Government of the People’s Republic of
Bangladesh
Local
Government Engineering Department
Office of the Executive Engineer
District: Satkhira.
Memo No : LGED/XEN/Sat/2215 Dated : 14 /
12/ 2011
Invitation for Tender (Works)
Sealed tenders are hereby
invited from the tenders enlisted under Clause No. 52 (I) & (2) of PPR - 2008 for limited tender Method up to
Taka 2.00 Crore and as defined in the
tender documents for the under mentioned works as per terms and conditions
stated below:
Package No. |
Gr No |
Name of
Works |
Tender security
(Tk.) |
Time for completion ( days ) |
Price of tender document (Tk.) |
|||
|
Rehabilitation of AILA Affected Rural Infrastructure Project |
|
|
|||||
RAILA/SRT/W-11 |
1 |
Rehabilitation of Kallyanpur
Northpara Late Mozdul Haque road at Ch:00-2100m under Assasuni Upazila, Satkhira. |
1,90,000/- |
365 days |
3,000/- |
|||
RAILA/SRT/W-14 |
2 |
Rehabilitation of Khazra
UP-Bardal GC road at Ch:4250-6330m under Assasuni Upazila, Satkhira. |
1,40,000/- |
365 days |
2,000/- |
|||
RAILA/SRT/W-15 |
3 |
Rehabilitation of Khazra
UP-Bardal GC road at Ch:6330-8180m under Assasuni Upazila, Satkhira. |
1,35,000/- |
365 days |
2,000/- |
|||
RAILA/SRT/W-16 |
4 |
Rehabilitation of
Noabenki-Munshiganj-Harinagar-Vetkhali-Zada hat-Noornagar road at Ch:18800-19800m
under Shyamnagar Upazila, Satkhira. |
90,000/- |
365 days |
1,000/- |
|||
|
Rural Infrastructure development (Khulna, Bagarhat & Satkhira)
Project |
|
|
|||||
RIDP(KBS)/GC-1 |
5 |
Development of Patkelghata hat (GC) under Tala Upazila, Satkhira. |
55,000/- |
365 days |
1,000/- |
|||
RIDP(KBS)/UZR(BC)/ -01/Sat/12 |
6 |
Improvement of Subornabad
GC-Bangdah GC (Sadar) road by 25mm thick Dense Carpeting at Ch: 300-1300m
under Debhata Upazila, Satkhira. |
1,00,000/- |
365 days |
2,000/- |
|||
|
Union Rural Infrastructure development (Khulna, Bagarhat & Satkhira)
Project |
|
||||||
UIDP(KBS)/UNR/ Structure-01/Sat/11-12 |
7 |
Construction of 2-Vent
3.50x3.50m RCC Box culvert at Ch:4m on the Tentulia UP office(R&H)-Ghona
Bazar Via Dewani para Bazar road under
Tala Upazila, Satkhira. |
40,000/- |
365 days |
750/- |
|||
UIDP(KBS)/UNR/ Structure-02/Sat/11-12 |
8 |
Construction of 2-Vent
3.50x3.50m RCC Box culvert at Ch:5480m on the Kasighata Bazar
(R&H)-Mohandi Bazar Via Khalilnagor UP road under Tala Upazila, Satkhira. |
40,000/- |
365 days |
750/- |
|||
UIDP(KBS)/VR(BC)/ -18/Sat/10-11 |
9 |
Improvement of Ghalghalia
Uttarpara Jame Mosque-Bhatshala Shammelani High School (Rouf Khandaker
house-Battala) road by 25mm thick BC + 7mm thick Seal Coat at Ch: 00-1205m
under Debhata Upazila, Satkhira. |
1,20,000/- |
365 days |
2,000/- |
|||
UIDP(KBS)/VR(HBB)/ -03/Sat/11-12 |
10 |
Improvement of East
Kadakati (Parish Mondol ghate)-Katakhali WAPDA Via Khagurdanga road at
Ch:280-1350.45m by HBB under Assasuni Upazila, Satkhira. |
18,000/- |
365 days |
500/- |
|||
UIDP(KBS)/VR(BC)/ -07/Sat/11-12 |
11 |
Improvement of Tentulia
Bazar-WAPDA road at Ch:2100-2550m by BC under Kaligonj Upazila, Satkhira. |
37,000/- |
365 days |
750/- |
|||
UIDP(KBS)/UNR(RCC)/-03/Sat/11-12 |
12 |
Improvement of Kakbasia
bazar-Monipur Khayghat-Khazra UP road by R.C.C at Ch: 2753-3296m under
Assasuni Upazila, Satkhira. |
65,000/- |
365 days |
1,000/- |
|||
