Government of the People’s
Republic of Bangladesh
Local Government Engineering
Department
Office of the Executive Engineer
District: Satkhira.
Memo No : LGED/XEN/Sat/12/1367 Dated : 20/06/12
Sealed tenders are hereby
invited from the eligible Tenderers as defined in the tender documents for the
under mentioned works as per terms and conditions stated below:
Package No. |
Gr No |
Name
of Works |
Tender
security
(Tk.) |
Time
for completion
(days) |
Price
of tender documents (Tk.) |
Important
Rural Infrastructure Development Project on Priority Basis |
|||||
IRIDP/STK/W-34 |
1 |
(a)
Improvement of Bharashimla Nasir House - LSD Godown via Kharhat road by 25mm
dense carpeting at Ch:00-550m With Construction of 1No 0.600mx0.625m U-Type drain culvert at
Ch: 100 on the
same road under
Kaligonj Upazila, Satkhira. (b)
Improvement of Kalibari UZR - Palpara Bazar road by 25mm dense carpeting at
Ch:186m-846m with Construction of 2Nos 0.600mx0.625m U-Type drain culvert at
Ch: 407m & 450m on the
same road under
Kaligonj Upazila, Satkhira. |
75,000.00 |
365
days |
1,000.00 |
IRIDP/STK/W-38 |
2 |
(a)
Improvement of Nazimgonj GC - Powkhali RHD road by 25mm dense carpeting at
Ch: 1600-1820m with Construction of 1 No 0.600mx1.125m Box drain culvert at
Ch:1695m on the same road under Kaligonj Upazila, Satkhira. (b) Improvement of Shitalpur - Gonapati via H/O
Sukur Ali & H/O Mizanur Islam road by 25mm dense carpeting at Ch:00-1075m
with Construction of 4Nos 0.625mx0.600m U-Type drain culvert at Ch:244, 510m,
715m & 1060m on the same road under Kaligonj Upazila, Satkhira. |
1,05,000.00 |
365
days |
2,000.00 |
IRIDP/STK/W-83 |
3 |
(a)
Improvement of Noabanki - Munshigonj - Harinagar - Vetkhali - Jada hat -
Nurnagar-Khanpur ZR road by BC at Ch:24240m-25278m (b) Construction of 2Nos
0.600mx0.900m Drain culvert at Ch:24390m & Ch:24840 on the same road
under Shyamnagar
Upazila, Satkhira. |
1,10,000.00 |
365 days |
2,000.00 |
IRIDP/STK/W-104 |
4 |
Improvement
of Bashtala Bazar - Uzirpur Bazar via
Chandulia & Thalna road by 25mm danse carpeting at Ch: 2000-4000m under
Kaligonj Upazila, Satkhira. |
1,50,000.00 |
365 days |
2,000.00 |
IRIDP/STK/W-105 |
5 |
(a)
Improvement of Jaforpur - Tetulia Bazar via Tetulia Bazar to Borea Assarayan
Project road by 25mm danse carpeting at Ch: 00-2000m (b) Construction of 3
Nos 0.600mx1.125m Box drain culvert at Ch: 30m, 295m & 1735m on the same
road under Kaligonj Upazila, Satkhira. |
1,35,000.00 |
365 days |
2,000.00 |
IRIDP/STK/W-106 |
6 |
Improvement
of Kazla LGED - Sannashirchalk Bazar road by 25mm danse carpeting at Ch:
3204-4694m under Kaligonj Upazila, Satkhira. |
1,10,000.00 |
365 days |
2,000.00 |
IRIDP/STK/W-91 |
7 |
(a)
Improvement of Indronagar More (Issapur) - Kazla Pucca road via Notun Mosque
, Habu Gazi House, Arshad Par House, Indronagar Madrasha & Abul Hossain
House road by 25mm Dense Carpating at Ch: 700m-1300m (b) Construction of 1No
0.625mx0.600m U-Type drain culvert at Ch: 1155m on the same road under
Kaligonj Upazila, Satkhira. |
38,000.00 |
365 days |
750.00 |
IRIDP/STK/W-93 |
8 |
(a)
Improvement of Bichot - Chandbaria
Kheyaghat road by HBB at Ch:2300m-3500m (b) Construction of 1 No
0.600mx0.600m U-Type drain culvert at Ch: 2992m on the same road under
Assasuni Upazila, Satkhira. |
50,000.00 |
365 days |
1,000.00 |
IRIDP/STK/W-107 |
9 |
(a)Improvement
of Loudubi Yasuf house-Icepara road by 25mm Dense carpeting at Ch: 3410-4084m(b)Construction of 2Nos
0.625mx0.600m drain culvert at Ch: 3680m & 3780m of the same road under
Kalaroa Upazila, Satkhira |
50,000.00 |
365 days |
1,000.00 |
IRIDP/STK/W-111 |
10 |
(a)
Improvement of Ghoser Battola Madrasha more - Barali bridge road by 25mm
