer may obtain further information from the office of
the undersigned and purchase the tender documents in cash/treasury chalan/
bank draft from the places mentioned above. The Tenderer or their authorized
representatives are allowed to attend the opening of tenders. The authority
reserves the right to accept or reject any or all the tenders without
assigning any reasons whatsoever. |
|||||||
8. |
The provisions laid down
in the public Procurement Regulation (PRP) 2008, PRP(2nd
revision)-2009 & PW-2,PW-3 for procurement of work will be binding upon
the contractors |
|||||||
9. |
In case of official
estimate up to take 2.00(Two) crore, the total Quoted amount by the
contractor Must not be less or above than 5% of the official estimate,
otherwise the tender shall be rejected . |
|||||||
This invitation for tender
is available on the website http/www.lged.gov.bd & cptu website www.cptu.gov.bd
( Md. Anwarul Islam )
Executive Engineer
Ph: +88047163413
email. Xen.satkhira @ gmail.com
Memo No : LGED/XEN/Sat/ 11 / 1798 /1(100) Dated :
25-10-2011
Copy forwarded for kind information & necessary
action to :
1. The
Director General, CPTU, IMED, Block-12, 2nd Floor, Sher-E-Bangla Nagar, Dhaka-1207
2. The Superintending Engineer,
LGED,
3. The Project Director, Rehabilitation of AILA Affected Rural Infrastructure Project(RAARIP),
LGED
Bhaban, Agargaon, Sher-E-Bangla Nagar, Dhaka-1207
4. The Deputy Commissioner, District: Satkhira.
5. The Chief Executive
Officer, Zilla Parishad, Satkhira.
6. The Superintendent
of Police, District: Satkhira.
7. The Executive Engineer, LGED,
District:_____________________.
8. The Executive Engineer,
RHD/PHE/BWDB, Satkhira.
9. The Mayor, Pourashava, Satkhira.
10. The Upazila Engineer, LGED, Upazila :
_________________, Satkhira.
11. Assistant Engineer, LGED, GIS Unit,
Level - 4, LGED Bhaban, Agargaon, Dhaka-1207.
He is requested to publish the IFT at the LGED web site.
12. The Editor
....................................................................... He is requested to publish the tender notice.
13. Mr./Mrs. ..........................................................................
14. Notice Board (All).
( G. M. Mujibor Rahman )
Senior Assistant Engineer.
LGED, Satkhira.