Government of the People’s Republic of Bangladesh
Local
Government Engineering Department
Office of the Executive
Engineer
District-Sylhet.
Memo
No.LGED/XEN/SYL/M/05-09/2010/583 Date : 01/03/11.
Sealed tenders are hereby invited from the eligible
tenderers as defined in the tender documents for the under mentioned list of
works as per terms and conditions stated below :
Sl No. |
Package
No. |
Name
of Works |
Tender security (Tk.) |
Comple-tion time
(days) |
Price
of
tender
documents
(Tk) |
|
||
|
|
GOB Maintenance |
|
|
|
|
||
01 |
GOB/Maint/ Syl/W-54 |
Periodic Maintenance of
RHD-Jugirgaon-Jangail-Kaligonjbazar road from ch: 00-725m under Sylhet Sadar Uapzila District:Sylhet (ID
No 691524074) |
20,000/- |
45 |
500/- |
|
||
02 |
GOB/Maint/ Syl/W-55 |
Periodic Maintenance of
Badaghat-Mogalgaon UP Office road from ch: 9650-10500m under Sylhet Sadar
Uapzila District:Sylhet (ID No
691523010) |
50,000/- |
60 |
750/- |
|
||
|
|
Name of
Project : RRMIP |
|
|
|
|||
03 |
RRMIP/ Syl/
W-80 |
Improvement of RHD-Mullapur village
road from ch: 00-140m under Beanibazar
Uapzila District:Sylhet (ID No
691175207) . |
25,000/- |
120 |
750/- |
|||
04 |
RRMIP/ Syl/
W-82 |
Improvement of Kawlibag road from ch:
00-140m under Beanibazar Uapzila
District:Sylhet (ID No 691175141)
. |
25,000/- |
120 |
750/- |
|||
05 |
RRMIP/ Syl/
W-93 |
Improvement of Jalalabad UP-Kalirgaon
Bazar road from ch: 3550-4650m under Sylhet Sadar Uapzila District:Sylhet (ID
No 691623005) . |
80,000/- |
150 |
1000/- |
|||
06 |
RRMIP/ Syl/
W-94 |
a) Improvement of Jalalabad
UP-Kalirgaon Bazar road from ch: 4650-5650m by Earth filling work (b)
Construction of 2 Nos. Drainage Culvert at Ch: 5000m & 5600m. (c)
Construction of 1x2.00x2.00m RCC Box Culvert at Ch: 5120m. (d) Construction of 1x2.50x2.50m RCC Box
Culvert at Ch: 5210m. (e) Construction of 1x3.50x3.50m RCC Box Culvert at Ch:
5324m. under Sylhet Sadar Uapzila District:Sylhet (ID No 691623005) . |
60,000/- |
150 |
1000/- |
|||
|
|
Name of
Project :IRIDP |
|
|
|
|||
07 |
RRMIP/ Syl/
W-144 |
a) Improvement of Tazpur-Baruda-Saropar road from ch:
00-1200m & Construction of 1 No.
Drainage Culvert at Ch: 840m. (b) Construction of 2 Nos 1x3.50x3.50m RCC Box
Culvert at Ch: 450m & 1140m under Beanibazar Uapzila District:Sylhet (ID
No 691174035) . |
1,20,000/- |
150 |
1000/- |
|||
01. |
Source of Fund |
: |
GOB |
|||||
02. |
Date, time and place of
pre-tender meeting |
: |
10-03-2011,Time: 12:00 noon & and
Place : office of the undersigned
|
|||||
03. |
Last date, time and places of selling tender
documents |
: |
20-03-2011, Time: Up to
5.00 pm and a) Office of The Superintending
Engineer,LGED,Sylhet Region,Sylhet b) Office of The Project Director, RRMIP,LGED Bhabon,Dhaka . c) Office of
The Deputy Commissioner, Sylhet d) Office of
The Superintendent of Police,
Sylhet. e) Office of
The Executive Engineer, LGED,Moulavibazar. f) Office of The Undersigned g) Office of The Concerned Upazila Engineer,LGED,Beanibazar,Sylhet
Sadar,District: Sylhet |
|||||
04. |
Last date, time and places of receiving tender
documents. |
: |
21-03-2011, Time: 1:00
pm and a) Office of The Deputy Commissioner,
Sylhet. b) Office of The Superintendent of Police,Sylhet. c) Office of the undersigned. d) Office of The Concern Upazila
Engineer,LGED,Beanibazar,Sylhet Sadar,District: Sylhet |
|||||
05. |
Date, time and place of opening of tender |
: |
21-03-2011,Time: 4:00pm and office of the undersigned. |
|||||
06. |
Regarding
Lottery |
: |
For the work of all 07 (Seven)
groups,the total quoted amount by the tenderer must not be less or above than
5% of the official estimate.If more than one tenderer will quoted their
total tender price at the lowest rate
then the decision of tenders will be taken by lottery. |
|||||
07. |
Additional
terms & Condition |
: |
(a) If any provision or proposal of sub-contract will not be
incorporated in to the submitted tender by the tenderers then no sub
contracting will be allowed after contract agreement. (b) The
amount of salvaged materials is fixed and it will never be
changed/altered.The price of salvaged
materials will be deducted from the running/final bills as per rule. |
|||||
Contd/ P-2
-2-
8. |
Tender shall be valid for a period of
120 days after bid opening and must be accompanied by the tender
security specified above. Interested tenderer may obtain further information
from the office of the undersigned and purchase the tender documents in
cash/treasury chalan/ bank draft from the places mentioned above. The
tenderer or their authorized representatives are allowed to attend the
opening of tenders. The authority reserves the right to accept or reject any
or all the tenders without assigning any reasons whatsoever. |
09. |
The ivitation for tender is available
on the website: www.lged.gov.bd. |
(Md.Aminul Islam)
Executive Engineer
Tel: 0821-716116
Memo No.LGED/XEN/SYL/M/05-09/2010/583/1(24) Date :01/03/11.
Copy forwarded for kind information and
Circulation to :
1. The Superintending
Engineer (Admin),LGED,LGED Bhaban, Agargaon, Dhaka-1207.
2. The Superintending Engineer,
LGED, Sylhet,Region,District: Sylhet.
3. The Project Director, LGED, RRMIP/IRIDP,LGED HQ, Dhaka.
4. The Deputy Commissioner,
District: Sylhet.
5. The Superintendent of
Police, District: Sylhet.
6. The Executive Engineer,
LGED, District: Moulavibazar/Habigonj/Sunamgonj.
7. The Upazila Engineer,
LGED,Upazila : ------------------------------ District: Sylhet.
8. The
Editor,The Daily Financial Express /The Daily Manabzamin.He is requested
to publish the above Tender Notice in the
widely circulated News paper for one day on or before 03-03-2011 and sending
2 (two) copies of News paper
with published advertisement to the
office of the undersigned.
9. Notice Board (All).
(Md.Aminul
Islam)
Executive Engineer