UIDP(KBS)/VR(BC)/-06/Sat/11-12 |
13 |
(a) Improvement of Lohakura
FRB to Langaljhara Bazar road by dance carpeting at Ch: 00-780m (b)
Construction of 625x600mm size U-Type drain on same road at Ch:65m under
Kalaroa Upazila, Satkhira. |
70,000/- |
365 days |
1,000/- |
|||
|
Important Rural Infrastructure Development Project on Priority Basis |
|
|
|||||
IRIDP/STK/ W-54 |
14 |
(a)
Improvement of Alipur Burir Battala Mosqlue-Talbaria via Rishipara road by BC
at Ch:00-1000m (b) Construction of 2
Nos 625x600mm size U-Type drain culvert at Ch:582m & 972m and 3 Nos 375mmx450mm size U-Type drain
culvert at Ch:200m, 340m & 459m on
the same road under Sadar Upazila, Satkhira |
75,000/- |
365 days |
1,000/- |
|||
IRIDP/STK/W-44 |
15 |
(a)
Improvement of Kazla Alahi Box
house-Nalta Tarali road at Tiger Club
via Kazla Donpar, Sardarbari, Konnock house, Swapan house, Ismail house &
Samsu house road by 25mm BC & 7mm
thick seal coat at Ch:00 - 1000m (b) Construction of 1 Nos U-Type drain culvert at Ch:210m on
the same road under Kaligonj Upazila, |
76,000/- |
365 days |
1,000/- |
|||
IRIDP/STK/ W-45 |
16 |
Improvement
of Kazla LGED - Sannashirchalk Bazar
road by 25mm BC & 7mm thick seal coat at Ch:2204 - 3204m under Kaligonj
Upazila, Satkhira |
80,000/- |
365 days |
1,000/- |
|||
IRIDP/STK/W-46 |
17 |
(a)
Improvement of East Tarali
UZR-Kashipbati GPS (Nalta-Tarali UZR road) road by 25mm BC & 7mm thick seal coat at
Ch:2300 - 3300m (b) Construction of 4
Nos U-Type drain culvert at Ch:2420m, Ch:2568m, Ch:2675m & Ch:3282m on
the same road under Kaligonj Upazila, Satkhira |
90,000/- |
365 days |
1,000/- |
|||
IRIDP/STK/W-57 |
18 |
(a) Improvement of Bag
Nalta-Shanpukur H/O Sukendu (Nalta Chowmohoni-Ghona) road By 25mm BC &
7mm Seal Coat at Ch:00-505m (b) Construction of 2 Nos 625mm x 600mm U-Type
drain at Ch:192m & Ch:394m on the same road under Kaligonj Upazila,
Satkhira. |
35,000/- |
365 days |
750/- |
|||
IRIDP/STK/W-08 |
19 |
Improvement of Bohera Bazar
(RHD)-Ellarchar Bazar-Bangdh GC (Sadar) road by BC+7mm seal coat at
Ch:3100-3602m under Debhata Upazila, Satkhira. |
55,000/- |
365 days |
1,000/- |
|||
IRIDP/STK/W-51 |
20 |
Improvement of Sathalia
Junior High School-Sathalia BOP via Kasaripara road by HBB at Ch:00-1380m
under Kaligonj Upazila, Satkhira. |
60,000/- |
365 days |
1,000/- |
|||
|
|
|
|
|
|
|||
|
|
|
|
|||||
1. |
Tendering
Method
|
: |
LTM |
|||||
2. |
Source
of Funds
|
: |
GOB |
|||||
3. |
Date,
time and place of pre-tender meeting |
: |
Date : 08/01/2012, Time: 11.00am and Place : Office of the
undersigned |
|||||
4. |
Last
date, time and places of selling tender documents |
: |
Date : 16/01/2012, Time: During Office hours Places: Office of the
undersigned / The concern Upazila Engineer, Upazila: Sadar/ Kalaroa/
Tala/Assasuni/Kaligonj/Debhata/Shyamnagar/, District: Satkhira./ The
Executive Engineer, LGED Khulna/The Deputy Commissioner, Satkhira./ The
Superintendent of Police, Satkhira. / The
Project Director, Rehabilitation of AILA
Affected Rural Infrastructure Project(RAARIP)/ Rural Infrastructure
development (Khulna, Bagarhat & Satkhira) Project/Union Rural
Infrastructure development (Khulna, Bagarhat & Satkhira) Project/The
Superintendent Engineer, Khulna Region, Jessore. |
