Government of the People’s
Republic of
Local Government Engineering
Department
Office of the Executive Engineer
District: Satkhira.
Memo No : LGED/XEN/Sat/12/328 Dated :
13/02/2012
Invitation for Tender (Works)
Sealed tenders are hereby
invited from the tenders enlisted under Clause No. 52 (I) & (2) of
PPR-2008 for limited tender Method up to Taka 2.00 Crore and as defined
in the tender documents for the under mentioned works as per terms and
conditions stated below:
Package No. |
Gr No |
Name of
Works |
Tender security
(Tk.) |
Time
for completion ( days
) |
Price
of tender document (Tk.) |
|
Union Infrastructure
development ( |
|
|
||
UIDP(KBS)/VR/Structure-03/Sat/11-12 |
1 |
Construction of 4x4.5mx4.5m
RCC Box Culvert at Ch: 1000m on Munshigonj Bazar - Grage Hat road under
Shyamnagar Upazila, Satkhira. |
1,10,000.00 |
365 days |
2,000.00 |
UIDP(KBS)/
UNR/Structure-03/Sat/11-12 |
2 |
Construction of 3x4.0mx4.0m
RCC Box culvert on Nowapara UP - Budhata GC via Chandpur Atapur road over
Darer Khal at Ch: 5+800km under Debhata Upazila, Satkhira. |
65,000.00 |
365 days |
1,000.00 |
UIDP(KBS)/GC-03/ SAT/11-12 |
3 |
Development
of Kadakati GC under Assasuni Upazila, Satkhira. |
55,000.00 |
365 days |
1,000.00 |
|
Important Rural
Infrastructure Development Project on Priority Basis |
|
|
||
IRIDP/STK/W-83 |
4 |
(a)
Improvement of Noabanki - Munshigonj - Harinagar - Vetkhali - Jada hat -
Nurnagar-Khanpur ZR road by BC at Ch:24240m-25278m (b) Construction of 2Nos
0.600mx0.900m Drain culvert at Ch:24390m & Ch:24840 on the same road
under Shyamnagar
Upazila, Satkhira. |
1,10,000.00 |
365 days |
2,000.00 |
IRIDP/STK/W-102 |
5 |
Improvement
of Bikrompur FRB - Hizalde Bazar road by 25mm danse carpeting at
Ch:1750-2470m
road under
Kalaroa Upazila, Satkhira. |
75,000.00 |
365 days |
1,000.00 |
IRIDP/STK/W-103 |
6 |
(a)
Improvement of Uzirpur - Chandkhali road by 25mm danse carpeting at
Ch:00-1200m (b) Construction of 2 Nos
0.625mx0.600m U-Type drain culvert at Ch: 540m & 780m on the same road under Kaligonj Upazila, Satkhira. |
80,000.00 |
365 days |
1,000.00 |
IRIDP/STK/W-104 |
7 |
Improvement
of Bashtala Bazar - Uzirpur Bazar via
Chandulia & Thalna road by 25mm danse carpeting at Ch: 2000-4000m under
Kaligonj Upazila, Satkhira. |
1,50,00.00 |
365 days |
2,000.00 |
IRIDP/STK/W-105 |
8 |
(a)
Improvement of Jaforpur - Tetulia Bazar via Tetulia Bazar to Borea Assarayan
Project road by 25mm danse carpeting at Ch: 00-2000m (b) Construction of 3
Nos 0.600mx1.125m Box drain culvert at Ch: 30m, 295m & 1735m on the same
road under Kaligonj Upazila, Satkhira. |
1,35,000.00 |
365 days |
2,000.00 |
IRIDP/STK/W-106 |
9 |
Improvement
of Kazla LGED - Sannashirchalk Bazar road by 25mm danse carpeting at Ch:
3204-4694m under Kaligonj Upazila, Satkhira. |
1,10,000.00 |
365 days |
2,000.00 |
Rural Infrastructure Development
( |
|||||
RIDP(KBS)/VR(BC)-03/ SAT/12 |
10 |
(a)
Improvement of Solimpur A.K.Khan High School more - Jugikhali Bazar via H/O
Hazi Nasir Uddin (Solimpur A.K.Khan High School more - Jugikhali Bazar - H/O
Saydali Morol at Torulia via H/O Hazi Nasir Uddin) road by 25mm danse
carpeting at Ch:00-850m (b) Construction of 4Nos 0.625mx0.600m U-Type drain
culvert at Ch: 210m, 355m & 580m on the same road under Kalaroa Upazila,
Satkhira. |
75,000.00 |
365 days |
1,000.00 |
1. |
Method
of Tender
|
: |
LTM |
2. |
Source
of Funds
|
: |
GOB |
3. |
Date,
time and place of pre-tender meeting |
: |
Date : 28th February, 2012,
Time: 11.00am and Place: Office of the undersigned |
4. |
Last