Dense carpeting at Ch: 00-686m (b) Construction of 1No 0.625mx0.600m drain
culvert at Ch: 500m of the same road under Kalaroa Upazila, Satkhira. |
50,000.00 |
365 days |
1,000.00 |
IRIDP/STK/W-117 |
11 |
Improvement
of Tatuldanga WAPDA to Dalutpur road by HBB at Ch:00-1343m under Sadar
Upazila, Satkhira. |
55,000.00 |
365 days |
1,000.00 |
IRIDP/STK/W-118 |
12 |
Improvement
of Kushkhali Shakri more (FRB)-Kushkhali bazar road by 25mm Dense carpeting
at Ch:00-1535m under Sadar Upazila, Satkhira. |
1,00,000.00 |
365 days |
2,000.00 |
IRIDP/STK/W-119 |
13 |
Improvement
of Baikari Ashlay Member house to Natun Gram road by HBB at Ch:1100-2486m
under Sadar Upazila, Satkhira. |
55,000.00 |
365 days |
1,000.00 |
Contd. Page No-02
Page No-02
Package No. |
Gr No |
Name
of Works |
Tender
security
(Tk.) |
Time
for completion
(days) |
Price
of tender documents (Tk.) |
Improvement of
Bridge/Culvert Approach road Development Project |
|||||
IARP/SAT/10 |
14 |
Construction
of 20.00m RCC Bridge over Kukrali Khal with Approach road near house of Abu
Sakkar at Ch: 1025m under Sadar Upazila, Satkhira. |
65,000.00 |
365 days |
1,000.00 |
IARP/SAT/15 |
15 |
(a)
Construction of 20.00m Bridge Approach & Connecting road at Bezurdanga
School to Bagmari School math road.(b) Construction of (1.5x1.5)m cross drain
at Bezurdanga School to Bagmari School math road. at Ch: 485.50m under Sadar
Upazila, Satkhira. |
1,35,000.00 |
365 days |
2,000.00 |
Rural Infrastructure
Development (Khulna, Bagerhat & Satkhira) Project |
|||||
RIDP(KBS)/UZR-02/ (Incomplete Portion)
/SAT/12 |
16 |
(a)
Improvement of Khanpur Baliadanga GCCR - Uzirpur GC via Gobindokati hat road
by 25mm Dense carpeting at
Ch:9572-10333m (b)Construction of 2Nos 0.600mx1.125m Box drain culvert at
Ch:9722m & 10062m on same road under Kaligonj Upazila, Satkhira. |
85,000.00 |
365 days |
1,000.00 |
RIDP(KBS)/VR(BC)-04/ SAT/12 |
17 |
(a)
Improvement of Puraton Satkhira R&H road - Gobindopur Primary School
(Puraton Satkhira Boddipur Colouni - Gobindopur Khyaghat via Bardal road) by
25mm Dense Carpeting at Ch:3680-4420m (b) Construction of 1Nos 900mmx900mm
U-type drain culvert at Ch: 562 & 4Nos 625mmx600mm U-type drain culvert
at Ch: 291m, 325m , 409m & 928m on the same road under Sadar Upazila, Satkhira. |
65,000.00 |
365 days |
1,000.00 |
RIDP(KBS)/VR (BC)/-06/ SAT/12 |
18 |
(a)
Improvement of Magura - Madra Gushagram (Magura Bazar - Atulia Bazar) road by
25mm Dense carpeting at Ch:3620-4289m (b) Repair of 1No culvert at Ch: 4030m
on same road under Tala Upazila, Satkhira. |
45,000.00 |
365 days |
750.00 |
RIDP(KBS)/UNR(BC)-07/(Incomplete
portion)/Sat.12 |
19 |
(a)
Improvement of Jhawdanga R&H - Narayanpur Bazar via Hazipur road by BC at
Ch:2350-4180m (b) Construction of 2Nos 375mmx450mm U-Type drain culvert at
Ch:2530m, 2860m & 2Nos 625mmx600mm U-Type drain culvert at Ch: 2730m
4040m on the same road under Sadar Upazila, Satkhira. |
75,000.00 |
365 days |
1,000.00 |
RIDP(KBS)/VR(BC)-08/ (Incomplete
portion)/Sat.12 |
20 |
(a)
Improvement of Bansdah UP Office - Kawandanga road (Bhabanipur Pucca road) by
BC at Ch:915-2532m (b) Construction of 3Nos 625mmx600mm U-Type drain culvert
at Ch:1635m, 1795m & 2275m & 2Nos 375mmx450mm U-Type drain culvert at
Ch: 975m 1455m on the same road under Sadar Upazila, Satkhira. |
55,000.00 |
365 days |
1,000.00 |
Rehabilitation of AILA Affected Rural Infrastructure Project |
|||||
RAILA/SRT/W-17 |
21 |
Rehabilitation of
Khazra-Bardal GC road at Ch: 2215-2577m under Assasuni Upazila, Satkhira. |
25000.00 |
365 days |
750.00 |
RAILA/SRT/W-12 |
22 |
Rehabilitation of Khazra UP-Bardal GC road at Ch:00-2010m under