|||||
5. |
Last
date, time and places of receiving tender |
: |
Date :
17/01/2012, Time: 01.00 pm
and Places: Office of the
undersigned /The Upazila Engineer, Upazila: Sadar/ Kalaroa/
Tala/Assasuni/Kaligonj/Debhata/Shyamnagar/, District: Satkhira./ The Deputy
Commissioner, Satkhira./The Superintendent of Police, Satkhira/The Executive
Engineer, LGED Khulna/ The
Superintendent Engineer, Khulna Region, Jessore. |
|||||
6 |
Date,
time and place of opening of tender |
: |
Date : 17/01/2012, Time: 04.00 pm and Place : Office of the
undersigned |
|||||
7. |
Tender shall be valid for a
period of 120 days after
tender opening and must be accompanied by the tender security specified
above. Interested Tenderer may obtain further information from the office of
the undersigned and purchase the tender documents in cash/treasury chalan/
bank draft from the places mentioned above. The Tenderer or their authorized
representatives are allowed to attend the opening of tenders. The authority
reserves the right to accept or reject any or all the tenders without
assigning any reasons whatsoever. |
|||||||
8. |
The provisions laid down in
the public Procurement Regulation (PRP) 2008, PRP(2nd
revision)-2009 & PW-2,PW-3 for procurement of work will be binding upon
the contractors |
|||||||
9. |
In case of official
estimate up to take 2.00(Two) crore, the total Quoted amount by the
contractor Must not be less or above than 5% of the official estimate,
otherwise the tender shall be rejected . |
|||||||
This invitation for tender is
available on the website http/www.lged.gov.bd & cptu website www.cptu.gov.bd
( Md. Anwarul Islam )
Executive Engineer
Ph: +88047163413
email. Xen.satkhira @ gmail.com
Memo No : LGED/XEN/Sat/ Dated :
Copy forwarded for kind information & necessary
action to :
1. The
Director General, CPTU, IMED, Block-12, 2nd Floor, Sher-E-Bangla Nagar, Dhaka-1207
2. The Superintending Engineer,
LGED, Khulna Region, District: Jessore.
3. The Project Director, Rehabilitation of AILA Affected Rural Infrastructure Project(RAARIP)
4. The Project Director, Rural Infrastructure
development (Khulna, Bagarhat & Satkhira) Project.
5. The Project Director, Union Rural Infrastructure development (Khulna, Bagarhat &
Satkhira) Project.
6. The Project Director,Important Rural Infrastructure Development Project on Priority Basis, LGED Bhaban, Agargaon Sher-E-Bangla
Nagar,
Dhaka-1207
7. The Deputy Commissioner, District: Satkhira.
8. The
Chief Executive Officer, Zilla Parishad, Satkhira.
9. The
Superintendent of Police, District: Satkhira.
10. The Executive Engineer, LGED,
District:_____________________.
11. The Executive Engineer, RHD/PHE/BWDB,
Satkhira.
12. The Mayor, Pourashava, Satkhira.
13. The Upazila Engineer, LGED, Upazila :
_________________, Satkhira.
14. Assistant Engineer, LGED, GIS Unit,
Level - 4, LGED Bhaban, Agargaon, Dhaka-1207.
He is requested to publish the
IFT at the LGED web site.
15. The Editor,
....................................................................... He is requested to publish the tender notice.
16. Mr./Mrs.
..........................................................................
17. Notice Board (All).
( G. M. Mujibor Rahman )
Senior Assistant Engineer.
LGED, Satkhira.