date, time and places of selling tender documents |
: |
Date: 5th March, 2012, Time: During Office hours Places: Office of the
undersigned/The concern Upazila Engineer, Upazila:
Shyamnagar/Debhata/Kaligonj/Kalaroa & Assasuni, District: Satkhira./The
Executive Engineer, LGED Jessore/The Deputy Commissioner, Satkhira/The
Superintendent of Police, Satkhira/The Project Director, Union Infrastructure
development (Khulna, Bagarhat & Satkhira) Project/Rural Infrastructure Development (Khulna, Bagarhat &
Satkhira)Project, LGED Bhaban, Agargaon,
Sher-E-Bangla Nagar, Dhaka-1207/ The Superintending Engineer, Khulna Region, LGED Bhaban: Jessore. |
Contd. Page No-02
Page No-02
5. |
Last date, time and places of receiving tender |
: |
Date: 6th March,
2012, Time: 01.00 pm and Places:
Office of the undersigned/The Upazila Engineer, Upazila: Shyamnagar/Debhata/
Kaligonj/ Kalaroa & Assasuni, District: Satkhira, District: Satkhira./The
Deputy Commissioner, Satkhira./The Superintendent of Police, Satkhira/The
Executive Engineer, LGED Jessore. |
6. |
Date, time and place of opening of tender |
: |
Date: 6th March, 2012,
Time: 04.00 pm and Place: Office of the
undersigned |
7. |
Tender
shall be valid for a period of 120 days
after tender opening and must be accompanied by the tender security specified
above. Interested Tenderer may obtain further information from the office of
the undersigned and purchase the tender documents in cash/treasury chalan/
bank draft from the places mentioned above. The Tenderer or their authorized
representatives are allowed to attend the opening of tenders. The authority
reserves the right to accept or reject any or all the tenders without
assigning any reasons whatsoever. |
||
8. |
The
provisions laid down in the public Procurement Regulation (PRP) 2008, PRP(2nd
revision)-2009 & PW-2,PW-3 for procurement of work will be binding upon
the contractors |
||
9. |
In
case of official estimate up to take 2.00(Two) crore, the total Quoted amount
by the contractor Must not be less or above than 5% of the official estimate,
otherwise the tender shall be rejected . |
This
invitation for tender is available on the website http/www.lged.gov.bd
(Md. Anwarul Islam)
Executive Engineer.
Ph: +88047163413
email. xen.satkhira
@ gmail.com &
xen.Satkhira@lged.gov.bd.
Memo No : LGED/XEN/Sat/ 12/328 Dated :13/02/2012
Copy
forwarded for kind information & necessary action to :
01. |
The Superintending Engineer, LGED, |
02. |
The Project Director, Union Infrastructure
development ( |
03. |
The Project Director, Important Rural
Infrastructure Development Project on Priority Basis. |
04. |
The Project Director, Rural Infrastructure
Development ( |
05. |
The Deputy Commissioner, District: Satkhira. |
06. |
The Chief Executive Officer, Zilla Parishad, Satkhira |
07. |
The Superintendent of
Police, District: Satkhira. |
08. |
The Executive Engineer, LGED,
District:_____________________. |
09. |
The Executive Engineer, RHD/PHE/BWDB,
Satkhira. |
10. |
The Mayor, Pourashava, Satkhira. |
11. |
The Upazila Engineer, LGED, Upazila :
_________________, Satkhira. |
12. |
Assistant Engineer,LGED, GIS Unit,Level-4,
LGED Bhaban, Agargaon, Dhaka-1207. He is requested to publish the IFT at the
LGED web site. |
13. |
The Editor,
....................................................................... He is requested to publish the tender
notice. |
14. |
Mr./Mrs.
.......................................................................... |
15. |
Notice Board (All). |
(K M
Faruk Hossain)
Senior
Assistant Engineer.
LGED, Satkhira.