Assasuni Upazila, Satkhira. |
140000.00 |
365
days |
2,000.00 |
2. |
Method of Tender |
: |
OTM |
3. |
Source of Funds |
: |
GOB |
4. |
Date, time and place of pre-tender meeting |
: |
Date: 16th July, 2012, Time:
11.00am and Place: Office of the undersigned |
5. |
Last date, time and places of selling tender documents |
: |
Date: 23th July, 2012, Time: During Office hours Places: Office of the
undersigned/The concern Upazila Engineer, Upazila: Kaligonj, Shyamnagar,
Assasuni, Kalaroa, Sadar & Tala, District: Satkhira/The Executive
Engineer, LGED Khulna/The Deputy Commissioner, Satkhira/The Superintendent of
Police, Satkhira/The Project Director, Improvement of Bridge/Culvert Approach road Development Project/The
Project Director, Rural Infrastructure
Development (Khulna, Bagerhat & Satkhira) Project/The Project Director, Rehabilitation of AILA
Affected Rural Infrastructure Project, LGED Bhaban, Agargaon Sher-E-Bangla Nagar,
Dhaka-1207/The Superintending Engineer, LGED, Khulna Region, Khulna. |
6. |
Last date, time and places of receiving tender |
: |
Date : 24th July 2012, Time: 01.00 pm and Place: Office of the
undersigned/The Upazila Engineer, Upazila: Kaligonj, Shyamnagar, Assasuni,
Kalaroa, Sadar & Tala, District: Satkhira/The Deputy Commissioner,
Satkhira/The Superintendent of Police, Satkhira/The Executive Engineer, LGED
Khulna. |
7. |
Date, time and place of opening of tender |
: |
Date : 24th July 2012, Time: 04.00pm and Place: Office of the undersigned |
Contd. Page No-03
Page No-03
8. |
Tender
shall be valid for a period of 120 days after bid opening and must be
accompanied by the tender security specified above. Interested tenderer may
obtain further information from the office of the undersigned and purchase
the tender documents in cash/treasury chalan/ bank draft from the places
mentioned above. The tenderer or their authorized representatives are allowed
to attend the opening of tenders. The authority reserves the right to accept
or reject any or all the tenders without assigning any reasons whatsoever. This
invitation for tender is available at the web site www.lged.gov.bd |
( Md. Anwarul Islam )
Executive Engineer
Ph: +88047163413
email : xen.satkhira@lged.gov.bd.
Memo No : LGED/XEN/Sat/12/1367/1(100) Dated : 20/06/12
Copy forwarded for kind information & necessary
action to :
01.The
Superintending Engineer, LGED, Khulana
Region, District: Khulna.
02.The Project Director, Important Rural
Infrastructure Development Project on Priority Basis, LGED Bhaban, Agargaon, Dhaka
03.The Project Director, Improvement of Bridge/Culvert Approach road Development Project, LGED
Bhaban, Agargaon Dhaka.
04.The Project Director, Rural Infrastructure
Development (Khulna, Bagerhat & Satkhira) Project, LGED Bhaban, Agargaon,Dhaka.
05.The Project Director, Rehabilitation of AILA
Affected Rural Infrastructure Project, LGED Bhaban, Agargaon, Dhaka.
06.The Deputy Commissioner, District: Satkhira.
07.The Superintendent of Police, District: Satkhira.
08.The Executive Engineer, LGED,
District:_____________________.
09.The
Executive Engineer, RHD /PHE/BWDB, Satkhira.
10.The
Executive Officer, Zilla Parishad/Mayor, Pourashava, Satkhira.
11.The
Upazila Engineer, LGED, Upazila :
..........................,District:
Satkhira.
12.Assistant
Engineer, LGED GIS Unit, Level-4, LGED Bhaban, Agargaon, Dhaka-1207.
He is requested to publish the IFT at the
LGED web site.
13.The
Editor
....................................................................... He is requested to publish the tender notice.
14.Notice
Board (All).
(
K.M.Faruk Hossain)
Senior
Assistant Engineer.
LGED, Satkhira.